Permit 201302210637
330 Sanchez St
retrofit- instlal anchor bolts @4" sparing in e. foundations, 5/8" thr. epoxy set 8" inbed w/3"x 1/2" washers install plywood stffeing panels on accessible bsmt walls 1/2 cdx stri edges blocked & nailed 10 @3" (all voluntary work)
- Outcome
- Completed (city status: complete, Mar 25, 2013)
- Filed
- Feb 21, 2013
- Permit issued
- Feb 21, 2013
- Final sign-off
- Mar 25, 2013
- Declared cost
- $15,000
- Building use
- apartments
- Neighborhood
- Castro/Upper Market
- Contractor
- Kelton Construction (license 324498)
- Property
- All permits at this address (block 3564, lot 007)
Everyone on the permit
The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.
- Contractor
- Kelton Construction (license 324498), applicant