Permit 201808288537

170 Dolores St

replacing existing foundation with new foundation. first, second, and third floor: replacing existing double joist with steel beam. roof: replacing existing wood roof joist with new tji joists. replacing existing lath and plaster with new 5/8 sheetrock.

Outcome
Completed (city status: complete, May 2, 2019)
Filed
Aug 28, 2018
Permit issued
Sep 5, 2018
Final sign-off
May 2, 2019
Declared cost
$20,000
Building use
apartments
Neighborhood
Castro/Upper Market
Contractor
Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
Property
All permits at this address (block 3544, lot 013)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Owner-builder
Owner
Engineer
Harold E. Howell, Mercury Engineering Group (license C17591)