# 3300 Cesar Chavez St

Permit 200907092322. Page: https://www.permitgraph.org/p/200907092322

existing clean air separator ( cas) / enhanced vapor recovery ( epr) installed to comply with sffd violation # 5349 by adding rated enclosure and bollards per cfc 312.2 # 5 and cfc 312.2 #2.

- Outcome: Completed (city status: complete, Aug 21, 2009)
- Filed: Jul 9, 2009
- Permit issued: Jul 20, 2009
- Final sign-off: Aug 21, 2009
- Declared cost: $33,000
- Building use: filling/service stn
- Neighborhood: Mission
- Contractor: [Walton Engineering Inc.](https://www.permitgraph.org/contractor/walton-engineering-inc-617238) (license 617238)
- Property: [All permits at this address](https://www.permitgraph.org/a/6571/011) (block 6571, lot 011)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Walton Engineering Inc.](https://www.permitgraph.org/contractor/walton-engineering-inc-617238) (license 617238)
- Authorized agent: Keith Mclean, Mclean Construction Consulting (no license listed), applicant

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/p/200907092322.