Permit 201708256010
800 Duboce Av
soft story retrofit per sfebc sfebc chapter 4d: 2016 ceb appendix a-4
- Outcome
- Completed (city status: complete, Apr 11, 2018)
- Filed
- Aug 25, 2017
- Permit issued
- Aug 30, 2017
- Final sign-off
- Apr 11, 2018
- Declared cost
- $120,000
- Building use
- apartments
- Neighborhood
- Haight Ashbury
- Contractor
- Nabi Construction & Engineering Inc (license 792807)
- Property
- All permits at this address (block 1259, lot 013)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Nabi Construction & Engineering Inc (license 792807)