225 Hartford St
install 4" slab-on-grade at (e) basement space with #3 bar @ 12" o.c. each way
- Outcome
- Completed (city status: complete, Jun 19, 2017)
- Filed
- Feb 17, 2017
- Permit issued
- Feb 24, 2017
- Final sign-off
- Jun 19, 2017
- Declared cost
- $8,000
- Building use
- apartments
- Neighborhood
- Castro/Upper Market
- Contractor
- Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
- Property
- All permits at this address (block 3602, lot 036)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Owner-builder
- Owner, applicant
- Architect
- K Martin (license C23258)