Permit 201903195668
2440 16th St
at&t revision to app#201804105931. do not install new emerson power plant, remove 12 extg 90 ah batteries, swap 12 extg 155 ah batteries with 12 nw 180 ah batteries inside extg power plant.
- Outcome
- Completed (city status: complete, Jun 17, 2019)
- Filed
- Mar 19, 2019
- Permit issued
- May 13, 2019
- Final sign-off
- Jun 17, 2019
- Building use
- warehouse,no frnitur
- Neighborhood
- Mission
- Contractor
- Metropolitan Electrical Construction (license 401047)
- Property
- All permits at this address (block 3928, lot 013)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Metropolitan Electrical Construction (license 401047)
- Architect
- Jeffrey Rome, Jeffrey Rome Architecture (license C20876)