# Matrix Hg Inc

Contractor license 812232. San Francisco building permit record since 2000.

- Page: https://www.permitgraph.org/contractor/matrix-hg-inc-812232
- JSON: https://www.permitgraph.org/api/contractor?license=812232
- State license record: https://www.cslb.ca.gov/onlineservices/checklicenseII/LicenseDetail.aspx?LicNum=812232

208 permits since 2000: 154 completed, 14 in progress, 30 never finaled, 10 expired or cancelled. Typically 0 days from filing to permit and 130 days from permit to final inspection. Of the 30 never-finaled permits, 4 are 3 to 5 years old, 17 are 5 to 10 years old, 9 are over 10 years old.

- Based in: Concord
- On San Francisco permits: Aug 2005 to Nov 2026
- Last 24 months: 31 permits filed

This is the city's permit record, not a license check. It does not show whether the state license is active, bonded or insured.

## Permits filed each year

| Year | Completed | In progress | Never finaled | Expired or cancelled |
| --- | --- | --- | --- | --- |
| 2005 | 1 | 0 | 0 | 0 |
| 2006 | 4 | 0 | 1 | 0 |
| 2007 | 4 | 0 | 0 | 0 |
| 2008 | 6 | 0 | 0 | 0 |
| 2009 | 2 | 0 | 0 | 1 |
| 2010 | 2 | 0 | 0 | 0 |
| 2011 | 6 | 0 | 0 | 1 |
| 2012 | 4 | 0 | 0 | 0 |
| 2013 | 5 | 0 | 2 | 0 |
| 2014 | 8 | 0 | 2 | 1 |
| 2015 | 14 | 0 | 4 | 1 |
| 2016 | 9 | 0 | 0 | 1 |
| 2017 | 5 | 0 | 1 | 0 |
| 2018 | 12 | 0 | 8 | 1 |
| 2019 | 15 | 0 | 2 | 3 |
| 2020 | 8 | 0 | 2 | 1 |
| 2021 | 7 | 0 | 4 | 0 |
| 2022 | 8 | 0 | 2 | 0 |
| 2023 | 5 | 0 | 2 | 0 |
| 2024 | 11 | 3 | 0 | 0 |
| 2025 | 13 | 1 | 0 | 0 |
| 2026 | 5 | 10 | 0 | 0 |

## By project type

| Project type | Permits | Completed | In progress | Never finaled | Expired or cancelled | Typical days to permit | Typical days to final |
| --- | --- | --- | --- | --- | --- | --- | --- |
| Deck | 2 | 1 | 0 | 1 | 0 | 0 | 182 |
| Kitchen remodel | 2 | 1 | 0 | 1 | 0 | 0 | 63 |
| Bathroom remodel | 2 | 2 | 0 | 0 | 0 | 16 | 190 |

## Most recent permits

The 100 most recent of 208.

| Permit | Filed | Outcome | Address | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- |
| [202611160781](https://www.permitgraph.org/p/202611160781) | Nov 16, 2026 | In progress: issued Nov 2026 | [944 Stockton St](https://www.permitgraph.org/a/0210A/003) | replacement of 1) 20 ton fluid cooler and 4) 5 ton wshp | $67,000 |
| [202609027552](https://www.permitgraph.org/p/202609027552) | Nov 9, 2026 | In progress: filed Nov 2026, not yet issued | [300 Clay St](https://www.permitgraph.org/a/0204/021) | alteration to the existing mech. system serviing specific. basement zones and ground flr zones. reduce (e) constent air volume w/variable air volume sf-12 an economizer. provide (n) vav boxes for sf-… | $875,345 |
| [202609188317](https://www.permitgraph.org/p/202609188317) | Sep 18, 2026 | In progress: issued Sep 2026 | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | 10th floor: install vfd on (e) supply fan. no other modifications to the building (e) mech system are included. | $71,000 |
| [202608287345](https://www.permitgraph.org/p/202608287345) | Aug 28, 2026 | In progress: issued Aug 2026 | [2485 San Bruno Av](https://www.permitgraph.org/a/5437/042) | replacement of three rooftop package a/c units with gas heating. | $31,000 |
| [202608287323](https://www.permitgraph.org/p/202608287323) | Aug 28, 2026 | In progress: issued Aug 2026 | [1945 Irving St](https://www.permitgraph.org/a/1775/046) | replacement of four rooftop package a/c units with gas heating. same location of roof | $47,000 |
| [202608216969](https://www.permitgraph.org/p/202608216969) | Aug 21, 2026 | In progress: issued Aug 2026 | [180 Montgomery St](https://www.permitgraph.org/a/0289/009) | ste 1675: provide and install the new exhaust fan for server room. redistribute (1) low side duct runs for new space layout for wellness room. add supplies and returns in (1) new space with reference… | $17,600 |
| [202608136498](https://www.permitgraph.org/p/202608136498) | Aug 13, 2026 | In progress: issued Aug 2026 | [1570 Bay St](https://www.permitgraph.org/a/0459/032) | replacement of 3 bard units, 2 serving the swgr building and 1 serving the battery building and structural support to support the units. no new fire smoke dampers required. | $62,906 |
| [202606243787](https://www.permitgraph.org/p/202606243787) | Jun 24, 2026 | In progress: issued Jun 2026 | [150 California St](https://www.permitgraph.org/a/0236/019) | replace 2 existing boilers with new condensing gas fire boilers located in the roof penthouse. | $198,000 |
| [202605221765](https://www.permitgraph.org/p/202605221765) | May 22, 2026 | Completed: final sign-off Jul 2026 | [99 Rhode Island St](https://www.permitgraph.org/a/3912/002) | to obtain final inspection for work approved under pa #201909192116 all work completed |  |
| [202605151347](https://www.permitgraph.org/p/202605151347) | May 15, 2026 | Completed: final sign-off Jun 2026 | [2300 Harrison St](https://www.permitgraph.org/a/3593/001) | 2/f: restroom exhaust fan, ductwork, and outlets. one vav box relocation. ref permit 202604139302 | $15,000 |
| [202604089072](https://www.permitgraph.org/p/202604089072) | Apr 8, 2026 | Completed: final sign-off Oct 2026 | [300 Clay St](https://www.permitgraph.org/a/0204/021) | 26/f: replace the (e) general exhaust fan, ef-3, located on the 26th floor of one maritime plaza, with a 31,200 cfm variable - volume exhaust fan to increase tenant exhaust airflow capacity. the exha… | $90,000 |
| [202604089099](https://www.permitgraph.org/p/202604089099) | Apr 8, 2026 | In progress: issued May 2026 | [300 Clay St](https://www.permitgraph.org/a/0204/021) | installation of a mechanical service access platform and ladder in the street level fan room | $75,000 |
| [202604038826](https://www.permitgraph.org/p/202604038826) | Apr 3, 2026 | In progress: issued Apr 2026 | [650 Davis St](https://www.permitgraph.org/a/0168/057) | 1st floor: furnish and install (1) heat pump unit. furnish and install associated ductwork and air registers/diffusers. ref# 2026-0218-6079. | $8,400 |
| [202603036807](https://www.permitgraph.org/p/202603036807) | Mar 3, 2026 | Completed: final sign-off Aug 2026 | [655 Beach St](https://www.permitgraph.org/a/0024/025) | suite 210: hvac modifications to support interior tenant improvements. all terminal units are existing to remain. (e) central equipment is existing to remain. (e) controls to remain. ref building per… | $136,068 |
| [202602196137](https://www.permitgraph.org/p/202602196137) | Feb 19, 2026 | Completed: final sign-off Apr 2026 | [180 Montgomery St](https://www.permitgraph.org/a/0289/009) | ste, 1900 hvac modifications to support interior ti (e) central equipment to remain. (e) controls to remain. ref pa 202512030868 | $15,000 |
| [202512121631](https://www.permitgraph.org/p/202512121631) | Dec 12, 2025 | Completed: final sign-off May 2026 | [288 West Portal Av](https://www.permitgraph.org/a/2988A/032) | like for like replacement of 3 rooftop packaged a/c gas pack units | $30,000 |
| [202511058950](https://www.permitgraph.org/p/202511058950) | Nov 5, 2025 | Completed: final sign-off Feb 2026 | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | 11/fl- install (n) variable frequency drive on (e) supply fan. no other work to be done on the (e) mechanical system are included | $71,389 |
| [202510237965](https://www.permitgraph.org/p/202510237965) | Oct 23, 2025 | Completed: final sign-off Jan 2026 | [2350 Turk Bl](https://www.permitgraph.org/a/1107/006) | replacement of (e) flue stack serving (e) heating boiler and domestic hot water heater at the school of education bldg. provide new inline draft fan for flue stack. | $100,000 |
| [202510107152](https://www.permitgraph.org/p/202510107152) | Oct 10, 2025 | Completed: final sign-off Sep 2026 | [180 Montgomery St](https://www.permitgraph.org/a/0289/009) | suite 2150. demolish all (e) low pressure and air distribution down stream of the terminal units. install new low pressure ductwork and air distribution to match the new t.i. layout. install one new… | $86,763 |
| [202509266171](https://www.permitgraph.org/p/202509266171) | Sep 26, 2025 | Completed: final sign-off Mar 2026 | [1 Lombard St](https://www.permitgraph.org/a/0081/001) | replace rooftop unit, existing unit weight = 685lb, new unit weight = 565lb. | $42,375 |
| [202508294192](https://www.permitgraph.org/p/202508294192) | Aug 29, 2025 | Completed: final sign-off Feb 2026 | [315 Montgomery St](https://www.permitgraph.org/a/0259/029) | 5th fl - replacement of (1) 3 ton water source heat pump. the equipment is above ceiling & serves a 5th l iof closet | $15,000 |
| [202507019866](https://www.permitgraph.org/p/202507019866) | Jul 1, 2025 | Completed: final sign-off Dec 2025 | [101 02nd St](https://www.permitgraph.org/a/3721/089) | replace (e) trane 10-ton cooling only package unit with new trane 10-tom. package unit and reconnect to existing ductwork and electrical. no work in the interior of the building | $35,524 |
| [202506168732](https://www.permitgraph.org/p/202506168732) | Jun 16, 2025 | Completed: final sign-off Jan 2026 | [300 Clay St](https://www.permitgraph.org/a/0204/021) | add (3) overhead electric heaters in an existing outdoor dining area for an existing restaurant. | $36,789 |
| [202505287335](https://www.permitgraph.org/p/202505287335) | May 28, 2025 | Completed: final sign-off Sep 2025 | [180 Montgomery St](https://www.permitgraph.org/a/0289/009) | suite 2300 ref pa 2025-0402-3549 relocate (e) low pressure ductwork and air distribution to match now ti layout. install new transfer fan for it closet. relocate thermostats as needed to accommodate… | $63,694 |
| [202503212740](https://www.permitgraph.org/p/202503212740) | Mar 21, 2025 | Completed: final sign-off Jun 2025 | [33 New Montgomery St](https://www.permitgraph.org/a/3707/062) | hvac modifications to support interior ti. all other terminal units are existing to remain. (e) central equipment existing to remain. (e) pneumatic controls to remain. ref pa 202503061735 | $10,000 |
| [202503202623](https://www.permitgraph.org/p/202503202623) | Mar 20, 2025 | Completed: final sign-off Nov 2025 | [555 California St](https://www.permitgraph.org/a/0259/026) | basement - installation of a new cooling coil in (e) air handler; installation of 3 (n) condensing units, each; installation of 6 (n) exv's for cus & coils; install refrigerant pipe for cu/exv/coils;… | $103,000 |
| [202502130235](https://www.permitgraph.org/p/202502130235) | Feb 13, 2025 | In progress: issued Feb 2025 | [300 Clay St](https://www.permitgraph.org/a/0204/021) | fire sequence change. revision to pa#2024-0724-7142 | $50,000 |
| [202502039530](https://www.permitgraph.org/p/202502039530) | Feb 3, 2025 | Completed: final sign-off Jan 2026 | [180 Howard St](https://www.permitgraph.org/a/3717/020) | 1st/fl- ref 202410243671- hvac modifications to support interior tenant improvements, (n) grills, registers, diffusrs, and ductwork. install 1 (n) exhaust fan. | $168,000 |
| [202501289178](https://www.permitgraph.org/p/202501289178) | Jan 28, 2025 | Completed: final sign-off Jan 2026 | [255 California St](https://www.permitgraph.org/a/0262/013) | basement: replace 1) 250 ton chiller, install ref, nonitor device, install new sf & ef fansf for ref, ventilation new ufds for e) pumps, rework electrical for chiller & pumps new electrical for fans… | $250,000 |
| [202412207189](https://www.permitgraph.org/p/202412207189) | Dec 20, 2024 | Completed: final sign-off Jan 2025 | [400 Mcallister St](https://www.permitgraph.org/a/0766/002) | install one new 1.5 ton ductless mini -split unit to serve recently refurbished elevator machine room no architctural work machine room was recently refurbished under pa# 2023-0922-7195 & 2023-0221-2… | $53,434 |
| [202412136774](https://www.permitgraph.org/p/202412136774) | Dec 13, 2024 | In progress: issued Dec 2024 | [50 Green St](https://www.permitgraph.org/a/0111/002) | to obtain final inspection for work approved under pa# 201812178453. all work is complete. |  |
| [202409241486](https://www.permitgraph.org/p/202409241486) | Sep 24, 2024 | In progress: filed Sep 2024, not yet issued | [300 Clay St](https://www.permitgraph.org/a/0204/021) | revision to 202407247142. fire sequence change return air duct add | $50,000 |
| [202409241446](https://www.permitgraph.org/p/202409241446) | Sep 24, 2024 | Completed: final sign-off Jul 2025 | [300 Clay St](https://www.permitgraph.org/a/0204/021) | ground fl - replace (e) mechanical system serving the plaza level tenant space, bar sprezzatura. relocate heat pumps to permanent locations on ground fl; connect plaza level return to the heat pump u… | $352,749 |
| [202408239326](https://www.permitgraph.org/p/202408239326) | Aug 23, 2024 | Completed: final sign-off Oct 2024 | [301 Howard St](https://www.permitgraph.org/a/3738/011) | 14/f suite 1400: hvac modification to support interior tenant improvements no new fsd's ref pa# 2024-0530-3259 | $17,500 |
| [202408168816](https://www.permitgraph.org/p/202408168816) | Aug 16, 2024 | Completed: final sign-off Sep 2024 | [601 California St](https://www.permitgraph.org/a/0258/032) | 3/f-ste 300:hvac modifications to support interior tenant improvement ref pa# 202406214979. | $22,000 |
| [202407247142](https://www.permitgraph.org/p/202407247142) | Jul 24, 2024 | Completed: final sign-off Aug 2025 | [300 Clay St](https://www.permitgraph.org/a/0204/021) | replace (2) air handling units, vavs and coils. | $800,000 |
| [202406214962](https://www.permitgraph.org/p/202406214962) | Jun 21, 2024 | Completed: final sign-off Aug 2024 | [300 Clay St](https://www.permitgraph.org/a/0204/021) | suite 15 1st fl: demo mopsink faucet and fixture trim. install airgap fitting to (e) handsink. install grease intercepter and modify (e) sanitary drain and vent piping for connection. install kitchen… | $20,000 |
| [202404059384](https://www.permitgraph.org/p/202404059384) | Apr 5, 2024 | In progress: issued Apr 2024 | [595 Market St](https://www.permitgraph.org/a/3708/043) | 13th fl, #1350 - revision to pa 202310259457 t-24 pages were updated to show correct forms needed |  |
| [202402236411](https://www.permitgraph.org/p/202402236411) | Feb 23, 2024 | Completed: final sign-off May 2024 | [650 California St](https://www.permitgraph.org/a/0241/025) | 27th fl ti using base building hvac system. modifications to air distribution system in tenant space to suite arch renovations, includidng installation of water source heat pump and associated ductwo… | $45,000 |
| [202401294793](https://www.permitgraph.org/p/202401294793) | Jan 29, 2024 | Completed: final sign-off Jun 2024 | [120 Kearny St](https://www.permitgraph.org/a/0292/008) | 34/f-ste 3450: modification to air distribution system in tenant space to suite architectural renovations, ref ti pa# 202311211204. | $11,203 |
| [202401294795](https://www.permitgraph.org/p/202401294795) | Jan 29, 2024 | Completed: final sign-off Jun 2024 | [120 Kearny St](https://www.permitgraph.org/a/0292/008) | 27/f-ste 2700: modification to air distribution system in tenant space to suite architectural renovations, ref ti pa# 202311211257. | $48,834 |
| [202401294790](https://www.permitgraph.org/p/202401294790) | Jan 29, 2024 | Completed: final sign-off Mar 2024 | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | install variable frequency drives on existing supply fans. no other modifications to the buildings existing mechanical system are included | $31,698 |
| [202401123873](https://www.permitgraph.org/p/202401123873) | Jan 12, 2024 | Completed: final sign-off May 2024 | [650 California St](https://www.permitgraph.org/a/0241/025) | 27/f: ti using the (e) base building hvac system. modifications to the air distribution system in the tenant space to suit architectural renovations, including installation of new vav boxes and insta… | $69,848 |
| [202311100583](https://www.permitgraph.org/p/202311100583) | Nov 10, 2023 | Completed: final sign-off Mar 2024 | [425 California St](https://www.permitgraph.org/a/0260/001) | 22nd fl - ti project using the (e) base building hvac system modificaitons to the air distribution system in the tenant space to suit architectural renovations, including replacement of vav dual duct… | $84,239 |
| [202310058111](https://www.permitgraph.org/p/202310058111) | Oct 5, 2023 | Completed: final sign-off Jan 2024 | [1 Lombard St](https://www.permitgraph.org/a/0081/001) | boiler replacement. | $150,000 |
| [202308255237](https://www.permitgraph.org/p/202308255237) | Aug 25, 2023 | Completed: final sign-off Oct 2023 | [300 Clay St](https://www.permitgraph.org/a/0204/021) | document the previous installtion of variable frequency drives on e supply fans as request by fire life safety contractor. installation of variable frequency drives was by others. no modifications to… | $1,000 |
| [202307111856](https://www.permitgraph.org/p/202307111856) | Jul 11, 2023 | Never finaled: issued Jul 2023, no final | [1074 Connecticut St](https://www.permitgraph.org/a/4220A/001) | patch and paint drywall, repair tile in restroom, weatherproof tub and replace window in kitchen to match existing to comply with nov# 202291369. | $5,000 |
| [202307111824](https://www.permitgraph.org/p/202307111824) | Jul 11, 2023 | Completed: final sign-off Jan 2024 | [699 08th St](https://www.permitgraph.org/a/3783/009) | replace (e) fuel oil pipe with new. | $179,620 |
| [202306099650](https://www.permitgraph.org/p/202306099650) | Jun 9, 2023 | Completed: final sign-off Dec 2023 | [250 Clay St](https://www.permitgraph.org/a/0204/023) | replace (2) 20 ton split-system dx units with (2) new 20 ton packaged rooftop cooling only ac units, miscellaneous duct work modifications | $197,568 |
| [202302021258](https://www.permitgraph.org/p/202302021258) | Feb 2, 2023 | Never finaled: issued Feb 2023, no final | [455 Market St](https://www.permitgraph.org/a/3709/012) | hvac tenant improvement install new ater source heat pump, install ceiling plunum, mounted exhaust fan install carbon dioxide sensor. convert e control system to ddc. provide air balancer. base build… | $149,417 |
| [202212198623](https://www.permitgraph.org/p/202212198623) | Dec 19, 2022 | Never finaled: issued Dec 2022, no final | [255 California St](https://www.permitgraph.org/a/0262/013) | #850: hvac modification to support interior t.i. no new vav terminal units. | $8,521 |
| [202212168530](https://www.permitgraph.org/p/202212168530) | Dec 16, 2022 | Completed: final sign-off Sep 2023 | [655 Beach St](https://www.permitgraph.org/a/0024/025) | replace (e) colling towner with new. replacement tower in an exact factory replacement with the same operating wirght and electrical chractristcs. chemical treatment is existing to remain. | $207,091 |
| [202212027530](https://www.permitgraph.org/p/202212027530) | Dec 2, 2022 | Completed: final sign-off Apr 2023 | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | replacement of outside air fan oaf-1 with similar airflow and power requirements | $177,539 |
| [202207017655](https://www.permitgraph.org/p/202207017655) | Jul 1, 2022 | Never finaled: issued Jul 2022, no final | [255 California St](https://www.permitgraph.org/a/0262/013) | 8th fl ste 800: hvac modifications to support interior tenant improvements. new grills, registers, diffusers and ductwork. ref arch 202206277197. | $149,397 |
| [202206146256](https://www.permitgraph.org/p/202206146256) | Jun 14, 2022 | Completed: final sign-off Oct 2022 | [101 Montgomery St](https://www.permitgraph.org/a/0288/031) | ste f: replace 1 4-ton 4-pipe fan coil unit. | $46,323 |
| [202206075756](https://www.permitgraph.org/p/202206075756) | Jun 7, 2022 | Completed: final sign-off Aug 2022 | [101 Montgomery St](https://www.permitgraph.org/a/0288/031) | 8th flr ste 888 - hvac modifications to support interior heating & cooling system by installing (1) vav box. | $34,607 |
| [202206065643](https://www.permitgraph.org/p/202206065643) | Jun 6, 2022 | Completed: final sign-off Jan 2023 | [1 Maritime Pz](https://www.permitgraph.org/a/0204/021) | g/f & 26/f - roof: install variable frequency drives on (e) supply fans. no other modifications to the buildings 9e) mechanical system are included. maher n/a. | $24,734 |
| [202205265081](https://www.permitgraph.org/p/202205265081) | May 26, 2022 | Completed: final sign-off Apr 2023 | [1 Maritime Pz](https://www.permitgraph.org/a/0204/021) | fire rated enclosure for flue pipe. ref 202203018952 |  |
| [202204122043](https://www.permitgraph.org/p/202204122043) | Apr 12, 2022 | Completed: final sign-off Jun 2022 | [301 Howard St](https://www.permitgraph.org/a/3738/011) | added controls for (e) exhaust fan for fire department override. | $5,000 |
| [202203018952](https://www.permitgraph.org/p/202203018952) | Mar 1, 2022 | Completed: final sign-off Apr 2023 | [1 Maritime Pz](https://www.permitgraph.org/a/0204/021) | 2 (e) steam boilers to be removed and replaced. add 4 (n) heating hot water boilers, 3 (n) air separators, 2 (n) heat exchangers, 6 (n) pumps, 2 (n) heating system expansion tanks to be provided to r… | $2,128,734 |
| [202111021640](https://www.permitgraph.org/p/202111021640) | Nov 2, 2021 | Completed: final sign-off Jan 2022 | [601 California St](https://www.permitgraph.org/a/0258/032) | demo and remove (e) ductwork, furnish and install new dual duct vav terminal. modify (e) duct system. ref pa #2021 0910 8140 | $13,820 |
| [202110271264](https://www.permitgraph.org/p/202110271264) | Oct 27, 2021 | Completed: final sign-off Jan 2022 | [333 Market St](https://www.permitgraph.org/a/3710/020) | adding 1 new heat pump to 6th fl. no new fsd's are being added. | $41,342 |
| [202110140475](https://www.permitgraph.org/p/202110140475) | Oct 14, 2021 | Never finaled: issued Oct 2021, no final | [425 California St](https://www.permitgraph.org/a/0260/001) | install new 1 ton mini split sytem to cool existing it closet. it closet is normally unoccupied. | $16,494 |
| [202107285314](https://www.permitgraph.org/p/202107285314) | Jul 28, 2021 | Completed: final sign-off Feb 2022 | [1601 19th Av](https://www.permitgraph.org/a/1924/004) | replace 2 castiron hot water boilers with 2 new castiron boilers. reconfigure piping to accommodate new boilers. install new 80 gallon vertical buffer tank and pipe to the new boiler. | $126,019 |
| [202107144330](https://www.permitgraph.org/p/202107144330) | Jul 14, 2021 | Completed: final sign-off Sep 2021 | [2325 Noriega St](https://www.permitgraph.org/a/2067/006) | replace 4 existing rooftop package units with new of same make and capacity. replacement unit weights are within 5% of the existing unit weight. | $28,913 |
| [202107083976](https://www.permitgraph.org/p/202107083976) | Jul 8, 2021 | Completed: final sign-off Oct 2021 | [123 Townsend St](https://www.permitgraph.org/a/3794/010) | roof top: replace (1) heating hot water boiler w/ (2) (n) higher officiency boilers of identical capacity, miscellaneous piping, and miscellaneous hydronic accessories. | $134,078 |
| [202106172681](https://www.permitgraph.org/p/202106172681) | Jun 17, 2021 | Completed: final sign-off Feb 2022 | [655 Montgomery St](https://www.permitgraph.org/a/0208/028) | replacement of (2) gas fired boilers with 3 condensing gas fired boilers. hhw pumps (2) replaced with exact replacement as well as hhwp-3 replaced with pump sized for design conditions. replace expan… | $160,607 |
| [202106152490](https://www.permitgraph.org/p/202106152490) | Jun 15, 2021 | Never finaled: issued Jun 2021, no final | [1656 California St](https://www.permitgraph.org/a/0643/017) | install (1) 3 ton mini split cooling systems to serve it closet. | $15,756 |
| [202106041702](https://www.permitgraph.org/p/202106041702) | Jun 4, 2021 | Completed: final sign-off Nov 2021 | [410 Townsend St](https://www.permitgraph.org/a/3785/002A) | replace: 1 cooling tower with new of same capacity, 1 boiler with new of the same capacity,1 primary pump of same capacity, 2 condenser water pumps with new of same capacity. | $220,000 |
| [202106011362](https://www.permitgraph.org/p/202106011362) | Jun 1, 2021 | Never finaled: issued Jun 2021, no final | [1171 Mission St](https://www.permitgraph.org/a/3727/233) | install new design build hvac system to serve 3/f, install (1) make-up air fan & 24 tons of variable refrigerant flow. provide/install (6) fan coils | $187,060 |
| [202105180520](https://www.permitgraph.org/p/202105180520) | May 18, 2021 | Never finaled: issued Sep 2021, no final | [434 Ellis St](https://www.permitgraph.org/a/0323/009) | minor non structural demo. new exterior rooftop mechanical unit to replace existing. new mep work to tie to (e) bldg utilities. no change of building use. no change to (e) parking (no off street park… | $349,413 |
| [202012140931](https://www.permitgraph.org/p/202012140931) | Dec 14, 2020 | Never finaled: issued Feb 2021, no final | [235 Pine St](https://www.permitgraph.org/a/0267/015) | hvac modifications to support interior tenant improvements. ref pa# 202008061204. | $71,280 |
| [202012019993](https://www.permitgraph.org/p/202012019993) | Dec 1, 2020 | Completed: final sign-off Jul 2021 | [275 Battery St](https://www.permitgraph.org/a/0238/001) | 31/f & r: replace 2 heating hot water boilers with 4 new higher efficiency biolers, misco piping and misc hyronic accessories. maher n/a | $460,847 |
| [202009265161](https://www.permitgraph.org/p/202009265161) | Sep 26, 2020 | Completed: final sign-off Jan 2021 | [465 California St](https://www.permitgraph.org/a/0260/015) | install new vrf ductless system as part of ti. | $185,967 |
| [202008222421](https://www.permitgraph.org/p/202008222421) | Aug 22, 2020 | Completed: final sign-off Feb 2022 | [100 Montgomery St](https://www.permitgraph.org/a/0289/005) | 18th fl: hvac air distribution modifications to support interior tenant improvements | $103,159 |
| [202007220653](https://www.permitgraph.org/p/202007220653) | Jul 22, 2020 | Completed: final sign-off Dec 2020 | [180 Montgomery St](https://www.permitgraph.org/a/0289/009) | #1850: hvac air distribution modification for t.i. | $30,001 |
| [202007210616](https://www.permitgraph.org/p/202007210616) | Jul 21, 2020 | Completed: final sign-off Apr 2021 | [555 Montgomery St](https://www.permitgraph.org/a/0227/048) | 12th fl: hvac modifications to support interior ti. ref atch ti pa# 202002134365. | $139,100 |
| [202006028064](https://www.permitgraph.org/p/202006028064) | Jun 2, 2020 | Completed: final sign-off Nov 2020 | [101 Henry Adams St](https://www.permitgraph.org/a/3915/001) | replace one heating hot water boiler, primary pumps, and misc. hydronic accessories. | $129,870 |
| [202005137518](https://www.permitgraph.org/p/202005137518) | May 13, 2020 | Completed: final sign-off Jun 2022 | [301 Howard St](https://www.permitgraph.org/a/3738/011) | replace existing chillers and chilled water pumping system. provide new energy management system and intergrate into existing system | $1,100,000 |
| [202002194824](https://www.permitgraph.org/p/202002194824) | Feb 19, 2020 | Expired or cancelled: cancelled Jan 2026 | [101 02nd St](https://www.permitgraph.org/a/3721/089) | suite 800: install water source heat pump to serve existing idf closet. | $39,408 |
| [202001282885](https://www.permitgraph.org/p/202001282885) | Jan 28, 2020 | Never finaled: issued Feb 2020, no final | [300 Montgomery St](https://www.permitgraph.org/a/0260/010) | mech for suite 450: furnish & install new air distribution with new air outlets, new air conditioning unit and new return fan. ref pa #201909091019 | $361,480 |
| [202001282890](https://www.permitgraph.org/p/202001282890) | Jan 28, 2020 | Completed: final sign-off Feb 2020 | [425 California St](https://www.permitgraph.org/a/0260/001) | mech for 1400: new air distribution added to serve new space, new vav boxes (10), and (1) new fsd added. ref pa #201910174872. | $109,879 |
| [201912260693](https://www.permitgraph.org/p/201912260693) | Dec 26, 2019 | Completed: final sign-off Aug 2020 | [1 La Avanzada](https://www.permitgraph.org/a/2724/003) | replace existing split-systm with identical unit by same manufacturer | $84,804 |
| [201911258132](https://www.permitgraph.org/p/201911258132) | Nov 25, 2019 | Completed: final sign-off Aug 2020 | [201 Spear St](https://www.permitgraph.org/a/3741/032) | roof - replace (e) supply fan with new unit (roof) of identical capacity and reconnect existing duct work | $199,000 |
| [201911076711](https://www.permitgraph.org/p/201911076711) | Nov 7, 2019 | Completed: final sign-off Feb 2020 | [425 California St](https://www.permitgraph.org/a/0260/001) | ste: 300 - ref pa# 201908169025; install (10) new vav boxes, (1) new fsd, and new air distribution to serve new space plan. n/a maher | $122,064 |
| [201910295828](https://www.permitgraph.org/p/201910295828) | Oct 29, 2019 | Completed: final sign-off Jun 2020 | [201 California St](https://www.permitgraph.org/a/0262/021) | replace existing evaporative condenser with a new unit of equal capacity and similar footprint, per plans. modify existing piping to accomodate new condenser. in kind replacement. | $285,000 |
| [201910184922](https://www.permitgraph.org/p/201910184922) | Oct 18, 2019 | Completed: final sign-off Mar 2020 | [180 Montgomery St](https://www.permitgraph.org/a/0289/009) | 19/f ste1900: modify duct work for office, add (1) diffuser, insulate ductowrk | $15,469 |
| [201910174799](https://www.permitgraph.org/p/201910174799) | Oct 17, 2019 | Completed: final sign-off Sep 2021 | [300 Clay St](https://www.permitgraph.org/a/0204/021) | 1/f & 26f: install variable frequency motor drives (vfd) on (e) supply fans, no other modifcations to the (e) mechanical systems are included. | $45,475 |
| [201910114267](https://www.permitgraph.org/p/201910114267) | Oct 11, 2019 | Completed: final sign-off Dec 2019 | [601 California St](https://www.permitgraph.org/a/0258/032) | 4/f: ref pa# 201909272992; relocate (e) duct work, add new ductwork, air devices, and terminal units as required to accommodate floor plan changes. maher n/a. | $8,651 |
| [201910114266](https://www.permitgraph.org/p/201910114266) | Oct 11, 2019 | Never finaled: issued Oct 2019, no final | [535 Pacific Av](https://www.permitgraph.org/a/0176/024) | ref pa# 201908027715; furnish & install (1) nine zone vav distriburion system | $136,668 |
| [201910114272](https://www.permitgraph.org/p/201910114272) | Oct 11, 2019 | Expired or cancelled: cancelled Jan 2026 | [1 La Avanzada](https://www.permitgraph.org/a/2724/003) | remove & replace (1) split system | $79,084 |
| [201909192116](https://www.permitgraph.org/p/201909192116) | Sep 19, 2019 | Expired or cancelled: expired Jul 2026 | [99 Rhode Island St](https://www.permitgraph.org/a/3912/002) | replace 1 heating hot water boiler, distribution pumps and misc hydront accessories. n/a for maher | $42,000 |
| [201909192121](https://www.permitgraph.org/p/201909192121) | Sep 19, 2019 | Expired or cancelled: cancelled Feb 2021 | [201 California St](https://www.permitgraph.org/a/0262/021) | furnish and install 1 inline fan on spring isolators. furnish and install new ducting from the fan to 2 supply slot grilles. ref app#201902082459 | $25,000 |
| [201908128541](https://www.permitgraph.org/p/201908128541) | Aug 12, 2019 | Completed: final sign-off Dec 2019 | [180 Montgomery St](https://www.permitgraph.org/a/0289/009) | furnish and install four cooling vav convert controls to ddc. replace diffusers with supply slots. furnish & install 3 transfer air sound boots. insulate concealed ductwork & hhw piping. ref 20190617… | $29,000 |
| [201907317469](https://www.permitgraph.org/p/201907317469) | Jul 31, 2019 | Completed: final sign-off Sep 2020 | [601 California St](https://www.permitgraph.org/a/0258/032) | 4th flr - r&r vav boxes ref 201902052077 | $198,721 |
| [201906123233](https://www.permitgraph.org/p/201906123233) | Jun 12, 2019 | Completed: final sign-off Aug 2019 | [555 Montgomery St](https://www.permitgraph.org/a/0227/048) | demo (e) system, install 19 new vav's and associated duct and registers, install odc controls on vav's and install 1 new fsd for return air. ref pa 201904188368. | $196,400 |
| [201904188311](https://www.permitgraph.org/p/201904188311) | Apr 18, 2019 | Never finaled: issued Apr 2019, no final | [45 Fremont St](https://www.permitgraph.org/a/3710/019) | replace (e) 3-ton water source heat pump with new n/a maher | $29,684 |
| [201904107547](https://www.permitgraph.org/p/201904107547) | Apr 10, 2019 | Completed: final sign-off Aug 2019 | [123 Mission St](https://www.permitgraph.org/a/3717/022) | 29th fl - replace (2) boilers & distribution pumps and other hydronic specialties | $246,000 |
| [201902041973](https://www.permitgraph.org/p/201902041973) | Feb 4, 2019 | Completed: final sign-off Oct 2019 | [235 Pine St](https://www.permitgraph.org/a/0267/015) | 15th floor: ductwork modifications to support interior t.i. ref app#201901100026. n/a for maher | $17,768 |
| [201901311673](https://www.permitgraph.org/p/201901311673) | Jan 31, 2019 | Completed: final sign-off Apr 2019 | [33 New Montgomery St](https://www.permitgraph.org/a/3707/062) | ref pa# 201812289310; revise low pressure air distribution for new partition layout. replace medium pressure flex duct on svav's, install exhaust fan and 2 ton floor mounted wshp | $40,123 |

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 23 November 2026.
This is the text of https://www.permitgraph.org/contractor/matrix-hg-inc-812232.