# 225 Bush St

Permit 201311010901. Page: https://www.permitgraph.org/p/201311010901

13th floor: relocate 22 pendent sprinkler heads on the 13th floor. relocate 16 upright sprinkler, upgrade end of line bracing. ti pa# 201310038355

- Outcome: Completed (city status: complete, Nov 26, 2013)
- Filed: Nov 1, 2013
- Permit issued: Nov 1, 2013
- Final sign-off: Nov 26, 2013
- Declared cost: $19,570
- Building use: office
- Neighborhood: Financial District/South Beach
- Contractor: [Golden Gate Fire Protection Inc](https://www.permitgraph.org/contractor/golden-gate-fire-protection-inc-960198) (license 960198)
- Property: [All permits at this address](https://www.permitgraph.org/a/0289/007) (block 0289, lot 007)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Golden Gate Fire Protection Inc](https://www.permitgraph.org/contractor/golden-gate-fire-protection-inc-960198) (license 960198), applicant

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/p/201311010901.