# 665 03rd St

Permit 201405307063. Page: https://www.permitgraph.org/p/201405307063

replacement of ground floor window sash along 3rd st elevation. replace 2 entry doors. ** maher: compliance with ordinance no# 155-13 not required **

- Outcome: Completed (city status: complete, Sep 7, 2016)
- Filed: May 30, 2014
- Permit issued: Apr 9, 2015
- Final sign-off: Sep 7, 2016
- Declared cost: $300,000
- Building use: office
- Neighborhood: Financial District/South Beach
- Contractor: [Team Commercial Construction Inc.](https://www.permitgraph.org/contractor/team-commercial-construction-inc-735561) (license 735561)
- Property: [All permits at this address](https://www.permitgraph.org/a/3788/041) (block 3788, lot 041)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Team Commercial Construction Inc.](https://www.permitgraph.org/contractor/team-commercial-construction-inc-735561) (license 735561)
- Architect: [Naomi Miroglio](https://www.permitgraph.org/professional/naomi-miroglio-22990), Archtectural Resources Group (license 22990)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.