66 08th St

repair former vent shaft on the exterior of 8th st side of substation, replace exisitng lights. exterior work only.

Outcome
Completed (city status: complete, Dec 4, 2013)
Filed
Aug 9, 2012
Permit issued
Aug 10, 2012
Final sign-off
Dec 4, 2013
Declared cost
$400,000
Building use
power plant
Neighborhood
South of Market
Contractor
Paradigm General Contractors (license 608135)
Property