# Teamwrkx Inc.

Contractor license 841440. San Francisco building permit record since 2000.

- Page: https://www.permitgraph.org/contractor/teamwrkx-inc-841440
- JSON: https://www.permitgraph.org/api/contractor?license=841440
- State license record: https://www.cslb.ca.gov/onlineservices/checklicenseII/LicenseDetail.aspx?LicNum=841440

66 permits since 2000: 53 completed, 11 never finaled, 2 expired or cancelled. Typically 7 days from filing to permit and 91 days from permit to final inspection. Of the 11 never-finaled permits, 11 are over 10 years old.

- Based in: San Jose
- On San Francisco permits: Jun 2006 to Jan 2016
- Last 24 months: 0 permits filed

This is the city's permit record, not a license check. It does not show whether the state license is active, bonded or insured.

## Permits filed each year

| Year | Completed | In progress | Never finaled | Expired or cancelled |
| --- | --- | --- | --- | --- |
| 2006 | 3 | 0 | 1 | 0 |
| 2007 | 11 | 0 | 1 | 0 |
| 2008 | 4 | 0 | 0 | 2 |
| 2009 | 2 | 0 | 0 | 0 |
| 2010 | 3 | 0 | 0 | 0 |
| 2011 | 5 | 0 | 3 | 0 |
| 2012 | 5 | 0 | 1 | 0 |
| 2013 | 4 | 0 | 5 | 0 |
| 2014 | 7 | 0 | 0 | 0 |
| 2015 | 7 | 0 | 0 | 0 |
| 2016 | 2 | 0 | 0 | 0 |

## By project type

| Project type | Permits | Completed | In progress | Never finaled | Expired or cancelled | Typical days to permit | Typical days to final |
| --- | --- | --- | --- | --- | --- | --- | --- |
| Kitchen remodel | 1 | 1 | 0 | 0 | 0 | 12 | 34 |
| Stairs | 2 | 1 | 0 | 0 | 1 | 2 | 49 |

## Most recent permits

| Permit | Filed | Outcome | Address | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- |
| [201601197369](https://www.permitgraph.org/p/201601197369) | Jan 19, 2016 | Completed: final sign-off Apr 2016 | [55 Francisco St](https://www.permitgraph.org/a/0056/007) | 7th flr: barrier removal project for restroom ada (disabled access) and new finishes/fixtures; maher n/a | $137,000 |
| [201601197370](https://www.permitgraph.org/p/201601197370) | Jan 19, 2016 | Completed: final sign-off Apr 2016 | [55 Francisco St](https://www.permitgraph.org/a/0056/007) | 6th flr: barrier removal. project for restroom. ada upgrades (disabled access upgrades) and (n) finishes/fixtures.; maher n/a | $137,000 |
| [201511193077](https://www.permitgraph.org/p/201511193077) | Nov 19, 2015 | Completed: final sign-off Jan 2016 | [499 Illinois St](https://www.permitgraph.org/a/3940/004) | 3rd floor: scope of work includes t.i. in an extg 6 story bldg. including relocation of an extg door and infill at demo area and associated finishes. work also includes mechanical and electrical impr… | $60,000 |
| [201510230638](https://www.permitgraph.org/p/201510230638) | Oct 23, 2015 | Completed: final sign-off Feb 2016 | [4406 18th St](https://www.permitgraph.org/a/2650/016) | revision to 201506128888 and app#201406279797. change per sfdph mandated exhaust fan. remove extg sink and install new sink using extg plumbing. | $4,500 |
| [201506048157](https://www.permitgraph.org/p/201506048157) | Jun 4, 2015 | Completed: final sign-off Feb 2016 | [55 Francisco St](https://www.permitgraph.org/a/0056/007) | new ceiling height partitions, power/data, millwork, doors, frames, hardware and finishes throughout. new ada showers in scope as well. n/a for maher. | $279,504 |
| [201505206817](https://www.permitgraph.org/p/201505206817) | May 20, 2015 | Completed: final sign-off Dec 2015 | [201 Spear St](https://www.permitgraph.org/a/3741/032) | 10/f: revision to 201504032758. interior remodel, new walls, doors, glass partitions, walls and floor finishes, ceiling. sprinklers, fire alarm, mech & elec on sep permit. compliance with maher ordin… | $14,500 |
| [201504032758](https://www.permitgraph.org/p/201504032758) | Apr 3, 2015 | Completed: final sign-off Dec 2015 | [201 Spear St](https://www.permitgraph.org/a/3741/032) | revision to 201410158952. interior wall reconfiguration. mech, electrical under sep permit. |  |
| [201504032756](https://www.permitgraph.org/p/201504032756) | Apr 3, 2015 | Completed: final sign-off Nov 2017 | [201 Spear St](https://www.permitgraph.org/a/3741/032) | tenant improvement 13th fl demo of e offices, conference rooms. installation of millwork and fixtures and finishes. new walls and doors. ceiling to remain existing, new and relocate lights. elec and… | $124,088 |
| [201501216280](https://www.permitgraph.org/p/201501216280) | Jan 21, 2015 | Completed: final sign-off Nov 2017 | [201 Spear St](https://www.permitgraph.org/a/3741/032) | revision to 201410158954. partial demo of offices, installation of new millwork, new finishes throughout space, floor and walls, ada upgrade at restrooms. mech, elec, plumbing sep permit | $51,556 |
| [201412224255](https://www.permitgraph.org/p/201412224255) | Dec 22, 2014 | Completed: final sign-off Feb 2016 | [55 Francisco St](https://www.permitgraph.org/a/0056/008) | 3rd fl: barrier removal for restroom. ada upgrade and new finishes/fixtures. maher not req | $97,903 |
| [201412224254](https://www.permitgraph.org/p/201412224254) | Dec 22, 2014 | Completed: final sign-off Feb 2016 | [55 Francisco St](https://www.permitgraph.org/a/0056/008) | 1st fl barrier removal for restroom. ada upgrade and new finishes/fixtures. compliance with maher ordinance no 155-13. | $66,570 |
| [201411191873](https://www.permitgraph.org/p/201411191873) | Nov 19, 2014 | Completed: final sign-off Nov 2017 | [201 Spear St](https://www.permitgraph.org/a/3741/032) | install new led 2x4 fixtures throughout the 10th fl and partial parts of the 12th fl. install dimmable led pendent and downlights. add power to conference rooms and offices for this spec site | $260,000 |
| [201410158954](https://www.permitgraph.org/p/201410158954) | Oct 15, 2014 | Completed: final sign-off Feb 2018 | [201 Spear St](https://www.permitgraph.org/a/3741/032) | 12th flr: ab-017 no occupancy. minor tenant improvement includes: demolition of offices & remodel of break room & floor covering, install new millwork & finishes (mech & elec under separate permit) m… | $95,500 |
| [201410158952](https://www.permitgraph.org/p/201410158952) | Oct 15, 2014 | Completed: final sign-off Nov 2017 | [201 Spear St](https://www.permitgraph.org/a/3741/032) | 10th flr: tenant improvement include corridors, wall, & new partitions, doors & ceiling & lighting, restrooms upgrade & elevator lobby of 10th flr, mech & elec under separate permit; maher n/a | $500,000 |
| [201409237016](https://www.permitgraph.org/p/201409237016) | Sep 23, 2014 | Completed: final sign-off Oct 2014 | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | demolition of partitons, millwork and associated electrical and plumbing and ceiling work. space is currently unoccupied. path of travel not required per ab-017 | $20,000 |
| [201408214419](https://www.permitgraph.org/p/201408214419) | Aug 21, 2014 | Completed: final sign-off Sep 2014 | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | 9th floor - project consist demolition of select partitoin, millwork, & associated electrical, plumbing & ceiling. construction of one conference room & one office. the spac eis currently unoccupied.… | $95,000 |
| [201308295595](https://www.permitgraph.org/p/201308295595) | Aug 29, 2013 | Never finaled: issued Sep 2013, no final | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | 4/f- t.i. from shell condition including non-load bearing partitions, doors, frames, interior glazing, casework, lighting, oiling grid, mech, electrical, plumbing included. life safety & sprinkler to… | $1,188,550 |
| [201306058693](https://www.permitgraph.org/p/201306058693) | Jun 5, 2013 | Never finaled: issued Jun 2013, no final | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | new electrical and reowrk hvac 16th fl ref 201305207413 | $42,000 |
| [201305308247](https://www.permitgraph.org/p/201305308247) | May 30, 2013 | Completed: final sign-off Aug 2013 | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | suite 1150: ti to e suite 1150 for new wall (non load bearing) new doors and glazing, new elec, relocate lighting, e ceiling, hvac and life safety to be modified by d/b contractor under separate perm… | $366,000 |
| [201305247889](https://www.permitgraph.org/p/201305247889) | May 24, 2013 | Completed: final sign-off Aug 2013 | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | the 18th floor upgrades rest room that involves barrier removal full accessible compliance. work involves demolition of fixture and installation of new accessible toilet partitions, accessories, fixt… | $25,000 |
| [201305207413](https://www.permitgraph.org/p/201305207413) | May 20, 2013 | Never finaled: issued May 2013, no final | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | 16th floor suite 1600 - tenant improvement to include demolition, new partitions, new ceiling tiles, new millwork & new finishes throughout. mep, sprinklers and fire alarm. core of building is under… | $281,000 |
| [201305207300](https://www.permitgraph.org/p/201305207300) | May 20, 2013 | Never finaled: issued May 2013, no final | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | build multi tenant corridor incl. walls, doors, frames , lighting, finishes. elec, mech, fire life safety to be design/build and submitted seperately. | $120,000 |
| [201305096491](https://www.permitgraph.org/p/201305096491) | May 9, 2013 | Never finaled: issued Jan 2014, no final | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | hc accessible stall striping and signage on pkg level 2. | $2,500 |
| [201303283268](https://www.permitgraph.org/p/201303283268) | Mar 28, 2013 | Completed: final sign-off Apr 2013 | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | 17/f: remodeling of extg office suite. | $14,800 |
| [201302271092](https://www.permitgraph.org/p/201302271092) | Feb 27, 2013 | Completed: final sign-off Aug 2013 | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | suite # 1400:this project involves modification of extg t.i. space to spec suite condition, including selective demolition and construction of non load bearing partitions, new suspended ceiling grid… | $127,518 |
| [201212055494](https://www.permitgraph.org/p/201212055494) | Dec 5, 2012 | Completed: final sign-off Feb 2013 | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | remove wall, lights, and tile. build 2 new offices, telephone closet and conference room. new lights, ceiling tile, carpet, paint. rework existing plumbing. mep under separate permit. | $150,000 |
| [201208066598](https://www.permitgraph.org/p/201208066598) | Aug 6, 2012 | Completed: final sign-off Oct 2012 | [601 California St](https://www.permitgraph.org/a/0258/032) | 6th floor:demolition of partitions power & tel/data, millwork, finishes,new partitions, doors/frames, relocate light fixtures, new sink location. | $90,000 |
| [201203276924](https://www.permitgraph.org/p/201203276924) | Mar 27, 2012 | Completed: final sign-off May 2012 | [601 California St](https://www.permitgraph.org/a/0258/032) | 12th floor:demolition of partitions, power and tele data, new millwork finishes and door and frames. new non-structural partitions, doors and frames, millwork tele-data power, new dishwasher,light re… | $90,000 |
| [201203276986](https://www.permitgraph.org/p/201203276986) | Mar 27, 2012 | Completed: final sign-off May 2012 | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | minor tenant improvement to build 1 corner office,replace countertop, new outlets (220 sf) including doors, frames, glazing. elec,mech sep permit. new lighting and fire alarm separate permit. tenant… | $66,374 |
| [201203196390](https://www.permitgraph.org/p/201203196390) | Mar 19, 2012 | Completed: final sign-off Apr 2012 | [225 Bush St](https://www.permitgraph.org/a/0289/007) | 11th floor demolition of some non-structural partitions & finishes. new partitions, glazing & doors. mech/elec to be submitted under spearate permit. | $150,000 |
| [201201091872](https://www.permitgraph.org/p/201201091872) | Jan 9, 2012 | Never finaled: issued Feb 2012, no final | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | 19th floor #1910 demo existing walls & build demising wall, install ceiling grid where needed, fire sprinkler, life safety alarm work will be under separate permit. | $56,000 |
| [201112221156](https://www.permitgraph.org/p/201112221156) | Dec 22, 2011 | Completed: final sign-off Feb 2012 | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | unit#1720:demo ceiling and walls. build offices, kitchen and conference rooms. fire, sprinkler alarm work under separate permit. | $120,000 |
| [201110066271](https://www.permitgraph.org/p/201110066271) | Oct 6, 2011 | Completed: final sign-off Dec 2011 | [601 California St](https://www.permitgraph.org/a/0258/032) | 15th floor-combine 2 suites into 1 suite-demo of office partitons, doors, teledata, receptacles & finishes. new partitions, doors, ceiling & finishes. no restroom work. 2 required exits shall be main… | $85,000 |
| [201106077571](https://www.permitgraph.org/p/201106077571) | Jun 7, 2011 | Never finaled: issued Jun 2011, no final | [1270 Sanchez St](https://www.permitgraph.org/a/6553/001) | revision to 200812098151, new pier and grade beam foundation for steel momement frame | $2,500 |
| [201105065510](https://www.permitgraph.org/p/201105065510) | May 6, 2011 | Completed: final sign-off Jul 2011 | [601 California St](https://www.permitgraph.org/a/0258/032) | project consists of demolition of partitions, power & tele data, millwork, finishes and doors/frames. construction ofnew partitions door/frames, millwork, finishes, power and tele/data. space is curr… | $120,000 |
| [201105065508](https://www.permitgraph.org/p/201105065508) | May 6, 2011 | Completed: final sign-off Jul 2011 | [601 California St](https://www.permitgraph.org/a/0258/032) | project consists of demolition of partitions, power & tele data, millwork, finishes and doors/frames. construction ofnew partitions door/frames, millwork, finishes, power and tele/data. space is curr… | $61,200 |
| [201104194359](https://www.permitgraph.org/p/201104194359) | Apr 19, 2011 | Completed: final sign-off Feb 2012 | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | 17th floor-demo walls, ceiling tiles & carpet. space to remain vacant per ab-017 | $1,200 |
| [201104194356](https://www.permitgraph.org/p/201104194356) | Apr 19, 2011 | Never finaled: issued Apr 2011, no final | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | 18th floor-demo walls, ceiling tiles & carpet. space to remain vacant per ab-017 | $7,000 |
| [201104194360](https://www.permitgraph.org/p/201104194360) | Apr 19, 2011 | Never finaled: issued Apr 2011, no final | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | 11th floor-demo walls, ceiling tiles & carpet. space to remain vacant per ab-017 | $5,000 |
| [201012166855](https://www.permitgraph.org/p/201012166855) | Dec 16, 2010 | Completed: final sign-off Apr 2011 | [225 Bush St](https://www.permitgraph.org/a/0289/007) | demolition of existing non structural partitions outlets and ceiling panels. consturction of new interior partition, power and data, relocation of lights and finishes | $88,000 |
| [201005061923](https://www.permitgraph.org/p/201005061923) | May 6, 2010 | Completed: final sign-off Feb 2011 | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | 17th floor-this project includes demolition of (e) suite #1700 & construction of new offices & support spaces. mep under separate permit. | $440,262 |
| [201002096173](https://www.permitgraph.org/p/201002096173) | Feb 9, 2010 | Completed: final sign-off Aug 2010 | [601 California St](https://www.permitgraph.org/a/0258/032) | 2nd floor-demo walls, carpet & vct. build corridor & offices. rework hvac, replace lights & relocate plumbing | $125,000 |
| [200905158490](https://www.permitgraph.org/p/200905158490) | May 15, 2009 | Completed: final sign-off Jul 2009 | [2750 Van Ness Av](https://www.permitgraph.org/a/0502/005G) | 2nd floor-demolition of (e) finishes & non-structural partitions. install new finishes, non-structural walls, upgrade of restrooms includes electrical, mechanical & plumbing | $96,626 |
| [200903204505](https://www.permitgraph.org/p/200903204505) | Mar 20, 2009 | Completed: final sign-off Oct 2009 | [909 Montgomery St](https://www.permitgraph.org/a/0163/005) | renew pa# 2006/01/11/1921 to obtain final inspection. all work has been completed. |  |
| [200810033288](https://www.permitgraph.org/p/200810033288) | Oct 3, 2008 | Completed: final sign-off Feb 2009 | [601 California St](https://www.permitgraph.org/a/0258/032) | tenant improvement on a multi-tenant floors, space is vacant, work consist, demo walls, construct new offices and plumbing to new location. mechanical, electric & sprinkler under separate permit. | $108,000 |
| [200809111390](https://www.permitgraph.org/p/200809111390) | Sep 11, 2008 | Completed: final sign-off Dec 2008 | [717 Market St](https://www.permitgraph.org/a/3706/064) | office tenat improvement: demolition on non-structural partition, building new partition and ada compliant millwork. mep will be filed under separate permits. | $173,260 |
| [200805021169](https://www.permitgraph.org/p/200805021169) | May 2, 2008 | Expired or cancelled: expired Mar 2010 | [60 Francisco St](https://www.permitgraph.org/a/0037/001) | revision to appl #200803247799 (ref #200803207577) - remove 2 private office layouts from plan to provide for larger yoga room, vault walls to remain (no door existing) added construction notes for l… |  |
| [200803247799](https://www.permitgraph.org/p/200803247799) | Mar 24, 2008 | Expired or cancelled: expired Mar 2010 | [60 Francisco St](https://www.permitgraph.org/a/0037/001) | tenant improvement on a single floor (ground), space is currently unoccupied. mech, fire & demo under separate permit. two men & women's restrooms to remain, 2 new unisex retrooms, new partitions, st… | $86,000 |
| [200803207577](https://www.permitgraph.org/p/200803207577) | Mar 20, 2008 | Completed: final sign-off May 2008 | [60 Francisco St](https://www.permitgraph.org/a/0037/001) | demolition on single tenant ground floor including partitions, stair & 2 existing single restrooms, const plan & m.e.p. under separate permit. tenant space is currently unoccupied. | $565,000 |
| [200802295935](https://www.permitgraph.org/p/200802295935) | Feb 29, 2008 | Completed: final sign-off Mar 2008 | [300 Montgomery St](https://www.permitgraph.org/a/0260/010) | 4th floor, suite 400: minor demo under grid & doors. replace carpet. | $5,000 |
| [200709284070](https://www.permitgraph.org/p/200709284070) | Sep 28, 2007 | Completed: final sign-off Feb 2008 | [250 Montgomery St](https://www.permitgraph.org/a/0268/019) | demo accoustical ceiling corridor & replace 1 hour rated hard lid ceiling (lights, registers, sprinklers to remain untouched) | $15,000 |
| [200709193068](https://www.permitgraph.org/p/200709193068) | Sep 19, 2007 | Completed: final sign-off Dec 2007 | [250 Montgomery St](https://www.permitgraph.org/a/0268/017) | construct new non-rated partition walls for new office space. mechanical, electrical & fire safety will be done under separate permit. ref. pa # 200708301306 for demolition work. d. a. requirement un… | $110,000 |
| [200709072013](https://www.permitgraph.org/p/200709072013) | Sep 7, 2007 | Completed: final sign-off Mar 2008 | [250 Montgomery St](https://www.permitgraph.org/a/0268/017) | recessed ceiling lights relocated. 1 sprinkler head relocated, carpet replaced. bldg directory relocated. security desk modified, relocated and made compliant. 1 storefront replaced, ext. finishes re… | $98,000 |
| [200708301306](https://www.permitgraph.org/p/200708301306) | Aug 30, 2007 | Completed: final sign-off Dec 2007 | [250 Montgomery St](https://www.permitgraph.org/a/0268/017) | 2nd floor - demolition of approx. 100'-0" of undergrid walls, carpet & ceiling tile only. t.i. under separate permit. no exterior work. | $4,200 |
| [200708089105](https://www.permitgraph.org/p/200708089105) | Aug 8, 2007 | Completed: final sign-off Mar 2008 | [250 Montgomery St](https://www.permitgraph.org/a/0268/017) | furnish and install new t-bar ceiling. m.e.p. under separate permit | $50,000 |
| [200704279856](https://www.permitgraph.org/p/200704279856) | Apr 27, 2007 | Completed: final sign-off Jul 2007 | [250 Montgomery St](https://www.permitgraph.org/a/0268/017) | soft demo non structural partitions- removal 15th floor. | $40,000 |
| [200704279855](https://www.permitgraph.org/p/200704279855) | Apr 27, 2007 | Never finaled: issued Apr 2007, no final | [250 Montgomery St](https://www.permitgraph.org/a/0268/017) | 3rd floor - soft demo non structural partitions- removal 3rd floor. | $10,000 |
| [200704269779](https://www.permitgraph.org/p/200704269779) | Apr 26, 2007 | Completed: final sign-off Jun 2007 | [250 Montgomery St](https://www.permitgraph.org/a/0268/017) | soft demo non structural partitions- removal 6th floor. | $10,000 |
| [200704239394](https://www.permitgraph.org/p/200704239394) | Apr 23, 2007 | Completed: final sign-off Jul 2007 | [601 California St](https://www.permitgraph.org/a/0258/032) | 17th floor: interior tenant improvement (rework h.v.a.c./existing) mep only for pa#2007/03/06/5524. | $7,000 |
| [200702093855](https://www.permitgraph.org/p/200702093855) | Feb 9, 2007 | Completed: final sign-off Mar 2007 | [909 Montgomery St](https://www.permitgraph.org/a/0163/005) | demonstrate restroom wall to tenant space as existing to remain. change hardware on restroom doors to push/pull plate system. | $500 |
| [200702093861](https://www.permitgraph.org/p/200702093861) | Feb 9, 2007 | Completed: final sign-off May 2007 | [909 Montgomery St](https://www.permitgraph.org/a/0163/005) | demonstrate existing corridor wall as one-hour rated. |  |
| [200702093857](https://www.permitgraph.org/p/200702093857) | Feb 9, 2007 | Completed: final sign-off Mar 2007 | [909 Montgomery St](https://www.permitgraph.org/a/0163/005) | request hardship, add door operator control button, demonstrate existing corridor wall as one-hour rated. | $9,000 |
| [200611097311](https://www.permitgraph.org/p/200611097311) | Nov 9, 2006 | Never finaled: issued Nov 2006, no final | [821 Folsom St](https://www.permitgraph.org/a/3752/094) | hvac work-1st floor only. | $10,000 |
| [200609182568](https://www.permitgraph.org/p/200609182568) | Sep 18, 2006 | Completed: final sign-off May 2007 | [909 Montgomery St](https://www.permitgraph.org/a/0163/005) | restroom upgrade: demolition, new construction, plumbing, electrical, lighting, finishes | $60,000 |
| [200609182570](https://www.permitgraph.org/p/200609182570) | Sep 18, 2006 | Completed: final sign-off Mar 2007 | [909 Montgomery St](https://www.permitgraph.org/a/0163/005) | restroom upgrade: demolition, new construction, plumbing, electrical, lighting, finishes | $60,000 |
| [200606053181](https://www.permitgraph.org/p/200606053181) | Jun 5, 2006 | Completed: final sign-off Nov 2006 | [821 Folsom St](https://www.permitgraph.org/a/3752/094) | tenant improvement to include new partitions for offices, toilets, conference rooms. | $115,000 |

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 23 November 2026.