Permit 201811024894

650 Potrero Av

construction phase changes to work undeway per 201707273049, 201708023674. add 4 modular workstations

Outcome
Completed (city status: complete, Mar 8, 2019)
Filed
Nov 2, 2018
Permit issued
Nov 19, 2018
Final sign-off
Mar 8, 2019
Declared cost
$5,000
Building use
manufacturing
Neighborhood
Mission
Contractor
Nabi Construction & Engineering Inc (license 792807)
Property
All permits at this address (block 4025, lot 003A)