822 permits since 2000: 631 completed, 59 in progress, 123 never finaled, 9 expired or cancelled. Typically 8 days from filing to permit and 151 days from permit to final inspection. Of the 123 never-finaled permits, 14 are 3 to 5 years old, 57 are 5 to 10 years old, 52 are over 10 years old.

- Based in: San Francisco
- On San Francisco permits: Oct 2010 to Nov 2026
- Last 24 months: 140 permits filed

This is the city's permit record, not a license check. It does not show whether the state license is active, bonded or insured.

## Permits filed each year

| Year | Completed | In progress | Never finaled | Expired or cancelled |
| --- | --- | --- | --- | --- |
| 2010 | 6 | 0 | 0 | 0 |
| 2011 | 29 | 0 | 3 | 0 |
| 2012 | 43 | 0 | 10 | 0 |
| 2013 | 38 | 0 | 4 | 3 |
| 2014 | 30 | 0 | 11 | 0 |
| 2015 | 61 | 0 | 19 | 0 |
| 2016 | 23 | 0 | 7 | 0 |
| 2017 | 54 | 0 | 8 | 2 |
| 2018 | 53 | 0 | 21 | 1 |
| 2019 | 70 | 0 | 19 | 1 |
| 2020 | 28 | 0 | 3 | 0 |
| 2021 | 25 | 0 | 7 | 1 |
| 2022 | 35 | 0 | 3 | 0 |
| 2023 | 21 | 0 | 8 | 0 |
| 2024 | 34 | 7 | 0 | 1 |
| 2025 | 60 | 7 | 0 | 0 |
| 2026 | 21 | 45 | 0 | 0 |

## By project type

| Project type | Permits | Completed | In progress | Never finaled | Expired or cancelled | Typical days to permit | Typical days to final |
| --- | --- | --- | --- | --- | --- | --- | --- |
| Stairs | 26 | 17 | 1 | 7 | 1 | 22 | 145 |
| Kitchen remodel | 4 | 4 | 0 | 0 | 0 | 28 | 140 |
| Bathroom remodel | 5 | 5 | 0 | 0 | 0 | 10 | 109 |
| Deck | 1 | 1 | 0 | 0 | 0 | 321 | 219 |

## Most recent permits

The 100 most recent of 822.

| Permit | Filed | Outcome | Address | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- |
| [202611170832](https://www.permitgraph.org/p/202611170832) | Nov 17, 2026 | In progress: filed Nov 2026, not yet issued | [55 Spear St](https://www.permitgraph.org/a/3713/007) | ground flr/1st flr. ref: 202610219705. mechanical for 202610219705 | $58,000 |
| [202610290069](https://www.permitgraph.org/p/202610290069) | Oct 29, 2026 | In progress: issued Nov 2026 | [888 Brannan St](https://www.permitgraph.org/a/3780/006) | revision to pa #202609107888 include non-structural and finish work of new all gender restrooms, egress door and path of travel upgrades. new permit revision to include change to restroom layout and… |  |
| [202610219702](https://www.permitgraph.org/p/202610219702) | Oct 21, 2026 | In progress: issued Oct 2026 | [55 Spear St](https://www.permitgraph.org/a/3713/007) | b1: demolition of (e) non-structural partitions. doors & frame, finishes, ceiling, lighting & plumbing fixtures. construction of new non-structural partitions, finishes, ceiling, lighting & plumbing… | $650,000 |
| [202610219705](https://www.permitgraph.org/p/202610219705) | Oct 21, 2026 | In progress: issued Oct 2026 | [55 Spear St](https://www.permitgraph.org/a/3713/007) | grd fl: plumbing fixtures. new mail room and bike room | $800,000 |
| [202610219700](https://www.permitgraph.org/p/202610219700) | Oct 21, 2026 | In progress: filed Oct 2026, not yet issued | [345 Spear St](https://www.permitgraph.org/a/3744/002) | 1st fl t.i. combining 2 existing suites into singular office space. new flooring, ceilings, lighting and wall partition with glass office fronts. new pantry/breakroom. set of e glass entry doors (ext… | $292,338 |
| [202610079151](https://www.permitgraph.org/p/202610079151) | Oct 7, 2026 | In progress: filed Oct 2026, not yet issued | [221 Main St](https://www.permitgraph.org/a/3740/034) | suite #700: mechanical sheets only in referance to permit #202401264744. relocate existing duct work and diffuser. | $52,000 |
| [202609308804](https://www.permitgraph.org/p/202609308804) | Sep 30, 2026 | In progress: issued Sep 2026 | [101 California St](https://www.permitgraph.org/a/0263/011) | 46th fl - deferred elec -common restroom upgarde: lighting w/associated circuits & controls; power & signal w/associated circuits and wiring. ref pa 202606183494 | $35,000 |
| [202609308800](https://www.permitgraph.org/p/202609308800) | Sep 30, 2026 | In progress: issued Sep 2026 | [101 California St](https://www.permitgraph.org/a/0263/011) | 39th fl - common restroom upgrade: lighting with associated circuits and controls; power and signals with associated circuits and wiring. reference arch permit # 202607225369 | $35,000 |
| [202609298784](https://www.permitgraph.org/p/202609298784) | Sep 29, 2026 | In progress: issued Sep 2026 | [101 California St](https://www.permitgraph.org/a/0263/011) | 10th fl - common restroom upgarde: lighting w/associated circuits & controls; power & signal w/associated circuits and wiring. ref pa 202606253884 | $35,000 |
| [202609258635](https://www.permitgraph.org/p/202609258635) | Sep 25, 2026 | In progress: issued Oct 2026 | [1 Beach St](https://www.permitgraph.org/a/0018/001) | deferred mep for pa#2026-0302-6788 suite 350. | $500,000 |
| [202609258621](https://www.permitgraph.org/p/202609258621) | Sep 25, 2026 | In progress: issued Oct 2026 | [1 Beach St](https://www.permitgraph.org/a/0018/001) | deferred mep for 202608206913 suite 150. | $187,000 |
| [202609178302](https://www.permitgraph.org/p/202609178302) | Sep 17, 2026 | In progress: issued Nov 2026 | [575 Market St](https://www.permitgraph.org/a/3708/175) | 39/fl- interior ti to include soft demo of non structural partitions, finishes, ceilings, lighting, and millwork. new non structural partitions, finishes, ceilings, light fixtures, and millwork. mep… | $150,000 |
| [202609168175](https://www.permitgraph.org/p/202609168175) | Sep 16, 2026 | In progress: issued Sep 2026 | [300 Mission St](https://www.permitgraph.org/a/3710/018) | 14/f: revision to pa#202607225388. provide & install new lighting fixtures & controls per title 24 requirements. provide & install new devices shown on plan. lighting t-24 calculation. provide all el… | $50,000 |
| [202609158119](https://www.permitgraph.org/p/202609158119) | Sep 15, 2026 | Completed: final sign-off Oct 2026 | [300 Mission St](https://www.permitgraph.org/a/3710/018) | 14th - floor (5) evacuation maps. | $3,000 |
| [202609107930](https://www.permitgraph.org/p/202609107930) | Sep 10, 2026 | In progress: issued Sep 2026 | [101 02nd St](https://www.permitgraph.org/a/3721/089) | 8/f suite 800: deferred mep for ref pa 202607144969. electrical - office t.i retrofit: lighting with associated circuits and controls, power and signal with associated circuits and wiring. mechanical… | $92,450 |
| [202609107888](https://www.permitgraph.org/p/202609107888) | Sep 10, 2026 | In progress: issued Sep 2026 | [888 Brannan St](https://www.permitgraph.org/a/3780/006) | 1/fl-scope of work consist of selective interior demo of no strutural elements and new construction of all gender restrooms and new egress door from tenant suite. new ada upgrades for building path o… | $250,000 |
| [202609027599](https://www.permitgraph.org/p/202609027599) | Sep 2, 2026 | In progress: issued Nov 2026 | [575 Market St](https://www.permitgraph.org/a/3708/175) | suite 3400: interior tenant improvement, demo of non stuctual parititions, finishes, ceiling, light fixtures, millwork. new non stuctural partitions, finishes, ceiling light fixtures and millwork. me… | $300,000 |
| [202608277286](https://www.permitgraph.org/p/202608277286) | Aug 27, 2026 | In progress: issued Sep 2026 | [101 California St](https://www.permitgraph.org/a/0263/011) | 47th fl common area restrooms. shall consist of interior demolition and construction of non structural elements including interoir partitions, finishes, ceilings, lighting and fixtures. mep and fire… | $202,000 |
| [202608206913](https://www.permitgraph.org/p/202608206913) | Aug 20, 2026 | In progress: issued Sep 2026 | [1 Beach St](https://www.permitgraph.org/a/0018/001) | 1/f suite 150. including non bearing partitions, ceilings, light fixtures, doors and side lites and new finishes. mep deferred. | $574,044 |
| [202608176695](https://www.permitgraph.org/p/202608176695) | Aug 17, 2026 | In progress: issued Sep 2026 | [55 Spear St](https://www.permitgraph.org/a/3713/007) | 18th floor: revision to bpa: 202606032408 room 18-009/ pantry and finishes to single sex rr was deferred. adressing architectural set and corresponding meps for this review. | $37,488 |
| [202608136536](https://www.permitgraph.org/p/202608136536) | Aug 13, 2026 | In progress: issued Aug 2026 | [1 Embarcadero Center](https://www.permitgraph.org/a/0230/028) | 11floor: high rise common corridor, elevator lobby, restroom lighting remodel. new lighting fixtures and associated circuiting/ controls ref bpa: 202512222453 | $85,000 |
| [202608106298](https://www.permitgraph.org/p/202608106298) | Aug 10, 2026 | In progress: issued Sep 2026 | [539 Bryant St](https://www.permitgraph.org/a/3776/041) | tenant improvement remodel including new enclosure at basement level elevator hoistway opening and a new smoke draft curtain at 2nd and 4th floor elevator hoistway opening. | $89,646 |
| [202607305827](https://www.permitgraph.org/p/202607305827) | Jul 30, 2026 | In progress: issued Sep 2026 | [1 Beach St](https://www.permitgraph.org/a/0018/001) | 3rd fl, ste 350 - revision to pa 202603026788 includes new structural partitions, ceilings, light fixtures, doors and sidelites, millwork and finishes |  |
| [202607225369](https://www.permitgraph.org/p/202607225369) | Jul 22, 2026 | In progress: issued Aug 2026 | [101 California St](https://www.permitgraph.org/a/0263/011) | 39th fl:common area restrooms,shall consist of interior demolition and construction of non-structural elements including, but not necessary limited to, interior partitions, finishes,ceiling,light&fix… | $202,000 |
| [202607225371](https://www.permitgraph.org/p/202607225371) | Jul 22, 2026 | In progress: issued Aug 2026 | [101 California St](https://www.permitgraph.org/a/0263/011) | 45th flr: non-structural interior demolition of partitions doors, fihishes, ceilings, lighting, mechanical & electrical outlets & switches in common restrooms. restroom ada accessibility upgrades, el… | $202,000 |
| [202607225388](https://www.permitgraph.org/p/202607225388) | Jul 22, 2026 | In progress: issued Aug 2026 | [300 Mission St](https://www.permitgraph.org/a/3710/018) | 14th floor: electrical for pa #202605201633 project. | $573,000 |
| [202607145001](https://www.permitgraph.org/p/202607145001) | Jul 14, 2026 | Completed: final sign-off Sep 2026 | [345 Spear St](https://www.permitgraph.org/a/3744/002) | 2nd & 4th floors: revision to pa#202606173460, (6) new phone booths & (4) existing phone booths to be brought up to code on level2. (2) new phone booths on level 4 with structural drawings and calcs… | $30,000 |
| [202607144969](https://www.permitgraph.org/p/202607144969) | Jul 14, 2026 | In progress: issued Jul 2026 | [101 02nd St](https://www.permitgraph.org/a/3721/089) | 8/f suite 800: tenant improvement remodel including new partitions, office door and glazing. reference plan for restrooms #202504285316 completed 11/18/2025. mep deferred. | $324,000 |
| [202607134900](https://www.permitgraph.org/p/202607134900) | Jul 13, 2026 | In progress: issued Jul 2026 | [300 Mission St](https://www.permitgraph.org/a/3710/018) | 14/f: mechanical for pa# 202605201633 provide new mains and lowside ductwork per new architectural layout. provide new transfer for serving server room. provide new water source heat pump serving boa… | $513,000 |
| [202607094770](https://www.permitgraph.org/p/202607094770) | Jul 9, 2026 | Completed: final sign-off Nov 2026 | [114 Sansome St](https://www.permitgraph.org/a/0267/010) | suite 1400: installation of two new phone booths, including anchoring details. | $2,560 |
| [202606294121](https://www.permitgraph.org/p/202606294121) | Jun 29, 2026 | In progress: issued Jun 2026 | [55 Spear St](https://www.permitgraph.org/a/3713/007) | 17th fl structural for high density files. ref 202606032446 |  |
| [202606233688](https://www.permitgraph.org/p/202606233688) | Jun 23, 2026 | In progress: issued Jun 2026 | [345 California St](https://www.permitgraph.org/a/0261/019) | mep deferred. partial 24th floor office ti. demo of some interior non bearing walls, ceiling, lighting, electrical. construction of new full height partitions, doors, glazing, millwork, and finishes. | $342,850 |
| [202606233756](https://www.permitgraph.org/p/202606233756) | Jun 23, 2026 | In progress: issued Jul 2026 | [345 California St](https://www.permitgraph.org/a/0261/019) | 24th floor: mechanical: duct distribution to be modified to serve new space plan in area of work. 5 new vav boxes are being added. electrical: new led light fixtures and power and signal. plumbing: n… | $375,000 |
| [202606183494](https://www.permitgraph.org/p/202606183494) | Jun 18, 2026 | In progress: issued Jun 2026 | [101 California St](https://www.permitgraph.org/a/0263/011) | 46th fl limited demo, construction of partitions, ceiling, lighting, doors & inishes to demise suite 4600 into suite 4600 & 4625. also, refreshing, common area restrooms & limited demo, new partition… | $250,000 |
| [202606173460](https://www.permitgraph.org/p/202606173460) | Jun 17, 2026 | Completed: final sign-off Sep 2026 | [345 Spear St](https://www.permitgraph.org/a/3744/002) | 2nd & 4th floors - installation of phone furniture booths, 7 on level 2 and 2 on level 4. structural plans and clacs for anchoring included. no mep work | $30,000 |
| [202606092869](https://www.permitgraph.org/p/202606092869) | Jun 9, 2026 | In progress: issued Jun 2026 | [550 Kearny St](https://www.permitgraph.org/a/0240/016) | 5/f suite 500: mechanical modifications to accommodate layout changes. new vav box, ductwork, and hot water piping with insulation as needed. new power and signal devices throughout. title 24 complia… | $75,000 |
| [202606052686](https://www.permitgraph.org/p/202606052686) | Jun 5, 2026 | In progress: filed Jun 2026, not yet issued | [550 Kearny St](https://www.permitgraph.org/a/0240/016) | 5/f (ste 500) revision to pa# 202604099141: removal of path of travel and restroom scope that will not be upgraded because of the project valuations less than the 2026 evaluation threshold. removal o… |  |
| [202606032446](https://www.permitgraph.org/p/202606032446) | Jun 3, 2026 | In progress: issued Jun 2026 | [55 Spear St](https://www.permitgraph.org/a/3713/007) | spear street tower, 17th flr: t.i. selected demo of remaining soffite and partitions, primary demo under 202603137532. new construction will consist of new partitions and doors, ceilings, light fixtu… | $2,199 |
| [202606032408](https://www.permitgraph.org/p/202606032408) | Jun 3, 2026 | In progress: issued Jun 2026 | [55 Spear St](https://www.permitgraph.org/a/3713/007) | 18f t.i: demo done under permit. new partitons & doors, ceilings, lights, el distribution. mep included. including structural work. n unisex accessible toilet. see coversheet for cope. deffered submi… | $3,279,000 |
| [202605201633](https://www.permitgraph.org/p/202605201633) | May 20, 2026 | In progress: issued Jun 2026 | [300 Mission St](https://www.permitgraph.org/a/3710/018) | 14 fl: interior tenant improvement which includes multi-use men and women restrooms, new partitions, finishes, light fixtures, ceiling,assembly, millwork and plumbing fixtures. mep deferred. | $2,000,000 |
| [202605191497](https://www.permitgraph.org/p/202605191497) | May 19, 2026 | Completed: final sign-off Sep 2026 | [55 Spear St](https://www.permitgraph.org/a/3713/007) | 16th fl: mechanical & electrical for 202604169572(aka one market plaza spear tower) | $150,000 |
| [202605181420](https://www.permitgraph.org/p/202605181420) | May 18, 2026 | In progress: issued May 2026 | [101 02nd St](https://www.permitgraph.org/a/3721/089) | suite: 350 - new power and signal throught the space, new 2025 t24 lighting and controls. ref bpa: 202603268312 | $70,000 |
| [202605141296](https://www.permitgraph.org/p/202605141296) | May 14, 2026 | In progress: issued May 2026 | [101 02nd St](https://www.permitgraph.org/a/3721/089) | unit# 350: furnish and istall one new 1-ton water source heat pump associated ductwork. piping and condensate for it room. ref 202630268312 | $54,000 |
| [202604270132](https://www.permitgraph.org/p/202604270132) | Apr 27, 2026 | In progress: issued Apr 2026 | [101 02nd St](https://www.permitgraph.org/a/3721/089) | (ste# 350 / 3rd floor) revision to pa# 202603268312: work includes installation of 6 phone booths. |  |
| [202604169572](https://www.permitgraph.org/p/202604169572) | Apr 16, 2026 | Completed: final sign-off Sep 2026 | [55 Spear St](https://www.permitgraph.org/a/3713/007) | 16/fl- demolition of existing non structural partitions, doors, and frames, finishes, ceilings, lighting, plumbing fixtures. duct work havac and elec to be pulled back to source and plumbing to be ca… | $1,000,000 |
| [202604099141](https://www.permitgraph.org/p/202604099141) | Apr 9, 2026 | In progress: issued Apr 2026 | [550 Kearny St](https://www.permitgraph.org/a/0240/016) | selective demolition of non-structural interior elements, including interior portions, doors, ceilings, lighting, mechanical & electrical, and finishes. new construction scope includes non-structural… | $135,000 |
| [202603278413](https://www.permitgraph.org/p/202603278413) | Mar 27, 2026 | Completed: final sign-off May 2026 | [66 Kearny St](https://www.permitgraph.org/a/0311/007) | revision to permit 202511260493. minor changes to coffee bar and equipment. revise coffee bar and equipment associated at back of the house. |  |
| [202603268312](https://www.permitgraph.org/p/202603268312) | Mar 26, 2026 | In progress: issued Mar 2026 | [101 02nd St](https://www.permitgraph.org/a/3721/089) | 3/f suite 350 - work includes: new partitions, office door and glazing and mill work. | $125,000 |
| [202603238090](https://www.permitgraph.org/p/202603238090) | Mar 23, 2026 | Completed: final sign-off Aug 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/008) | 7/f: structural reinforcement at two beam locations for gym equipment. building is fully sprinklered. | $15,000 |
| [202603177684](https://www.permitgraph.org/p/202603177684) | Mar 17, 2026 | In progress: issued Mar 2026 | [595 Market St](https://www.permitgraph.org/a/3708/043) | suite 2450a: def mechanical & electrical for 202602135931. | $129,654 |
| [202603137532](https://www.permitgraph.org/p/202603137532) | Mar 13, 2026 | In progress: issued Mar 2026 | [1 Market St](https://www.permitgraph.org/a/3713/007) | 17th fl - selective interior demo only (ab-017) ref 26-158 | $70,000 |
| [202603137530](https://www.permitgraph.org/p/202603137530) | Mar 13, 2026 | In progress: issued Mar 2026 | [1 Market St](https://www.permitgraph.org/a/3713/007) | 18th fl - selective interior demo only (ab-017) ref fire 26-158 | $70,000 |
| [202603127462](https://www.permitgraph.org/p/202603127462) | Mar 12, 2026 | Completed: final sign-off Sep 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/009) | 20/f: revision to permit 202511109312. technical infeasibility request for men's restroom screen. |  |
| [202603107224](https://www.permitgraph.org/p/202603107224) | Mar 10, 2026 | Completed: final sign-off May 2026 | [66 Kearny St](https://www.permitgraph.org/a/0311/007) | 1st fl - meps for 202511260493 | $194,832 |
| [202603067068](https://www.permitgraph.org/p/202603067068) | Mar 6, 2026 | Completed: final sign-off May 2026 | [66 Kearny St](https://www.permitgraph.org/a/0311/007) | revision to bpa# 202511260493. administrative permit to clarify that the entry door does not require panic hardware, include sign above door that states "door shall remain open during business hours." |  |
| [202603036837](https://www.permitgraph.org/p/202603036837) | Mar 3, 2026 | Completed: final sign-off Sep 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/009) | 19th floor. add 2 ton wshp to serve 1df room. |  |
| [202602266574](https://www.permitgraph.org/p/202602266574) | Feb 26, 2026 | Completed: final sign-off Aug 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/009) | 4th fl - permit revision ti permit 202510288260 for remodel of existing communication stair and a technical infeasibility @ women's restrooms | $12,000 |
| [202602246427](https://www.permitgraph.org/p/202602246427) | Feb 24, 2026 | Completed: final sign-off Mar 2026 | [345 Spear St](https://www.permitgraph.org/a/3744/002) | to obtain final inspection for work approved under pa # 202412116597. all work is complete. |  |
| [202602176004](https://www.permitgraph.org/p/202602176004) | Feb 17, 2026 | Completed: final sign-off Sep 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/009) | 7/f: meps for t.i. 202511250451. | $450,000 |
| [202602176029](https://www.permitgraph.org/p/202602176029) | Feb 17, 2026 | Completed: final sign-off Sep 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/008) | 11th fl - mep for pa 202511109302 | $350,000 |
| [202602176007](https://www.permitgraph.org/p/202602176007) | Feb 17, 2026 | Completed: final sign-off Sep 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/008) | 6/f: meps for t.i. 202511250447. | $120,000 |
| [202602135931](https://www.permitgraph.org/p/202602135931) | Feb 13, 2026 | In progress: issued Feb 2026 | [595 Market St](https://www.permitgraph.org/a/3708/043) | 24th fl suite 2450a: minor demolition of non structural elements including partitions, finishes, ceilings & lighting. construction of new office fronts and doors, same lobby, vestibule and lighting.… | $400,000 |
| [202602045210](https://www.permitgraph.org/p/202602045210) | Feb 4, 2026 | Completed: final sign-off Sep 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/008) | 20th fl - meps for pa 202511109312 | $307,000 |
| [202602045180](https://www.permitgraph.org/p/202602045180) | Feb 4, 2026 | Completed: final sign-off Sep 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/009) | 13th floor: add 3 ton wshp to serve mdf room. | $55,000 |
| [202601214220](https://www.permitgraph.org/p/202601214220) | Jan 21, 2026 | Completed: final sign-off Aug 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/009) | 18th floor: mep project. ref pa #202511048826 |  |
| [202601214230](https://www.permitgraph.org/p/202601214230) | Jan 21, 2026 | Completed: final sign-off Aug 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/009) | 4th fl - ref arch 202510288260 mep for project | $120,000 |
| [202512222453](https://www.permitgraph.org/p/202512222453) | Dec 22, 2025 | In progress: issued May 2026 | [1 Embarcadero Center](https://www.permitgraph.org/a/0230/028) | 11/f: interior improvements to elevator lobby, hallways, and restrooms on the 11th floor. including paint, lighting, toilet fixtures, partitions, and accessories, signage, carpet flooring, and cerami… | $400,000 |
| [202512111504](https://www.permitgraph.org/p/202512111504) | Dec 11, 2025 | Completed: final sign-off Mar 2026 | [4 Embarcadero Center](https://www.permitgraph.org/a/0233/044) | demo of level 28-level 29 convenience stairs & slab in-fill. | $150,000 |
| [202512111528](https://www.permitgraph.org/p/202512111528) | Dec 11, 2025 | Completed: final sign-off Aug 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/008) | deferred mep for 17th floor ti under permit 202510217772. | $75,000 |
| [202512111531](https://www.permitgraph.org/p/202512111531) | Dec 11, 2025 | Completed: final sign-off Aug 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/008) | 3rd/f mep for t.i. 202510147260: mep for project | $145,000 |
| [202512041028](https://www.permitgraph.org/p/202512041028) | Dec 4, 2025 | Completed: final sign-off Feb 2026 | [121 Spear St](https://www.permitgraph.org/a/3716/021) | 2nd floor: addition of 7 phone booths in office space. | $20,000 |
| [202512010652](https://www.permitgraph.org/p/202512010652) | Dec 1, 2025 | Completed: final sign-off Apr 2026 | [215 Fremont St](https://www.permitgraph.org/a/3738/012) | level 2,3,4,5,6 & 7: permitting of phone booths. ref pa # 202105200701 & 202101273406 | $640,000 |
| [202512010657](https://www.permitgraph.org/p/202512010657) | Dec 1, 2025 | Completed: final sign-off Nov 2026 | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | 19/f: demo (e) toilet partitions and finishes and replace with (n). (n) bathroom finishes and fixtures and lighting. | $67,088 |
| [202511260493](https://www.permitgraph.org/p/202511260493) | Nov 26, 2025 | Completed: final sign-off May 2026 | [66 Kearny St](https://www.permitgraph.org/a/0311/007) | project consists of an interior remodel to an existing cafe (formerly starbucks) to accomodate a new cafe for andytown coffee and roasters. scope includes: new coffee bar and equipment. equipmeent ch… | $800,000 |
| [202511250451](https://www.permitgraph.org/p/202511250451) | Nov 25, 2025 | Completed: final sign-off Sep 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/008) | 7th fl - t.i. includes the building of new non-structural partitions. all new or revised meps, life safety work will be design build and submitted separately for permits. bldg is fully sprinklered. r… | $1,251,419 |
| [202511250447](https://www.permitgraph.org/p/202511250447) | Nov 25, 2025 | Completed: final sign-off Sep 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/008) | 6th fl - ti includes the building of new non-structural partitions. all new or revised meps, life safety work will be design build and submitted separately for permits. bldg is fully sprinklered. ref… | $1,243,215 |
| [202511149640](https://www.permitgraph.org/p/202511149640) | Nov 14, 2025 | In progress: issued Nov 2025 | [1 Bush St](https://www.permitgraph.org/a/0290/011) | 8/f: new power and signal devices throughtou the space. new title 24 complaint lighting & controls. ref pa# 202510167525. | $25,000 |
| [202511139481](https://www.permitgraph.org/p/202511139481) | Nov 13, 2025 | Completed: final sign-off Mar 2026 | [1 Embarcadero Center](https://www.permitgraph.org/a/0230/028) | 29th and 30 flr. communication stiar t.i. includes the remove of a non-egress interconnecting - stair and the infill of the slab opening. all new or revised life safety work will be design buildg and… | $198,000 |
| [202511109302](https://www.permitgraph.org/p/202511109302) | Nov 10, 2025 | Completed: final sign-off Sep 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/008) | 11/f. ti includes the building of new non-structural partitions. all new or revised meps and life safety work will be design build and submitted separately. bldg is fully sprinlerd. ref demo # 202508… | $573,000 |
| [202511109312](https://www.permitgraph.org/p/202511109312) | Nov 10, 2025 | Completed: final sign-off Sep 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/008) | 20/f. ti includes the building of new non-structural partitions. all new or revised meps and life safety work will be design build and submitted separately. bldg is fully sprinlerd. ref demo # 202508… | $777,000 |
| [202511079210](https://www.permitgraph.org/p/202511079210) | Nov 7, 2025 | In progress: issued Jan 2026 | [333 Pine St](https://www.permitgraph.org/a/0268/016) | 1/f suite 100: tenant improvement. change of occupancy from b to m. interior modifications involve selective demolition and construction of new non-load bearing partitions, interior door and glazing… | $670,500 |
| [202511069100](https://www.permitgraph.org/p/202511069100) | Nov 6, 2025 | Completed: final sign-off Dec 2025 | [101 02nd St](https://www.permitgraph.org/a/3721/089) | 15/fl: new lighting and controls for whit ebox space reference arch permit#2025-1001-6514 | $10,000 |
| [202511048826](https://www.permitgraph.org/p/202511048826) | Nov 4, 2025 | Completed: final sign-off Aug 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/008) | 18th floor: t.i. includes building of new non-structural partitions: all new or revised mep and life safety work will be design-build and submitted for permit seperately. building is fully sprinklere… | $734,582 |
| [202510288260](https://www.permitgraph.org/p/202510288260) | Oct 28, 2025 | Completed: final sign-off Aug 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/009) | 4th/fl: ti improvement includes building of new non structural partitions. all new or revised meps and life safety work will be design build and submitted seperately (bldg is fully sprinklers). | $537,611 |
| [202510217779](https://www.permitgraph.org/p/202510217779) | Oct 21, 2025 | Completed: final sign-off Jan 2026 | [333 Bush St](https://www.permitgraph.org/a/0288/032) | ref 202504164519- 25/fl- mep work only. | $60,000 |
| [202510217772](https://www.permitgraph.org/p/202510217772) | Oct 21, 2025 | Completed: final sign-off Aug 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/008) | 17th fl - ti includes building of new non-structural partitions. all new mep & life safety work will be design build and submitted for permit separately. bldg is fully sprinklered | $959,611 |
| [202510177572](https://www.permitgraph.org/p/202510177572) | Oct 17, 2025 | Completed: final sign-off May 2026 | [333 Bush St](https://www.permitgraph.org/a/0288/032) | 20th flr/ suite 2020. ref arch#: 202509044546. mech and electrical. | $120,000 |
| [202510167525](https://www.permitgraph.org/p/202510167525) | Oct 16, 2025 | Completed: final sign-off Jan 2026 | [1 Bush St](https://www.permitgraph.org/a/0290/011) | 8th fl - ti include the demo of non-structural partition and building new non-structural partition ny new or revised electrical life safety work will bnd submitted separately | $77,958 |
| [202510147260](https://www.permitgraph.org/p/202510147260) | Oct 14, 2025 | Completed: final sign-off Aug 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/008) | 3rd fl. demo under 202508213610. t.i. includes the bldging of new non-structural partitions. all new or revised meps life safety/sprinklers will be design bldg and submitted. separately. (bldg is ful… | $832,402 |
| [202510076905](https://www.permitgraph.org/p/202510076905) | Oct 7, 2025 | Completed: final sign-off Mar 2026 | [345 Spear St](https://www.permitgraph.org/a/3744/002) | 6th fl- architectural only for 3 new phone booth units in office. | $20,000 |
| [202509155263](https://www.permitgraph.org/p/202509155263) | Oct 6, 2025 | In progress: issued Oct 2025 | [101 California St](https://www.permitgraph.org/a/0263/011) | 8th fl - minor revision to pa 202412126710 for upgrading interior stair vestibule to 2 hour rated with 90 min rated doors. all other areas within previously approved design are to remain unchanged fl… |  |
| [202510016514](https://www.permitgraph.org/p/202510016514) | Oct 1, 2025 | Completed: final sign-off Dec 2025 | [101 02nd St](https://www.permitgraph.org/a/3721/089) | 15th/fl: demolition of non load bearing artitions , ceilings, light fixtures, millwork and finishes. | $250,000 |
| [202509256128](https://www.permitgraph.org/p/202509256128) | Sep 25, 2025 | Completed: final sign-off Dec 2025 | [101 02nd St](https://www.permitgraph.org/a/3721/089) | 3rd, 4th, & 8th floors: new 2022 title-24 compliant lighting and controls for janitor closets. ref pa #202508213649 | $7,500 |
| [202509155280](https://www.permitgraph.org/p/202509155280) | Sep 15, 2025 | Completed: final sign-off Jan 2026 | [333 Bush St](https://www.permitgraph.org/a/0288/032) | 7th/f ste 700: revision to 202505196809 & 202508223701, add fsd to demo plan, fire smoke dampers, mechanical work only. |  |
| [202509155320](https://www.permitgraph.org/p/202509155320) | Sep 15, 2025 | Completed: final sign-off Mar 2026 | [333 Bush St](https://www.permitgraph.org/a/0288/032) | 21st fl ref pa # 2024-1205-6265: provide new lighting & branch circuiting to existing panel. provide california title 24 complaince forms. | $75,000 |
| [202509104986](https://www.permitgraph.org/p/202509104986) | Sep 10, 2025 | Completed: final sign-off Jan 2026 | [1 Embarcadero Center](https://www.permitgraph.org/a/0230/028) | 32nd floor: infill former stair opening 11' x 13' with new floor slab. | $198,000 |
| [202509044546](https://www.permitgraph.org/p/202509044546) | Sep 4, 2025 | Completed: final sign-off Jul 2026 | [333 Bush St](https://www.permitgraph.org/a/0288/032) | floor/20- ste 2020 consist of minor demo of non structural elements including paritions doors, lighting and ceiling. construction at pantry and copy area. (n) ceiling, lighting and finishes. mep , li… | $250,000 |
| [202508273960](https://www.permitgraph.org/p/202508273960) | Aug 27, 2025 | Completed: final sign-off Dec 2025 | [88 Kearny St](https://www.permitgraph.org/a/0311/008) | 20/fl- demo of non structrual partitions, suspended ceilings, lighting, plumbing, finishes, etc. (e) sprinkler heads will be turned up once the suspended accoustical ceiling has been removed. ref 202… | $59,000 |
| [202508273958](https://www.permitgraph.org/p/202508273958) | Aug 27, 2025 | Completed: final sign-off Dec 2025 | [88 Kearny St](https://www.permitgraph.org/a/0311/008) | 18/fl- demo of non structrual partitions, suspended ceilings, lighting, plumbing, finishes, etc. (e) sprinkler heads will be turned up once the suspended accoustical ceiling has been removed. ref 202… | $59,000 |
| [202508273962](https://www.permitgraph.org/p/202508273962) | Aug 27, 2025 | Completed: final sign-off Mar 2026 | [88 Kearny St](https://www.permitgraph.org/a/0311/008) | 04/fl- demo of non structrual partitions, suspended ceilings, lighting, plumbing, finishes, etc. (e) sprinkler heads will be turned up once the suspended accoustical ceiling has been removed. ref 202… | $77,406 |

---