1670 Hayes St
soft story retrofiting 4 garage portals in the ground floor steel strong walls (2) and a header to be connected to floor joists. foundation under walls to be enlarge. soft story retrofit per sfbc 34b. engineering criteria sfbc 2013.
- Outcome
- Completed (city status: complete, Sep 22, 2014)
- Filed
- Mar 21, 2014
- Permit issued
- Mar 25, 2014
- Final sign-off
- Sep 22, 2014
- Declared cost
- $35,000
- Building use
- apartments
- Neighborhood
- Lone Mountain/USF
- Contractor
- Owner-builder: the owner is listed as the builder, so no contractor is ranked for this permit
- Property
- All permits at this address (block 1198, lot 018)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Owner-builder
- Owner Builder
- Engineer
- Muthanna Omran (no license listed)