Back to bathroom remodel contractors
K 2 Builders Inc
- Based in
- San Francisco
- On San Francisco permits
- Dec 2004 to Aug 2026
- Last 24 months
- 20 permits filed
165 permits since 2000: 133 completed, 7 in progress, 16 never finaled, 9 expired or cancelled.
Of the 16 never-finaled permits, 3 are 3 to 5 years old, 6 are 5 to 10 years old, 7 are over 10 years old.
This is the city’s permit record, not a license check. It does not show whether the state license is active, bonded or insured. How to read these records
Permits filed each year
How long permits take
Each point is the quarter the permits were filed, for bathroom remodel across San Francisco. A median counts only permits that have finished, so the shaded recent quarters look faster than they will end up: their slow permits have not finished yet. Hover a point for the slowest 10%. Gaps mean fewer than 5 permits. A rise in the issue line is the city’s review backlog, not the contractor.
Bathroom remodel permits
31 bathroom remodel permits: 25 completed, 2 in progress, 3 never finaled, 1 expired or cancelled. Typically 0 days from filing to permit and 445 days from permit to final inspection.
| Filed | Outcome | Address | Work described on the permit | Declared cost |
|---|---|---|---|---|
| Aug 31, 2026 | In progress issued Sep 2026 | 980 Ashbury St | first floor: renovate (e) kitchen, relocate 1/2 bath. @nd floor: renovate(2)(e) bathrooms and laundry area. renovate principal bedroom and closet area. remove (e) masonary chimneyDetails
first floor: renovate (e) kitchen, relocate 1/2 bath. @nd floor: renovate(2)(e) bathrooms and laundry area. renovate principal bedroom and closet area. remove (e) masonary chimney | $130,000 |
| May 19, 2026 | In progress issued May 2026 | 1522 Chestnut St | kitchen and bath remodel. kitchen: remove e drywall to repalace in kind. remove and replace existing fixtures. bath: replace existing fixtures and finishes in kind. no wall changes or relocation.Details
kitchen and bath remodel. kitchen: remove e drywall to repalace in kind. remove and replace existing fixtures. bath: replace existing fixtures and finishes in kind. no wall changes or relocation. | $9,500 |
| Mar 10, 2026 | Completed final sign-off Oct 2026 | 11 Jordan Av | remodel third floor bathroom inn kind. replace all fixtures in kind. no change to fixture locations. strip finishes & replace as existing. no exterior work. approx. 48 sq ft.Details
remodel third floor bathroom inn kind. replace all fixtures in kind. no change to fixture locations. strip finishes & replace as existing. no exterior work. approx. 48 sq ft. | $3,000 |
| Jul 22, 2022 | Completed final sign-off Apr 2024 | 258 09th St | change of use from warehouse s-2 to industrial f-2. new sprinkler system & new bathroom & showerDetails
change of use from warehouse s-2 to industrial f-2. new sprinkler system & new bathroom & shower | $400,000 |
| Oct 26, 2021 | Completed final sign-off Feb 2023 | 74 Toledo Wy | interior remodel of one kitchen and one bathroom. remove and replace fixtures and finishes, new tile, new cabinets, no structural work.Details
interior remodel of one kitchen and one bathroom. remove and replace fixtures and finishes, new tile, new cabinets, no structural work. | $4,000 |
| Oct 12, 2021 | Completed final sign-off Dec 2022 | 2674 Filbert St | interior remodel: replacement of (e) g/f bathroom, add new dry sauna, new gas fireplace, new replacement of (e) door and (e) windows with new french doors at rear balcony, replacement of 3' of (e) wood slat exterior stair enclosure with new glass view panels. no change to habitable square footage.Details
interior remodel: replacement of (e) g/f bathroom, add new dry sauna, new gas fireplace, new replacement of (e) door and (e) windows with new french doors at rear balcony, replacement of 3' of (e) wood slat exterior stair enclosure with new glass view panels. no change to habitable square footage. | $60,000 |
| Aug 17, 2021 | Completed final sign-off Apr 2023 | 1998 Broadway | one kitchen and two bath remodel : remove and replace kitchen cabinets, countertops and appliances. remove and replace tile in 2 bathrooms with 2 vanities, countertop and plumbing fixtures. no structural changes. plumbing and electrical under separate permit. must comply with sffc 1103.7.6.1Details
one kitchen and two bath remodel : remove and replace kitchen cabinets, countertops and appliances. remove and replace tile in 2 bathrooms with 2 vanities, countertop and plumbing fixtures. no structural changes. plumbing and electrical under separate permit. must comply with sffc 1103.7.6.1 | $200,000 |
| Jul 9, 2021 | Completed final sign-off Dec 2022 | 216 Yerba Buena Av | in-kind remodeling of 1 kitchen(s) in 1st fl and in-kind remodeling of 2 bathroom(s) in 1st fl with 0 shower pan(s).Details
in-kind remodeling of 1 kitchen(s) in 1st fl and in-kind remodeling of 2 bathroom(s) in 1st fl with 0 shower pan(s). | $31,800 |
| Jun 14, 2021 | Completed final sign-off Sep 2022 | 210 Yerba Buena Av | add habitable space to 1st floor/garage level-media room, bath & 2 bedrooms, rebuild interiror stair connecting levels 1 & 2. 2nd floor renovation:remodel kitchen & bathrooms, remove bay @ rear. rear yard deck @ grade.Details
add habitable space to 1st floor/garage level-media room, bath & 2 bedrooms, rebuild interiror stair connecting levels 1 & 2. 2nd floor renovation:remodel kitchen & bathrooms, remove bay @ rear. rear yard deck @ grade. | $253,000 |
| Apr 29, 2021 | Completed final sign-off Apr 2023 | 2344 15th St | new post & beam in garage. conversion of (e) unconditioned 1st fl space into new bathroom. renovate 2nd & 3rd fl bathrooms. new skylights & roof.Details
new post & beam in garage. conversion of (e) unconditioned 1st fl space into new bathroom. renovate 2nd & 3rd fl bathrooms. new skylights & roof. | $85,000 |
| Aug 5, 2020 | Completed final sign-off Sep 2022 | 1285 08th Av | rev to #201707212632. 1/f revise entry to unit 9; revise kitchen layout for unit 10; revise ramp to be stairs outside of unit 10. revise laundry locations. mezz fl incorporate e bedrm from unit 4 into unit 11; revise kitch/bath/bedrm layout of unit 11. 2/f infill e stair opening to bedrm at mezz flDetails
rev to #201707212632. 1/f revise entry to unit 9; revise kitchen layout for unit 10; revise ramp to be stairs outside of unit 10. revise laundry locations. mezz fl incorporate e bedrm from unit 4 into unit 11; revise kitch/bath/bedrm layout of unit 11. 2/f infill e stair opening to bedrm at mezz fl | |
| Nov 2, 2018 | Completed final sign-off Jun 2023 | 55 Woodland Av | kitchen cabinets w/ top and fixtures, 2.5 bathroom cabinets, tile, fittings. electrical & plumbing under seperate permitDetails
kitchen cabinets w/ top and fixtures, 2.5 bathroom cabinets, tile, fittings. electrical & plumbing under seperate permit | $30,000 |
| May 9, 2018 | Completed final sign-off Jan 2019 | 1998 Broadway | no walls moved, removed or added. all (e) layouts to remain unchanged. remove & replace tile in 2 bathrooms with 2 vanities, countertops & plumbing fixtures. no structural changes, all fixtures to remain in current location.Details
no walls moved, removed or added. all (e) layouts to remain unchanged. remove & replace tile in 2 bathrooms with 2 vanities, countertops & plumbing fixtures. no structural changes, all fixtures to remain in current location. | $165,000 |
| Oct 31, 2017 | Completed final sign-off Jan 2018 | 330 Fillmore St | in unit # 2 kitchen repair cabinets & countertop in kind, bath repair vanity & tiles in kindDetails
in unit # 2 kitchen repair cabinets & countertop in kind, bath repair vanity & tiles in kind | $8,000 |
| Jul 31, 2017 | Never finaled issued Jul 2017, no final | 1998 Broadway | unit 805: interior remodel: r/r kitchen cabinets, counter tops & appliances. r/r tile in 2 bathrooms w/ 2 vanities, counter tops & plumbing fixtures. no structural changes; plumbing & electrical udner sep permits.Details
unit 805: interior remodel: r/r kitchen cabinets, counter tops & appliances. r/r tile in 2 bathrooms w/ 2 vanities, counter tops & plumbing fixtures. no structural changes; plumbing & electrical udner sep permits. | $65,000 |
| Jul 21, 2017 | Completed final sign-off Sep 2022 | 1285 08th Av | addition of (2) new units on 1st & mezzanine flrs per ord 162-16. total of: (2) living rooms, (4) bedrooms, (3) bathrooms, (2) offices, (2) kitchens, (1) powder room. include revision to soft story p.a.# 2017-0823-5637.Details
addition of (2) new units on 1st & mezzanine flrs per ord 162-16. total of: (2) living rooms, (4) bedrooms, (3) bathrooms, (2) offices, (2) kitchens, (1) powder room. include revision to soft story p.a.# 2017-0823-5637. | $100,000 |
| Jun 26, 2017 | Completed final sign-off Sep 2022 | 1285 08th Av | addition of one (n) unit on 1st flr per ord #162-16. (n) unit#9 = 305 sq. ft w/ one kitchen, one bathroom.Details
addition of one (n) unit on 1st flr per ord #162-16. (n) unit#9 = 305 sq. ft w/ one kitchen, one bathroom. | $60,000 |
| Oct 13, 2016 | Never finaled issued Oct 2016, no final | 338 Fillmore St | apt 5: repair/upgrade 2 bathroom in-kind due to tenant damage: shower door, tub surround, linoleum flooring, medicine cabinet, vanities, & misc item. patch & repair wall finishes through unit.Details
apt 5: repair/upgrade 2 bathroom in-kind due to tenant damage: shower door, tub surround, linoleum flooring, medicine cabinet, vanities, & misc item. patch & repair wall finishes through unit. | $6,000 |
| May 19, 2016 | Completed final sign-off Jun 2017 | 1625 Larkin St | unit a: remove and replace kitchen cabinets, countertop and floor coverings in unit #a. remove non-strictural, non-load bearing wall between kitchen and hall. retile bathroom; repair damaged lath and plaster. new appliances and bathroom fixtures.Details
unit a: remove and replace kitchen cabinets, countertop and floor coverings in unit #a. remove non-strictural, non-load bearing wall between kitchen and hall. retile bathroom; repair damaged lath and plaster. new appliances and bathroom fixtures. | $17,500 |
| Mar 21, 2016 | Completed final sign-off Jun 2017 | 1625 Larkin St | restore to wood double hung inkind replacement of 56 paintable sash windows - remove and replace kitchen cabinets and counters in units d, f anf g - retile bath rooms in units d, f and g.Details
restore to wood double hung inkind replacement of 56 paintable sash windows - remove and replace kitchen cabinets and counters in units d, f anf g - retile bath rooms in units d, f and g. | $52,000 |
| Feb 18, 2016 | Never finaled issued Mar 2016, no final | 2645 Leavenworth St | remodel 2nd flr unit only: add one bathroom,one powder room,remodel kitchen, existing bathroom & hallway. no exterior work on additional floor area; maher n/aDetails
remodel 2nd flr unit only: add one bathroom,one powder room,remodel kitchen, existing bathroom & hallway. no exterior work on additional floor area; maher n/a | $100,000 |
| Aug 15, 2014 | Completed final sign-off Dec 2014 | 2139 Green St | #f-revision to #2014.0521.6442: relocate 2 non-bearing,non struct walls in master bath;chip out 12"w x 10'l trench slab on grade to allow for relocation sanitary lines in guest bath; replace tub in ma. bath w/ shower.remove (e) wood burning fireplace & replace w/new gas burning & flue,remodel kitchDetails
#f-revision to #2014.0521.6442: relocate 2 non-bearing,non struct walls in master bath;chip out 12"w x 10'l trench slab on grade to allow for relocation sanitary lines in guest bath; replace tub in ma. bath w/ shower.remove (e) wood burning fireplace & replace w/new gas burning & flue,remodel kitch | $250,000 |
| May 21, 2014 | Completed final sign-off Dec 2014 | 2139 Green St | work done in unit # f only remove & replace kitchen cabinets, countertops, & appliances, retile 2 bathroom & remove/replace bathroom fixtueres no structural work , electrical & plumbing under separate permits.Details
work done in unit # f only remove & replace kitchen cabinets, countertops, & appliances, retile 2 bathroom & remove/replace bathroom fixtueres no structural work , electrical & plumbing under separate permits. | $30,000 |
| Mar 23, 2012 | Completed final sign-off May 2014 | 60 Gates St | existing spaces shall be completely remodeled with all new finishes, kitchen & bathroom cabinets fixtures, etc. new bathroom and replace concrete slab on 1st floor.Details
existing spaces shall be completely remodeled with all new finishes, kitchen & bathroom cabinets fixtures, etc. new bathroom and replace concrete slab on 1st floor. | $40,000 |
| Nov 3, 2011 | Completed final sign-off Mar 2015 | 672 Peralta Av | remodel by raising upper 2 floors 5'-6", new floor plans, bathrooms, remodel roof, new roof terrace. all new finishes.Details
remodel by raising upper 2 floors 5'-6", new floor plans, bathrooms, remodel roof, new roof terrace. all new finishes. | $140,000 |
| Feb 9, 2011 | Completed final sign-off Aug 2011 | 8 Jordan Av | interior non-struct. unit renovation incl.: replacement of kit. cab., counter & appliances; 2-bathrms. 1-removal & replacement of tile & fixtures; addition of (n) master bathrm. & walk-in-clo. (n) entry closet. adjust non-load bearing walls in hall. clo. for (n) master bath elec., plumb,sep permitDetails
interior non-struct. unit renovation incl.: replacement of kit. cab., counter & appliances; 2-bathrms. 1-removal & replacement of tile & fixtures; addition of (n) master bathrm. & walk-in-clo. (n) entry closet. adjust non-load bearing walls in hall. clo. for (n) master bath elec., plumb,sep permit | $40,000 |
| Feb 9, 2011 | Completed final sign-off Aug 2011 | 8 Jordan Av | interior, non-struction unit renovation including including: 1-replacement of kitchen cabinets, counter & appliances; 2-bathroom one removal & replacement of tile & fixtures; 3-additions of (n) master bathroom & walk-in closet & (n) entry closet. adjust non-load bearing walls in hall closet for (n).Details
interior, non-struction unit renovation including including: 1-replacement of kitchen cabinets, counter & appliances; 2-bathroom one removal & replacement of tile & fixtures; 3-additions of (n) master bathroom & walk-in closet & (n) entry closet. adjust non-load bearing walls in hall closet for (n). | $40,000 |
| Nov 17, 2010 | Expired or cancelled expired Nov 2022 | 676 Peralta Av | replace bath fixutres, retile, repaint, all fixtures remin in same location. remodel kitchen, replace cabinets, countertops, fixtures, remain in same locationDetails
replace bath fixutres, retile, repaint, all fixtures remin in same location. remodel kitchen, replace cabinets, countertops, fixtures, remain in same location | $18,000 |
| Jul 9, 2010 | Completed final sign-off Sep 2010 | 1325 Indiana St | unit # 116: re-install walls & fixtures to a second bathroom that the previous owner closed up (all units in the building have this 2nd bath in the exact same layout i am proposing). we are also making a storage closet.Details
unit # 116: re-install walls & fixtures to a second bathroom that the previous owner closed up (all units in the building have this 2nd bath in the exact same layout i am proposing). we are also making a storage closet. | $9,300 |
| Jun 25, 2009 | Completed final sign-off Dec 2009 | 75 Roosevelt Wy | remove gas fire place and shelves and walk in unit1. remodel unit 2 bathrm, kitch,new bathrm and w/d closet.elec/plbg work. new wood flooring. all int.work. enlarge sghower in unit 3 in master bath. repair dryrot wall and new roofing in light well 2nd flDetails
remove gas fire place and shelves and walk in unit1. remodel unit 2 bathrm, kitch,new bathrm and w/d closet.elec/plbg work. new wood flooring. all int.work. enlarge sghower in unit 3 in master bath. repair dryrot wall and new roofing in light well 2nd fl | $80,000 |
| Mar 19, 2009 | Completed final sign-off Dec 2009 | 75 Roosevelt Wy | interior work in unit #3 only top floor flat interior work : remodel 2 bathrooms layout and replacement of kitchen cabinets, appliances & finishes, also replacement of all exterior windows in kind.Details
interior work in unit #3 only top floor flat interior work : remodel 2 bathrooms layout and replacement of kitchen cabinets, appliances & finishes, also replacement of all exterior windows in kind. | $80,000 |