# 538 Eddy St

Permit 201805098599. Page: https://www.permitgraph.org/p/201805098599

exterior gfrc rainscreen cladding. ref pa 2015-1123-3360

- Outcome: Completed (city status: complete, May 24, 2018)
- Filed: May 9, 2018
- Permit issued: May 14, 2018
- Final sign-off: May 24, 2018
- Declared cost: $375,000
- Building use: power plant
- Neighborhood: Tenderloin
- Contractor: [Plant Construction Co, Lp](https://www.permitgraph.org/contractor/plant-construction-co-lp-995375) (license 995375)
- Property: [All permits at this address](https://www.permitgraph.org/a/0335/002D) (block 0335, lot 002D)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Plant Construction Co, Lp](https://www.permitgraph.org/contractor/plant-construction-co-lp-995375) (license 995375)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/p/201805098599.