Permit GraphShortlistSan Francisco building permits since 2000

Permit 201708154867

219 Steiner St

upgrade plumbing & electrical in laundry area. install new furnace, open wall in laundry to insulate & patch back in kind.

Outcome
Completed (city status: complete, Nov 17, 2017)
Filed
Aug 15, 2017
Permit issued
Aug 15, 2017
Final sign-off
Nov 17, 2017
Declared cost
$30,000
Building use
apartments
Neighborhood
Haight Ashbury
Contractor
Clipper Construction Inc. (license 723585)
Property
All permits at this address (block 0861, lot 043)

Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

Contractor
Clipper Construction Inc. (license 723585), applicant