Permit 201506128852
266 Dolores St
retrofit target soft story per planning dept requirements for seismic reinforcement.include tie downs, anchor bolts,sheerwall & new foundation grade beams where needed; infill 3 windows; soft story retrofit per sfbc 34b, engineering criteria used:(other rational design)
- Outcome
- Completed (city status: complete, Apr 17, 2017)
- Filed
- Jun 12, 2015
- Permit issued
- Nov 1, 2016
- Final sign-off
- Apr 17, 2017
- Declared cost
- $40,000
- Building use
- apartments
- Neighborhood
- Castro/Upper Market
- Contractor
- G M M Construction Co (license 591208)
- Property
- All permits at this address (block 3557, lot 009B)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- G M M Construction Co (license 591208)
- Engineer
- Tsa (no license listed)