143 San Jose Av
add new bathroom at basement, 1st, 2nd and 3rd floors, remove and replace damaged roof rafter. strengthening 1st fl framing.
- Outcome
- Completed (city status: complete, Sep 6, 2018)
- Filed
- Dec 20, 2016
- Permit issued
- Feb 7, 2017
- Final sign-off
- Sep 6, 2018
- Declared cost
- $250,000
- Building use
- apartments
- Neighborhood
- Mission
- Contractor
- Kashaneh Construction (license 874124)
- Project type
- Bathroom remodel
- Property
- All permits at this address (block 3644, lot 015)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Kashaneh Construction (license 874124), applicant
- Engineer
- Amir Shahmirza, Asi Consulting Engineers (license C042941)