Permit 201502259342
1101 Fillmore St
revision to app#201309247627. not adding new dc power plant and not removing and replacing extg bbs 2000 cabinet.
- Outcome
- Completed (city status: complete, Mar 17, 2015)
- Filed
- Feb 25, 2015
- Permit issued
- Mar 6, 2015
- Final sign-off
- Mar 17, 2015
- Building use
- retail sales
- Neighborhood
- Western Addition (how long permits take there)
- Contractor
- Triton Tower Inc (license 794622)
- Property
- All permits at this address (block 0755, lot 002)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Triton Tower Inc (license 794622)
- Engineer
- James Spore, Streamline Engineering (license S6336)
- Lessee
- Att Mobility (no license listed)