the (e) elevator hoistway on the 2nd, 3rd, 4th and 5th floor of the wharfside bldg nare not separated from the circulation corridors on each floor by an elevator lobby. install a new smoke curtain at each of these existing elevator hoistway as permitted by section 708.14.1 exception 8 life safety,

- Outcome: Completed (city status: complete, Feb 5, 2013)
- Filed: Sep 24, 2012
- Permit issued: Oct 12, 2012
- Final sign-off: Feb 5, 2013
- Declared cost: $30,000
- Building use: office
- Neighborhood: Mission Bay
- Contractor: [Turner Construction Co](https://www.permitgraph.org/contractor/turner-construction-co-210639) (license 210639)
- Property: [All permits at this address](https://www.permitgraph.org/a/3803/001) (block 3803, lot 001)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Turner Construction Co](https://www.permitgraph.org/contractor/turner-construction-co-210639) (license 210639), applicant

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.