Permit 201807114327
232 Clipper St
erect a new 3 stories, 2 dwelling unit, no basement, type v-b. single family building
- Outcome
- Completed (city status: complete, Apr 6, 2021)
- Filed
- Jul 11, 2018
- Permit issued
- Dec 12, 2018
- Final sign-off
- Apr 6, 2021
- Declared cost
- $750,000
- Building use
- 1 family dwelling
- Neighborhood
- Noe Valley
- Contractor
- Eastwood Development Incorporated (license 959948)
- Property
- All permits at this address (block 6548, lot 009)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Eastwood Development Incorporated (license 959948)
- Architect
- Curtis Hollenbeck, Curtis Hollenbeck Architect (license C24843)