Permit 201603152045
1250 Sacramento St
soft story retrofit per sfbc chapter 34b engineering criteria: 2012 iebc appendix a-4. soft story of wood frame building. maher na
- Outcome
- Completed (city status: complete, Aug 9, 2017)
- Filed
- Mar 15, 2016
- Permit issued
- Nov 29, 2016
- Final sign-off
- Aug 9, 2017
- Declared cost
- $125,000
- Building use
- apartments
- Neighborhood
- Nob Hill (how long permits take there)
- Contractor
- Rosconn Construction (license 552004)
- Property
- All permits at this address (block 0221, lot 004C)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Owner-builder
- Owner Builder
- Contractor
- Rosconn Construction (license 552004)