# 1 Maritime Pz

Permit 200802013826. Page: https://www.permitgraph.org/p/200802013826

26th floor: retrofit existing open loop condensen water system to closed loop - install mech equip on mech room, (2) plate/frame heat exchanger, (2) close loop condenser pumps, flush and clean system.

- Outcome: Expired or cancelled (city status: expired, May 25, 2011)
- Filed: Feb 1, 2008
- Permit issued: Feb 29, 2008
- Declared cost: $250,000
- Building use: office
- Neighborhood: Financial District/South Beach
- Contractor: [Western Allied Mechanical Inc.](https://www.permitgraph.org/contractor/western-allied-mechanical-inc-826782) (license 826782)
- Property: [All permits at this address](https://www.permitgraph.org/a/0204/021) (block 0204, lot 021)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Western Allied Mechanical Inc.](https://www.permitgraph.org/contractor/western-allied-mechanical-inc-826782) (license 826782), applicant

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 23 November 2026.