Permit 200008117712
167 Hartford St
remove unsafe, old in-law unit. remove & properly cap/terminate. unit is on ground fl,behind garage
- Outcome
- Completed (city status: complete, Mar 23, 2001)
- Filed
- Aug 11, 2000
- Permit issued
- Aug 25, 2000
- Final sign-off
- Mar 23, 2001
- Declared cost
- $2,000
- Building use
- 1 family dwelling
- Neighborhood
- Castro/Upper Market
- Contractor
- Brayer Construction & Design (license 729726)
- Property
- All permits at this address (block 3583, lot 025)