# 833 Mission St

Permit 201803284808. Page: https://www.permitgraph.org/p/201803284808

electrical works associated with the replacement of parking access & revenue control systems (parcs) equipment for the garage, parcs equipments are not part of this permit application.

- Outcome: Never finaled (city status: issued, Oct 18, 2019)
- Filed: Mar 28, 2018
- Permit issued: Oct 18, 2019
- Declared cost: $1,411,550
- Building use: prkng garage/public
- Neighborhood: South of Market
- Contractor: [Mark Scott Construction Inc](https://www.permitgraph.org/contractor/mark-scott-construction-inc-682814) (license 682814)
- Property: [All permits at this address](https://www.permitgraph.org/a/3724/067) (block 3724, lot 067)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Mark Scott Construction Inc](https://www.permitgraph.org/contractor/mark-scott-construction-inc-682814) (license 682814)
- Engineer: [Daniel Castro](https://www.permitgraph.org/professional/daniel-castro-E21019), Engineering 350 (license E21019)
- Engineer: [David C Koski](https://www.permitgraph.org/professional/david-c-koski-C27622) (license C27622)
- Authorized agent: Nick Deanda, Mark Scott Construction Inc (no license listed)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.