Permit 201205110316. Page: https://www.permitgraph.org/p/201205110316

break out existing walkways & hardslape; install shoring; excavate 3 ft bgs; partial backfill; excavate 2nd area using sloping to total depth of 5 ft bgs; backfill to initial conditions.

- Outcome: Completed (city status: complete, Aug 8, 2013)
- Filed: May 11, 2012
- Permit issued: Jul 11, 2012
- Final sign-off: Aug 8, 2013
- Declared cost: $50,000
- Neighborhood: Marina
- Contractor: [Haley & Aldrich Inc](https://www.permitgraph.org/contractor/haley-aldrich-inc-955096) (license 955096)
- Property: [All permits at this address](https://www.permitgraph.org/a/0463A/008) (block 0463A, lot 008)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Haley & Aldrich Inc](https://www.permitgraph.org/contractor/haley-aldrich-inc-955096) (license 955096)
- Engineer: [Dean H. Iwasa](https://www.permitgraph.org/professional/dean-h-iwasa-GE2285) (license GE2285)
- Lessee: Sol Varon (no license listed)

---