# Dfi Construction Company

Contractor license 902076. San Francisco building permit record since 2000.

- Page: https://www.permitgraph.org/contractor/dfi-construction-company-902076
- JSON: https://www.permitgraph.org/api/contractor?license=902076
- State license record: https://www.cslb.ca.gov/onlineservices/checklicenseII/LicenseDetail.aspx?LicNum=902076

45 permits since 2000: 33 completed, 10 never finaled, 2 expired or cancelled. Typically 7 days from filing to permit and 126 days from permit to final inspection. Of the 10 never-finaled permits, 1 is 5 to 10 years old, 9 are over 10 years old.

- Based in: San Francisco
- On San Francisco permits: Jul 2006 to Mar 2021
- Last 24 months: 0 permits filed

This is the city's permit record, not a license check. It does not show whether the state license is active, bonded or insured.

## Permits filed each year

| Year | Completed | In progress | Never finaled | Expired or cancelled |
| --- | --- | --- | --- | --- |
| 2006 | 1 | 0 | 0 | 0 |
| 2007 | 3 | 0 | 2 | 0 |
| 2008 | 1 | 0 | 1 | 0 |
| 2009 | 6 | 0 | 0 | 2 |
| 2011 | 1 | 0 | 0 | 0 |
| 2013 | 1 | 0 | 1 | 0 |
| 2014 | 0 | 0 | 2 | 0 |
| 2015 | 4 | 0 | 2 | 0 |
| 2016 | 3 | 0 | 1 | 0 |
| 2017 | 9 | 0 | 0 | 0 |
| 2018 | 2 | 0 | 0 | 0 |
| 2019 | 1 | 0 | 1 | 0 |
| 2021 | 1 | 0 | 0 | 0 |

## By project type

| Project type | Permits | Completed | In progress | Never finaled | Expired or cancelled | Typical days to permit | Typical days to final |
| --- | --- | --- | --- | --- | --- | --- | --- |
| Bathroom remodel | 1 | 1 | 0 | 0 | 0 | 110 | 265 |
| Kitchen remodel | 1 | 0 | 0 | 0 | 1 | 11 |  |

## Most recent permits

| Permit | Filed | Outcome | Address | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- |
| [202103106237](https://www.permitgraph.org/p/202103106237) | Mar 10, 2021 | Completed: final sign-off Aug 2022 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | suite 290: remodel of (e) storage space to install new liquid nitrogen freezer storage and supply tanks. new floor finishes, painting. modifications to mep seismic anchorage for new equipment. ok to… | $50,000 |
| [201911127077](https://www.permitgraph.org/p/201911127077) | Nov 12, 2019 | Completed: final sign-off Nov 2021 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | wharfside bldg - 1st fl, suite 1050: remodel of existing office space. scope of work to include selective minor demolition, floor, finishes, painting, ceiling and minor modification to existing mech,… | $120,000 |
| [201909262802](https://www.permitgraph.org/p/201909262802) | Sep 26, 2019 | Never finaled: issued Oct 2019, no final | [185 Berry St](https://www.permitgraph.org/a/3803/005) | wharfside bldg: selective demo & construction of 1 demising wall & relocation of (e) suite entry door btwn (e) garage shuttle elevator lobby & bike storage room on ground fl. no ceiling work to occur… | $5,000 |
| [201809241150](https://www.permitgraph.org/p/201809241150) | Sep 24, 2018 | Completed: final sign-off Oct 2019 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | interior ti - include demo, drywall, glass and new finishes | $314,600 |
| [201809241153](https://www.permitgraph.org/p/201809241153) | Sep 24, 2018 | Completed: final sign-off Oct 2019 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | 4th fl - partial interior ti. including glass partitions, lighting & mec | $60,500 |
| [201709148184](https://www.permitgraph.org/p/201709148184) | Sep 14, 2017 | Completed: final sign-off Mar 2018 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | elevator lobby no.6 on 2nd floor renovation: demo of e doors/frames/hardware and finishes. new doors,frames, hardware finishes. elec,ls, fire prot under sep perm. (e) havac and lighting to remain. ma… | $20,000 |
| [201709148182](https://www.permitgraph.org/p/201709148182) | Sep 14, 2017 | Completed: final sign-off Mar 2018 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | elevator lobby no.6 on 3rd floor renovation: project consists of demo of e eoors/frames/hardware finishes. new doors frames hardware finishes elec, ls, fire protection modifications under sep permit… | $20,000 |
| [201708245739](https://www.permitgraph.org/p/201708245739) | Aug 24, 2017 | Completed: final sign-off Jan 2018 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | #1510- revision to pa#201706219952 includes (n) restroom access upgrade sheet g-105. n/a ordinance #155-13 |  |
| [201707283180](https://www.permitgraph.org/p/201707283180) | Jul 28, 2017 | Completed: final sign-off Aug 2018 | [580 Beach St](https://www.permitgraph.org/a/0011/007) | upgrade two roll-in shower bathrooms, three regular shower bathrooms, restaurant mill works, interior alterations to two suites. no change to lighting, fire sprinklers or hvac. n/a maher | $133,750 |
| [201706219952](https://www.permitgraph.org/p/201706219952) | Jun 21, 2017 | Completed: final sign-off Jan 2018 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | suite #1510: project consists of demo of light fixtures & finishes. construction of interior tenant partitions, doors, frames, power/data, lighting and finishes. mep & life safety & fire protection m… | $30,000 |
| [201703282565](https://www.permitgraph.org/p/201703282565) | Mar 28, 2017 | Completed: final sign-off Aug 2017 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | 4th floor suite 4801 - project consists of demo of partitions, lights, doors/frames. construction of interior tenant partitions, doors/frames, power/data, lighting, ceiling + finishes. plumbing, life… | $203,190 |
| [201703282561](https://www.permitgraph.org/p/201703282561) | Mar 28, 2017 | Completed: final sign-off Aug 2017 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | 6th floor suite 6700 - project consists of demo of partitions, lights, doors/frames. construction of partitions, doors/frames, power/data, lighting, ceiling + finishes. plumbing, life safety + fire p… | $203,190 |
| [201703242326](https://www.permitgraph.org/p/201703242326) | Mar 24, 2017 | Completed: final sign-off Aug 2017 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | ste. #4805: demo of partitions, lights, doors/frames. construction of partitions doors/frames, power data, lighting, ceiling, finishes. plumbing, ls, and fire protection deferred. maher not req | $203,190 |
| [201703242328](https://www.permitgraph.org/p/201703242328) | Mar 24, 2017 | Completed: final sign-off Aug 2017 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | demo of partitions, lights, door frames. new partitions, doors/frames, power data, lighting, ceiling, finishes, plumbing, l/s fire protection modifications under sep permit | $203,190 |
| [201608165065](https://www.permitgraph.org/p/201608165065) | Aug 16, 2016 | Completed: final sign-off Nov 2016 | [750 Battery St](https://www.permitgraph.org/a/0166/008) | 4th flor, suite 420: revision to ref pa 201605248192 to eliminate conf. rm demo add millwork, plumbing & elec maher na |  |
| [201605248192](https://www.permitgraph.org/p/201605248192) | May 24, 2016 | Never finaled: issued May 2016, no final | [750 Battery St](https://www.permitgraph.org/a/0166/008) | ste #420: landlord alterations, demise tenant suite, demolish glass conference room, life safety deferred; maher n/a | $3,850 |
| [201603313653](https://www.permitgraph.org/p/201603313653) | Mar 31, 2016 | Completed: final sign-off Jun 2016 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | ste. 4000: project consist of soft demo only suite 4000. vacant space on 4th fl of wharfside building in china basin. removal of interior doors, partitions, floor finishes, suite elements. no new con… | $92,000 |
| [201603303427](https://www.permitgraph.org/p/201603303427) | Mar 30, 2016 | Completed: final sign-off Oct 2017 | [750 Battery St](https://www.permitgraph.org/a/0166/008) | #101- demolish exterior existing non-accessible doors, install new accessible doors, window, sidelight and hardware. not visable from street. n/a ordinance #155-13 maher not req | $45,312 |
| [201512074264](https://www.permitgraph.org/p/201512074264) | Dec 7, 2015 | Completed: final sign-off Jun 2016 | [750 Battery St](https://www.permitgraph.org/a/0166/008) | full floor tenant improvement. barrier removal at 6th fl toilet rm. n/a ordinance #155-13 | $353,258 |
| [201511172878](https://www.permitgraph.org/p/201511172878) | Nov 17, 2015 | Never finaled: issued Dec 2015, no final | [750 Battery St](https://www.permitgraph.org/a/0166/008) | 3/f -remodel & new finishes to training room, green room and chair room. n/a for maher. life safety deferred. | $200,000 |
| [201511172770](https://www.permitgraph.org/p/201511172770) | Nov 17, 2015 | Completed: final sign-off Nov 2015 | [750 Battery St](https://www.permitgraph.org/a/0166/008) | interior demolition for 6th floor only | $43,500 |
| [201508043324](https://www.permitgraph.org/p/201508043324) | Aug 4, 2015 | Never finaled: issued Oct 2015, no final | [185 Berry St](https://www.permitgraph.org/a/3803/001) | suite 300 -scope to install walls, doors, exit lighting as required for 2 new doors to separate lobby from office space. relocate of light fixture. separate permits for mep, and fire safety | $7,700 |
| [201506259932](https://www.permitgraph.org/p/201506259932) | Jun 25, 2015 | Completed: final sign-off Jul 2016 | [185 Berry St](https://www.permitgraph.org/a/3803/001) | suite #1050 ground floor - consist of partial demo work & construction of new walls & doors of (e) wharfside building in china basin. demo consists of door & partial ceiling removal. new construction… | $120,000 |
| [201502208822](https://www.permitgraph.org/p/201502208822) | Feb 20, 2015 | Completed: final sign-off Aug 2015 | [750 Battery St](https://www.permitgraph.org/a/0166/008) | barrier removal at 3rd floor toilet rooms to meet new 2013 ca. bld. code req.s for assessible low energy automatic door operator. maher not required | $790 |
| [201404012121](https://www.permitgraph.org/p/201404012121) | Apr 1, 2014 | Never finaled: issued Apr 2014, no final | [185 Berry St](https://www.permitgraph.org/a/3803/001) | 5th floor ste 5425/5475/5501 - consists of infilling (3) existing door openings to create (3) separate suites. | $7,500 |
| [201402037608](https://www.permitgraph.org/p/201402037608) | Feb 3, 2014 | Never finaled: issued Mar 2014, no final | [185 Berry St](https://www.permitgraph.org/a/3803/005) | suite #3400, 3450 & 3500- demolition work per ab-17, space to remain vacant. | $40,000 |
| [201308053525](https://www.permitgraph.org/p/201308053525) | Aug 5, 2013 | Never finaled: issued Aug 2013, no final | [185 Berry St](https://www.permitgraph.org/a/3803/005) | 5th floor:demolition work to be performed in suite 5411/5501 a vacant space of extg wharfside bldg at china basin complex. this includes removal of interior doors, partitions, finishes,etc. scope of… | $30,000 |
| [201307111552](https://www.permitgraph.org/p/201307111552) | Jul 11, 2013 | Completed: final sign-off Jan 2014 | [750 Battery St](https://www.permitgraph.org/a/0166/008) | suite #100:not a high rise. t.i. demolish offices ceiling tile and flooring, provide new ceiling, lighting and break room configuration. fire sprinklers and alarm under seperate permit. | $196,738 |
| [201102079734](https://www.permitgraph.org/p/201102079734) | Feb 7, 2011 | Completed: final sign-off Mar 2011 | [2501 Ocean Av](https://www.permitgraph.org/a/7226/022) | repair to exterior wall damaged by vehicle impact to replace 2 cripple blocks, 2x blockage 1st 3 bay on vaener brick wall. | $10,000 |
| [200912163307](https://www.permitgraph.org/p/200912163307) | Dec 16, 2009 | Completed: final sign-off Feb 2010 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | suite 5300: tenant improvement of existing space to include new partitions, doors, and fixtures. fire/life safety under separate permit. | $30,000 |
| [200911191690](https://www.permitgraph.org/p/200911191690) | Nov 19, 2009 | Expired or cancelled: expired Mar 2013 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | 4th floor- # 4815. office ti. remodel of (e) office space to include new kitchen, new non struc interior partitions, new paint, carpet. no exterior work. mep underseparate permit. | $70,000 |
| [200906160517](https://www.permitgraph.org/p/200906160517) | Jun 16, 2009 | Completed: final sign-off Jul 2009 | [185 Berry St](https://www.permitgraph.org/a/3803/001) | 6th floor - new demising wall to demise private office into 2 offices. | $5,000 |
| [200903264913](https://www.permitgraph.org/p/200903264913) | Mar 26, 2009 | Expired or cancelled: expired Oct 2010 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | #3800- demise existing suite into 2 suites. new exit for suite 3800 including new demising partition and rated corridor. lighting, life safety to be under separate permit | $2,000 |
| [200903134079](https://www.permitgraph.org/p/200903134079) | Mar 13, 2009 | Completed: final sign-off Mar 2009 | [101 California St](https://www.permitgraph.org/a/0263/011) | 27th floor -life safety to add five (5) new strobes, one (1) new speaker & relocate one (1) smoke detector and one (1) speaker. | $10,000 |
| [200903134081](https://www.permitgraph.org/p/200903134081) | Mar 13, 2009 | Completed: final sign-off Jul 2009 | [101 California St](https://www.permitgraph.org/a/0263/011) | 1st floor -interior alteration of doors, walls, partitions, & fixtures incl restroom to creat shell for future t.i. under ab-017. | $10,000 |
| [200902242714](https://www.permitgraph.org/p/200902242714) | Feb 24, 2009 | Completed: final sign-off Mar 2009 | [101 California St](https://www.permitgraph.org/a/0263/011) | 27th floor - electrical & mechanical for partial floor, t.i. to reuse existing air handler unit 8 and add new air distribution ductwork, relocate fixtures & add new outlets, remove 2 fsds, refer to a… | $110,000 |
| [200902121996](https://www.permitgraph.org/p/200902121996) | Feb 12, 2009 | Completed: final sign-off Mar 2009 | [101 California St](https://www.permitgraph.org/a/0263/011) | existing office modifications: new walls, doors, floor covering. life safety, mechanical & electrical under separate permit. | $75,125 |
| [200812319402](https://www.permitgraph.org/p/200812319402) | Dec 31, 2008 | Completed: final sign-off Mar 2009 | [50 Fremont St](https://www.permitgraph.org/a/3709/019) | at 24th fl: electrical work & mechanical work for tenant space. ref. #200812198864 | $15,000 |
| [200811136466](https://www.permitgraph.org/p/200811136466) | Nov 13, 2008 | Never finaled: issued Sep 2009, no final | [1345 Turk St](https://www.permitgraph.org/a/0756/001) | demolish a vacant shed. | $9,000 |
| [200711148060](https://www.permitgraph.org/p/200711148060) | Nov 14, 2007 | Completed: final sign-off Jan 2008 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | 3rd floor-office tenant improvement for existing office 3509 | $50,000 |
| [200709284028](https://www.permitgraph.org/p/200709284028) | Sep 28, 2007 | Never finaled: issued Sep 2007, no final | [185 Berry St](https://www.permitgraph.org/a/3803/005) | 2nd floor - office t.i. on the second floor. work incl remove walls and replace new. electrical and mechanical systems. complaint #200720593. | $180,000 |
| [200709203230](https://www.permitgraph.org/p/200709203230) | Sep 20, 2007 | Never finaled: issued Sep 2007, no final | [185 Berry St](https://www.permitgraph.org/a/3803/001) | 2nd floor-interior non-structural demolition of suite 2100 of 2nd floor. office space will remain vacant pending approval of tenant improvement plan. fire safety devices will remain operational and f… | $2,500 |
| [200706042883](https://www.permitgraph.org/p/200706042883) | Jun 4, 2007 | Completed: final sign-off Jul 2008 | [500 Sansome St](https://www.permitgraph.org/a/0206/008) | oti-1, 500 sansome llc, 6th fl, el, me, ls, sp. | $145,400 |
| [200705302536](https://www.permitgraph.org/p/200705302536) | May 30, 2007 | Completed: final sign-off Jun 2007 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | correct ada compliance issues, revision to pa# 2006082506300-re stripe stall and extend ramp curb | $5,000 |
| [200607186914](https://www.permitgraph.org/p/200607186914) | Jul 18, 2006 | Completed: final sign-off Jul 2006 | [185 Berry St](https://www.permitgraph.org/a/3803/005) | renew 200511097782 for final inspection |  |

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 23 November 2026.