# 100 Pine St

Permit 200801313661. Page: https://www.permitgraph.org/p/200801313661

9th floor; selective demolition, new construction of walls, doors, frames, electrical work, minor changes to lighting. mech hvac, sprinklers, etc. will be submitted under separate permit.

- Outcome: Completed (city status: complete, Apr 7, 2008)
- Filed: Jan 31, 2008
- Permit issued: Feb 14, 2008
- Final sign-off: Apr 7, 2008
- Declared cost: $275,000
- Building use: office
- Neighborhood: Financial District/South Beach
- Contractor: [Team Commercial Construction Inc.](https://www.permitgraph.org/contractor/team-commercial-construction-inc-735561) (license 735561)
- Property: [All permits at this address](https://www.permitgraph.org/a/0262/020) (block 0262, lot 020)

## Everyone on the permit

The parties and license numbers written on the permit, as the city lists them; not a check with any state board. The person who paid the fee and the project contact are not shown.

- Contractor: [Team Commercial Construction Inc.](https://www.permitgraph.org/contractor/team-commercial-construction-inc-735561) (license 735561)
- Architect: [Carlo Gelardi](https://www.permitgraph.org/professional/carlo-gelardi-C19330) (license C19330)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/p/200801313661.