8 permits since 2000: 2 completed, 3 in progress, 3 never finaled. Typically 117 days from filing to permit and 65 days from permit to final inspection. Of the 3 never-finaled permits, 3 are 3 to 5 years old. 3 were filed but never issued.

- Based in: San Diego
- On San Francisco permits: Jun 2022 to Nov 2025
- Last 24 months: 2 permits filed

This is the city's permit record, not a license check. It does not show whether the state license is active, bonded or insured.

## Permits filed each year

| Year | Completed | In progress | Never finaled | Expired or cancelled |
| --- | --- | --- | --- | --- |
| 2022 | 0 | 1 | 2 | 0 |
| 2023 | 0 | 0 | 1 | 0 |
| 2024 | 1 | 1 | 0 | 0 |
| 2025 | 1 | 1 | 0 | 0 |

## Most recent permits

| Permit | Filed | Outcome | Address | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- |
| [S20251107303](https://www.permitgraph.org/p/S20251107303) | Nov 13, 2025 | Completed: final sign-off Dec 2025 | [246 Girard St](https://www.permitgraph.org/a/5980/007) | solar permit: installing 8 solar pv modules, 430 watts per module, total no. of rating 3.44 kw. mounted: roof, ballasted: n, including 1 energy storage unit, with 10 kwh each in capacity, ess units w… |  |
| [S20251010181](https://www.permitgraph.org/p/S20251010181) | Oct 17, 2025 | In progress: filed Oct 2025, not yet issued | [1455 Holloway Av](https://www.permitgraph.org/a/7242/001) | solar permit: installing 12 solar pv modules, 410 watts per module, total no. of rating 4.92 kw. mounted: roof, ballasted: n \| installation of 4.92kw roof-mounted pv system. | $30,470 |
| [202406144516](https://www.permitgraph.org/p/202406144516) | Jun 21, 2024 | Completed: final sign-off Feb 2025 | [191 Gellert Dr](https://www.permitgraph.org/a/7260A/002) | install a roof mounted pv solar system. 5.74kw. | $7,795 |
| [202402095670](https://www.permitgraph.org/p/202402095670) | Feb 9, 2024 | In progress: filed Feb 2024, not yet issued | [2440 Washington St](https://www.permitgraph.org/a/0605/014) | roof mounted 12.96kw solar pv system and (2) lg resu16h - 16kwh batteries | $80,705 |
| [202309277557](https://www.permitgraph.org/p/202309277557) | Sep 27, 2023 | Never finaled: filed Sep 2023, never issued | [212 Genebern Wy](https://www.permitgraph.org/a/5840/003) | roof mounted 6.80kw solar pv system and (2) lg resu16h - 16kwh batteries | $67,462 |
| [202211216925](https://www.permitgraph.org/p/202211216925) | Nov 21, 2022 | In progress: issued Feb 2024 | [427 Buchanan St](https://www.permitgraph.org/a/0841/045) | installation of roof mounted 6.00kw solar pv system. | $23,815 |
| [202207259232](https://www.permitgraph.org/p/202207259232) | Jul 25, 2022 | Never finaled: filed Jul 2022, never issued | [407 Mississippi St](https://www.permitgraph.org/a/4064/035) | installation of 1 lg chem resu 16h battery. battery anchored on garage | $15,000 |
| [202206216719](https://www.permitgraph.org/p/202206216719) | Jun 21, 2022 | Never finaled: filed Jun 2022, never issued | [409 Mississippi St](https://www.permitgraph.org/a/4064/036) | installation of 1 lg chem resu 16h battery. | $15,000 |

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 23 November 2026.