Permit 201804186707
726 Fillmore St
revision to permit 2018-0112-8575 update match existing conditions and shearwall lenght along north side revised
- Outcome
- Completed (city status: complete, Mar 12, 2019)
- Filed
- Apr 18, 2018
- Permit issued
- Apr 19, 2018
- Final sign-off
- Mar 12, 2019
- Building use
- apartments
- Neighborhood
- Hayes Valley
- Contractor
- Us Construction California, Inc (license 1031451)
- Property
- All permits at this address (block 0804, lot 018)