# 185 Berry St

Permit 201509258063. Page: https://www.permitgraph.org/p/201509258063

#6850 - china basin on 6th floor - construct of new partitions and minor mechanical, electrical, plumbing, fire alarm work and fire sprinkler. mep and fire alarm are to be submitted under separate permit. n/a ordinance #155-13

- Outcome: Completed (city status: complete, Jul 22, 2016)
- Filed: Sep 25, 2015
- Permit issued: Oct 5, 2015
- Final sign-off: Jul 22, 2016
- Declared cost: $754,859
- Building use: office
- Neighborhood: Mission Bay
- Contractor: [Rossi Builders Inc.](https://www.permitgraph.org/contractor/rossi-builders-inc-229568) (license 229568)
- Property: [All permits at this address](https://www.permitgraph.org/a/3803/005) (block 3803, lot 005)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Rossi Builders Inc.](https://www.permitgraph.org/contractor/rossi-builders-inc-229568) (license 229568), applicant
- Architect: [Peter Noone](https://www.permitgraph.org/professional/peter-noone-C31296), Solomon Cordwell Buenz (license C31296)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.