# 939 Ellis St

Permit 201903135077. Page: https://www.permitgraph.org/p/201903135077

6th floor: mechanical, electrical and plumbing for 201903114897

- Outcome: Completed (city status: complete, Jan 31, 2020)
- Filed: Mar 13, 2019
- Permit issued: May 23, 2019
- Final sign-off: Jan 31, 2020
- Declared cost: $567,000
- Building use: office
- Neighborhood: Western Addition
- Contractor: [Xl Construction, Corporation](https://www.permitgraph.org/contractor/xl-construction-corporation-647480) (license 647480)
- Property: [All permits at this address](https://www.permitgraph.org/a/0738/019) (block 0738, lot 019)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Xl Construction, Corporation](https://www.permitgraph.org/contractor/xl-construction-corporation-647480) (license 647480)
- Engineer: [Eunice Yoon](https://www.permitgraph.org/professional/eunice-yoon-M16881), Interface Engineering (license M16881)
- Engineer: [Jason Lau](https://www.permitgraph.org/professional/jason-lau-E16806), Interface Engineering (license E16806)
- Pmt consultant/expediter: S Harris (no license listed)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.