# 1080 Post St

Permit 201203075524. Page: https://www.permitgraph.org/p/201203075524

structural strenthening. 1. parapet bracing 2. brace tanks 3. brace steps 4. remove (e) brick non-bearing fire wall and door at boiler room and replace with 2-hr metal stud gypboard wall with 1-hr door.

- Outcome: Completed (city status: complete, Jul 11, 2012)
- Filed: Mar 7, 2012
- Permit issued: Apr 20, 2012
- Final sign-off: Jul 11, 2012
- Declared cost: $60,000
- Building use: apartments
- Neighborhood: Nob Hill
- Contractor: [Sincere Construction Company Inc](https://www.permitgraph.org/contractor/sincere-construction-company-inc-557739) (license 557739)
- Property: [All permits at this address](https://www.permitgraph.org/a/0692/011) (block 0692, lot 011)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Sincere Construction Company Inc](https://www.permitgraph.org/contractor/sincere-construction-company-inc-557739) (license 557739), applicant

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 23 November 2026.
This is the text of https://www.permitgraph.org/p/201203075524.