# 185 Berry St

Permit 201708114561. Page: https://www.permitgraph.org/p/201708114561

suite 1510 installation of 4 2x2 type f6 fixtures, add in switch locations, rough in of 2 teledata outlets. ref app#201706219952 n/a for maher

- Outcome: Completed (city status: complete, Jan 12, 2018)
- Filed: Aug 11, 2017
- Permit issued: Aug 11, 2017
- Final sign-off: Jan 12, 2018
- Declared cost: $6,000
- Building use: office
- Neighborhood: Mission Bay
- Contractor: [Paganini Electric Corp(See Signatories)](https://www.permitgraph.org/contractor/paganini-electric-corp-see-signatories-309677) (license 309677)
- Property: [All permits at this address](https://www.permitgraph.org/a/3803/005) (block 3803, lot 005)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Paganini Electric Corp(See Signatories)](https://www.permitgraph.org/contractor/paganini-electric-corp-see-signatories-309677) (license 309677), applicant

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/p/201708114561.