Permit 201806283291
1023 Vallejo St
remove tub shower. replace with closets change door from north wall to south wall. n/a for maher
- Outcome
- Completed (city status: complete, Dec 4, 2018)
- Filed
- Jun 28, 2018
- Permit issued
- Sep 6, 2018
- Final sign-off
- Dec 4, 2018
- Declared cost
- $15,000
- Building use
- 1 family dwelling
- Neighborhood
- Nob Hill
- Contractor
- Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
- Property
- All permits at this address (block 0150, lot 041)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Owner-builder
- Owner Builder