Permit 201810102722
350 Ellis St
revision to pa 2015-118-2921 for the front wall has been granted as part of main building permit. design of frontwall has been changed per owner's request (esthetics only)
- Outcome
- Completed (city status: complete, May 29, 2019)
- Filed
- Oct 10, 2018
- Permit issued
- Mar 7, 2019
- Final sign-off
- May 29, 2019
- Declared cost
- $150,611
- Building use
- apartments
- Neighborhood
- Tenderloin (how long permits take there)
- Contractor
- D & H Construction (license 693883)
- Property
- All permits at this address (block 0324, lot 023)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- D & H Construction (license 693883)
- Authorized agent
- Diovany Silva (no license listed), applicant