Permit 201709158442
149 Castro St
soft story retrofit per sfebc chapter 4d engineering criteria 2016 cebc appendix a4
- Outcome
- Completed (city status: complete, Jun 9, 2021)
- Filed
- Sep 15, 2017
- Permit issued
- Aug 26, 2020
- Final sign-off
- Jun 9, 2021
- Declared cost
- $80,000
- Building use
- apartments
- Neighborhood
- Castro/Upper Market
- Contractor
- Pjd Construction Inc (license 1007052)
- Property
- All permits at this address (block 3540, lot 066)