# D A Pope Inc

Contractor license 381993. San Francisco building permit record since 2000.

- Page: https://www.permitgraph.org/contractor/d-a-pope-inc-381993
- JSON: https://www.permitgraph.org/api/contractor?license=381993
- State license record: https://www.cslb.ca.gov/onlineservices/checklicenseII/LicenseDetail.aspx?LicNum=381993

141 permits since 2000: 121 completed, 2 in progress, 13 never finaled, 5 expired or cancelled. Typically 9 days from filing to permit and 101 days from permit to final inspection. Of the 13 never-finaled permits, 1 is 5 to 10 years old, 12 are over 10 years old.

- Based in: Foster City
- On San Francisco permits: Feb 2000 to Oct 2026
- Last 24 months: 5 permits filed

This is the city's permit record, not a license check. It does not show whether the state license is active, bonded or insured.

## Permits filed each year

| Year | Completed | In progress | Never finaled | Expired or cancelled |
| --- | --- | --- | --- | --- |
| 2000 | 2 | 0 | 0 | 3 |
| 2001 | 1 | 0 | 0 | 0 |
| 2002 | 0 | 0 | 1 | 0 |
| 2005 | 0 | 0 | 3 | 0 |
| 2006 | 1 | 0 | 0 | 0 |
| 2007 | 1 | 0 | 0 | 0 |
| 2008 | 7 | 0 | 1 | 0 |
| 2009 | 4 | 0 | 2 | 0 |
| 2010 | 5 | 0 | 1 | 0 |
| 2011 | 7 | 0 | 0 | 0 |
| 2012 | 6 | 0 | 0 | 1 |
| 2013 | 11 | 0 | 1 | 0 |
| 2014 | 12 | 0 | 0 | 1 |
| 2015 | 17 | 0 | 3 | 0 |
| 2016 | 7 | 0 | 0 | 0 |
| 2017 | 6 | 0 | 0 | 0 |
| 2018 | 9 | 0 | 1 | 0 |
| 2019 | 7 | 0 | 0 | 0 |
| 2020 | 1 | 0 | 0 | 0 |
| 2021 | 4 | 0 | 0 | 0 |
| 2022 | 8 | 0 | 0 | 0 |
| 2023 | 1 | 0 | 0 | 0 |
| 2024 | 1 | 0 | 0 | 0 |
| 2025 | 3 | 0 | 0 | 0 |
| 2026 | 0 | 2 | 0 | 0 |

## By project type

| Project type | Permits | Completed | In progress | Never finaled | Expired or cancelled | Typical days to permit | Typical days to final |
| --- | --- | --- | --- | --- | --- | --- | --- |
| Kitchen remodel | 1 | 1 | 0 | 0 | 0 | 118 | 414 |
| Roof deck | 1 | 1 | 0 | 0 | 0 | 17 | 105 |
| Stairs | 6 | 5 | 0 | 0 | 1 | 11 | 241 |

## Most recent permits

The 100 most recent of 141.

| Permit | Filed | Outcome | Address | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- |
| [202610059049](https://www.permitgraph.org/p/202610059049) | Oct 5, 2026 | In progress: issued Oct 2026 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 9th floor: seismic bolting of existing phone booths | $7,500 |
| [202609107928](https://www.permitgraph.org/p/202609107928) | Sep 10, 2026 | In progress: issued Oct 2026 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 4th fl/ t.i siesmic bracing of existing phone booths. | $7,500 |
| [202510097108](https://www.permitgraph.org/p/202510097108) | Oct 9, 2025 | Completed: final sign-off Nov 2026 | [2001 Lombard St](https://www.permitgraph.org/a/0509/001) | retrofit existing building main entry with new concrete ramp for accessible main entry. remodel existing ground floor breakroom and restroom as required for accessibilty. five new private offices on… | $196,542 |
| [202510016455](https://www.permitgraph.org/p/202510016455) | Oct 1, 2025 | Completed: final sign-off Sep 2026 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 7th/fl: ti includes seismic bolting of (e) phone booths (ada reference: 2018-0112-8516) | $15,000 |
| [202504255236](https://www.permitgraph.org/p/202504255236) | Apr 25, 2025 | Completed: final sign-off Apr 2025 | [1241 Stockton St](https://www.permitgraph.org/a/0160/003) | revision to permit 202408299726, ensure supply air and return are located in new office footprint. |  |
| [202408299726](https://www.permitgraph.org/p/202408299726) | Aug 29, 2024 | Completed: final sign-off Apr 2025 | [1241 Stockton St](https://www.permitgraph.org/a/0160/003) | 1/f: ti of (e) bank. no change in occupancy, use, or area. selective interior non-structural demo. non structural partitions door/frame/hardware/sidelight; finishes and millwork; ceiling patching/rep… | $101,814 |
| [202301260807](https://www.permitgraph.org/p/202301260807) | Jan 26, 2023 | Completed: final sign-off Sep 2023 | [3131 Webster St](https://www.permitgraph.org/a/0509/002) | furnish and install auto door openters for 1 door to comply with abe 202211305340 |  |
| [202210174517](https://www.permitgraph.org/p/202210174517) | Oct 17, 2022 | Completed: final sign-off Feb 2023 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 6/f: new phone room (private phone room) bolting to floor only. private phone rooms by other. electriccal sprinklers and f/ls to be under separate permit. | $3,500 |
| [202210074000](https://www.permitgraph.org/p/202210074000) | Oct 7, 2022 | Completed: final sign-off Feb 2023 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 6/fl revision to 202108045709 egress plan update to show roof deck furniture as requested by fire department for assembly permit. |  |
| [202209293431](https://www.permitgraph.org/p/202209293431) | Sep 29, 2022 | Completed: final sign-off May 2023 | [2380 Irving St](https://www.permitgraph.org/a/1726/022) | 1st fl: demolition of (e) non bearing interior partions (n) non bearing interior wall for future tenant office conference rooms add break/copy (e) restroom accesibility upgrade. fire alarm/sprinklers… | $535,000 |
| [202209263099](https://www.permitgraph.org/p/202209263099) | Sep 26, 2022 | Completed: final sign-off Nov 2022 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 9/f ti includes new non-str partitions, new millwork + new sink, existing room renovated to lactation room ref 2018-0112-8516. mep life safety fire alarm sprinklers under seperate permit if needed de… | $19,500 |
| [202208190889](https://www.permitgraph.org/p/202208190889) | Aug 19, 2022 | Completed: final sign-off Nov 2022 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 8/f: rev to pa202205103842. modifty the dining area, office area and opening office ara. configuring them differently. increasing the overall occupancy count from 345 to 350. structural included. |  |
| [202208180779](https://www.permitgraph.org/p/202208180779) | Aug 18, 2022 | Completed: final sign-off Oct 2022 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 2/f: t.i. new non-structural partitions and shower rooms. new or revised meps, lifesafety or fire sprinkleres will be design build if neeed and submitted separately. maher n/a | $150,000 |
| [202206176601](https://www.permitgraph.org/p/202206176601) | Jun 17, 2022 | Completed: final sign-off Mar 2023 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | (2nd fl) ti includes the demo of non-str paritions and building new non str paritions. all new revised meps and life safety work will be design build and submitted separately (bldg is fully sprinkler… | $398,624 |
| [202205103842](https://www.permitgraph.org/p/202205103842) | May 10, 2022 | Completed: final sign-off Nov 2022 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 8th fl: t.i. includes demo of non-structural partitions + building new non-structural partitions. all newer revised mep's + life safety + sprinkler work will be design-build & submitted separately. b… | $165,000 |
| [202110120250](https://www.permitgraph.org/p/202110120250) | Oct 12, 2021 | Completed: final sign-off Jan 2024 | [170 Capp St](https://www.permitgraph.org/a/3570/039) | 3rd flr-demolition of (e) non-bearing partitions, new non-load bearing partitions to create new training room. private offices & open space area. modify (e)electrical & lighting system to accomodate… | $269,669 |
| [202108045714](https://www.permitgraph.org/p/202108045714) | Aug 4, 2021 | Completed: final sign-off Feb 2023 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 6/f, revision to pa# 202106162596 mech only. | $225,000 |
| [202108045709](https://www.permitgraph.org/p/202108045709) | Aug 4, 2021 | Completed: final sign-off Dec 2022 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | (6/f ti/5th exit corr) ti includes demo of exterior wall and glazing at new patio; new interior ramp/stair/landing, exterior operable wall system and exterior canopy. all new or revised mep like safe… | $1,500,000 |
| [202106162596](https://www.permitgraph.org/p/202106162596) | Jun 16, 2021 | Completed: final sign-off Oct 2022 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 6th floor: t.i. include demo of non-structural partitions & building. (n)non-structural paritions, all new or reivsed mep, life safety & sprincklers if needed will be deisgn build and submitted separ… | $532,000 |
| [202001272793](https://www.permitgraph.org/p/202001272793) | Jan 27, 2020 | Completed: final sign-off Jul 2020 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 7th fl, ste 760 & 770 - ti include demo of non-structural partitions and build (n) non structural partitions; mep, life safety & sprinklers will be design build & submitted separately if needed. (bld… | $217,000 |
| [201909202264](https://www.permitgraph.org/p/201909202264) | Sep 20, 2019 | Completed: final sign-off Dec 2019 | [501 03rd St](https://www.permitgraph.org/a/3775/073) | revision to 201908068027 to (e) ti. installation of interior sound proof glass windows | $8,000 |
| [201909060892](https://www.permitgraph.org/p/201909060892) | Sep 6, 2019 | Completed: final sign-off May 2020 | [501 03rd St](https://www.permitgraph.org/a/3775/073) | suite 300: interior remodel (ti) to 3rd fl - light demolition, new drywall, offices, mep reconfiguration & interior finishes. | $450,000 |
| [201908068027](https://www.permitgraph.org/p/201908068027) | Aug 6, 2019 | Completed: final sign-off Dec 2019 | [501 03rd St](https://www.permitgraph.org/a/3775/073) | suite 200: demolition of e non bearing partion. new non bearing partitions to create new offices, phone rm, copy rm, open office | $400,000 |
| [201904238657](https://www.permitgraph.org/p/201904238657) | Apr 23, 2019 | Completed: final sign-off Jul 2020 | [300 California St](https://www.permitgraph.org/a/0238/002) | demo of 2 concrete panel of battery st. & 1 concrete panel on halleck alley, installation of new storefront in new opening on halleck ave. installation of new storefront windows in new opening on bat… | $270,000 |
| [201903266237](https://www.permitgraph.org/p/201903266237) | Mar 26, 2019 | Completed: final sign-off Jan 2020 | [300 California St](https://www.permitgraph.org/a/0238/002) | 1/f: demo of an (e) non-structural mezzanine. terminate all ele back to source. no structural work assocated with scope. fire/life safety/ele under sep permit. maher n/a. | $50,000 |
| [201902203357](https://www.permitgraph.org/p/201902203357) | Feb 20, 2019 | Completed: final sign-off Feb 2019 | [500 Washington St](https://www.permitgraph.org/a/0196/023) | suite 450: electrical design drawings for pa 201811065128. ref ew201901308459. add (n) led fixtures, outlets and power dishwasher. title 24 compliance. maher n/a. | $100,000 |
| [201901281368](https://www.permitgraph.org/p/201901281368) | Jan 28, 2019 | Completed: final sign-off Jul 2019 | [357 Tehama St](https://www.permitgraph.org/a/3733/139) | unit 3, 3rd flr. interior remodel of (e) live-work unit | $100,000 |
| [201811065128](https://www.permitgraph.org/p/201811065128) | Nov 6, 2018 | Completed: final sign-off Feb 2019 | [500 Washington St](https://www.permitgraph.org/a/0196/023) | suite 450. tenant improvement. remove of non-structural parititons, (n) finishes, millwork, plumbing and electrical. mep, fire, life safety and sprinkler under separate permit. restroom: barrier remo… | $200,000 |
| [201808248250](https://www.permitgraph.org/p/201808248250) | Aug 24, 2018 | Never finaled: issued Aug 2018, no final | [909 Montgomery St](https://www.permitgraph.org/a/0163/005) | demolition of extg interior office non-structural bearing walls. new transformer and electrical panel and stub ups for plumbing for market ready suite 105. ab-017. | $75,000 |
| [201808086816](https://www.permitgraph.org/p/201808086816) | Aug 8, 2018 | Completed: final sign-off Oct 2018 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 1st flr suite 154 - ti demo of non structural partitions and build new non str partitions. all new or revise mep/life safety/fire sprinkers under sep permit. bld is fully sprinklered | $30,000 |
| [201807205142](https://www.permitgraph.org/p/201807205142) | Jul 20, 2018 | Completed: final sign-off Nov 2018 | [501 03rd St](https://www.permitgraph.org/a/3775/073) | further voluntary seismic strengthening and ada upgrades | $80,000 |
| [201805189531](https://www.permitgraph.org/p/201805189531) | May 18, 2018 | Completed: final sign-off Jul 2020 | [300 California St](https://www.permitgraph.org/a/0238/002) | demolish part of concrte panel on halleck streets to accommodate new hollow metal doors. demolish part of corridor walls and add new and 1 hr rated wall at corridor, new finishes and lighting through… | $250,000 |
| [201805189535](https://www.permitgraph.org/p/201805189535) | May 18, 2018 | Completed: final sign-off Jul 2020 | [300 California St](https://www.permitgraph.org/a/0238/002) | amep ti - scope of project includes 2 single use ada shower and toilet room facilities. new partitoins, glazing, door/frames, ceilings, lighting, power, millwork, sinks inlcuded. no strucutral work a… | $300,000 |
| [201805038130](https://www.permitgraph.org/p/201805038130) | May 3, 2018 | Completed: final sign-off Jul 2018 | [1050 Sansome St](https://www.permitgraph.org/a/0135/008) | revision to 201801188925 addition of 5 offices, new tenant at ground floor | $40,000 |
| [201801188925](https://www.permitgraph.org/p/201801188925) | Jan 18, 2018 | Completed: final sign-off Jul 2018 | [1050 Sansome St](https://www.permitgraph.org/a/0135/008) | 1st fl - market ready prep for showing to market in hopes of leasing including partitions, lighting, restrooms, counters, millwork | $145,000 |
| [201801188906](https://www.permitgraph.org/p/201801188906) | Jan 18, 2018 | Completed: final sign-off Sep 2018 | [1050 Sansome St](https://www.permitgraph.org/a/0135/008) | 3/f: commercial t.i.: non-structural demo. new non-load bvearing partitions, new mechanical, electrical and plumbing to tie into (e) utilities. replacement of rooftop mechanical unit. well building c… | $558,800 |
| [201801128516](https://www.permitgraph.org/p/201801128516) | Jan 12, 2018 | Completed: final sign-off May 2018 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 2nd floor: t.i. includes ada barrier removal only. building is fully sprinklered. n/a for maher | $4,000 |
| [201708316541](https://www.permitgraph.org/p/201708316541) | Aug 31, 2017 | Completed: final sign-off Nov 2017 | [300 California St](https://www.permitgraph.org/a/0238/002) | revision to app#201705247498. revised ceiling scope and additional interior partitions and revised electrical & mechanical work. n/a for maher. |  |
| [201708215421](https://www.permitgraph.org/p/201708215421) | Aug 21, 2017 | Completed: final sign-off Nov 2017 | [1050 Sansome St](https://www.permitgraph.org/a/0135/008) | 2/f- interior improvements including non-structural partition walls and finishes. | $250,000 |
| [201706209842](https://www.permitgraph.org/p/201706209842) | Jun 20, 2017 | Completed: final sign-off Apr 2018 | [200 Green St](https://www.permitgraph.org/a/0113/006) | construction of non-structural partitions, doors, frames, hardware, millwork, drywall, ceiling and finishes. | $369,042 |
| [201705247498](https://www.permitgraph.org/p/201705247498) | May 24, 2017 | Completed: final sign-off Nov 2017 | [300 California St](https://www.permitgraph.org/a/0238/002) | 3rd flr: demo (e) non bearing walls, glazing, millwork, finishes, doors, frames hardware, ceiling grid, tile, light fixtures and non compliant restrooms. new non structural interior partitions, doors… | $385,000 |
| [201705096027](https://www.permitgraph.org/p/201705096027) | May 9, 2017 | Completed: final sign-off Dec 2017 | [300 California St](https://www.permitgraph.org/a/0238/002) | revise and upgrade path of travel to comply w cbc 2016 ii 2 new accessible parking stalls to comply with cbc 2016 section 11b 502 iii. new passenger drop-off & loading zone accessible. to complu w/ c… | $130,000 |
| [201701237708](https://www.permitgraph.org/p/201701237708) | Jan 23, 2017 | Completed: final sign-off Mar 2017 | [1050 Sansome St](https://www.permitgraph.org/a/0135/008) | 4th floor: t.i. work includes selective demo and new non-structural walls. | $38,000 |
| [201612286009](https://www.permitgraph.org/p/201612286009) | Dec 28, 2016 | Completed: final sign-off Feb 2017 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 4th flr: ti- upgrade lights add additional outlets maher na | $35,000 |
| [201604225509](https://www.permitgraph.org/p/201604225509) | Apr 22, 2016 | Completed: final sign-off Jun 2016 | [724 Battery St](https://www.permitgraph.org/a/0166/007) | general t.i. with minor demolition and electrical. no plumbing, extg lighting is extg to remain except for removal of a couple track lights. | $51,500 |
| [201603182423](https://www.permitgraph.org/p/201603182423) | Mar 18, 2016 | Completed: final sign-off Jul 2016 | [340 Bryant St](https://www.permitgraph.org/a/3764/061) | 4th floor full floor tenant improvement including non-structural demolition, construction of non-structural partitions, interior finishes, doors, casework, light fixtures & plumbing fixtures. life sa… | $610,148 |
| [201603162146](https://www.permitgraph.org/p/201603162146) | Mar 16, 2016 | Completed: final sign-off Jul 2016 | [340 Bryant St](https://www.permitgraph.org/a/3764/061) | 2nd flr: full floor tenant improvement including non structural demolition, construction of non-structural partitions,interior finishes,doors, casework, light fixtures & plumbing fixtures, l/s & mep… | $1,064,833 |
| [201603162144](https://www.permitgraph.org/p/201603162144) | Mar 16, 2016 | Completed: final sign-off Jul 2016 | [340 Bryant St](https://www.permitgraph.org/a/3764/061) | 3rd flr: full floor tenant improvement including non structural demolition, construction of non-structural partitions,interior finishes,doors, casework, light fixtures & plumbing fixtures, l/s & mep… | $1,212,827 |
| [201602290790](https://www.permitgraph.org/p/201602290790) | Feb 29, 2016 | Completed: final sign-off Mar 2016 | [1050 Sansome St](https://www.permitgraph.org/a/0135/008) | revision to 2015 0309 0298 / 2015 0811 3957: replace (e) outlets & lighting fixtures to comply with title 24 requirements |  |
| [201602058930](https://www.permitgraph.org/p/201602058930) | Feb 5, 2016 | Completed: final sign-off Jun 2016 | [410 Townsend St](https://www.permitgraph.org/a/3785/002A) | 1-4 floors: project consist only of barrier removal. demolition of extg drinking fountain of floors 1-4 and upgrading to ada compliance. extg mep, life safty and sprinkler modification are under sepe… | $6,000 |
| [201512084479](https://www.permitgraph.org/p/201512084479) | Dec 8, 2015 | Completed: final sign-off Jun 2016 | [410 Townsend St](https://www.permitgraph.org/a/3785/002A) | project consist of barrier removal. domo of existing 4th fl restroom finishes and accessories. finsihes and accessories upgraded. mech,elec, life safety, sprinkler sep permit. n/a ordinance #155-13 | $70,000 |
| [201511182980](https://www.permitgraph.org/p/201511182980) | Nov 18, 2015 | Completed: final sign-off Mar 2016 | [1050 Sansome St](https://www.permitgraph.org/a/0135/008) | 1st/2nd flrs: inspector required additional detail per revised s2.2 plan showing downturned slab edge as per details 1&2/s2.2 dtd. 7-31-15 revision plan, (rev to 201503090298) | $7,500 |
| [201511172885](https://www.permitgraph.org/p/201511172885) | Nov 17, 2015 | Never finaled: issued Nov 2015, no final | [1 Lombard St](https://www.permitgraph.org/a/0081/001) | ti add (5) light fixtures, seven outlets. ref pa 2015-1106-1977. n/a ordinance #155-13 | $15,022 |
| [201511061977](https://www.permitgraph.org/p/201511061977) | Nov 6, 2015 | Completed: final sign-off Dec 2015 | [1 Lombard St](https://www.permitgraph.org/a/0081/001) | 2nd flr, ste 200: this project involves modification of (e) tenant space to inclue selective demo and construction of non-load bearing partitions,new ceiling grid & tile,new light fixtures,new office… | $62,320 |
| [201509157023](https://www.permitgraph.org/p/201509157023) | Sep 15, 2015 | Completed: final sign-off Apr 2016 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | tenant improvement. upgrade lighting systems and power outlets. ref 201509025936 | $67,000 |
| [201509025936](https://www.permitgraph.org/p/201509025936) | Sep 2, 2015 | Completed: final sign-off Apr 2016 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 7th fl.( suite 750) t.i. includes the demo of non-structural partitions and build back of non-structural partitions. all new or revised m.e.p., life safety, and sprinklers drawings to be submitted un… | $106,000 |
| [201508113957](https://www.permitgraph.org/p/201508113957) | Aug 11, 2015 | Completed: final sign-off Mar 2016 | [1050 Sansome St](https://www.permitgraph.org/a/0135/008) | 1st and 2nd floor - replace existing outlets and lighting fixtures to comply with title 24 requirements. ref pa 201503090298 | $22,000 |
| [201507282651](https://www.permitgraph.org/p/201507282651) | Jul 28, 2015 | Completed: final sign-off Nov 2015 | [1050 Sansome St](https://www.permitgraph.org/a/0135/008) | revision to 201503049904. revision to 5th and 6th fl permit - interconnecting stairs | $110,000 |
| [201507131362](https://www.permitgraph.org/p/201507131362) | Jul 13, 2015 | Completed: final sign-off Jun 2017 | [1050 Sansome St](https://www.permitgraph.org/a/0135/008) | provide one (1) new exterior window, new canopy, new bldg entry door. replace glazing in 2nd floor windows. | $200,000 |
| [201507091069](https://www.permitgraph.org/p/201507091069) | Jul 9, 2015 | Completed: final sign-off Nov 2015 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 4th floor: electrical tenant improvement. additonal outlets, upgrade lighting. ref 201506300268 | $62,000 |
| [201506300268](https://www.permitgraph.org/p/201506300268) | Jun 30, 2015 | Completed: final sign-off Nov 2015 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 4th floor suite #450: t.i. includes demo of non-structural partitions and bldg new non-structural partitions. all new or revised hvac, electrical, plmg, life safety and sprinklers will be design buil… | $200,000 |
| [201506158931](https://www.permitgraph.org/p/201506158931) | Jun 15, 2015 | Never finaled: issued Aug 2015, no final | [410 Townsend St](https://www.permitgraph.org/a/3785/002A) | ground floor: project consist of demolition of extg ground floor restroom finishes and water closet relocation. finishes will be upgraded mep, life safty, and sprinkler are not included in this permi… | $70,000 |
| [201505115894](https://www.permitgraph.org/p/201505115894) | May 11, 2015 | Completed: final sign-off Apr 2016 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 9th flr: revision to 201504073017, reducing the scope of work on electrical only, arch. 201503191272; maher n/a. |  |
| [201504274695](https://www.permitgraph.org/p/201504274695) | Apr 27, 2015 | Completed: final sign-off Feb 2016 | [1050 Sansome St](https://www.permitgraph.org/a/0135/008) | voluntary seismic upgrade. | $198,000 |
| [201504073017](https://www.permitgraph.org/p/201504073017) | Apr 7, 2015 | Completed: final sign-off Nov 2015 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 9th floor: ti- includes revision/retrofit of (e) lighting fixtures. maher - not req'd | $86,000 |
| [201503191272](https://www.permitgraph.org/p/201503191272) | Mar 19, 2015 | Completed: final sign-off Nov 2015 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 9th flr: ti includes the demo of nonstructural partitions and build new non structural partitions. all new or revised hvac, elect, plumb, and life safety work will be submitted seperately. bld is ful… | $240,000 |
| [201503120719](https://www.permitgraph.org/p/201503120719) | Mar 12, 2015 | Never finaled: issued Mar 2015, no final | [1050 Sansome St](https://www.permitgraph.org/a/0135/008) | ti for 5th & 6th - electrical only ref pa# 2015 0304 9904 | $104,000 |
| [201503110514](https://www.permitgraph.org/p/201503110514) | Mar 11, 2015 | Completed: final sign-off Nov 2015 | [1050 Sansome St](https://www.permitgraph.org/a/0135/008) | ti 5th & 6th fl: 2 new a/c units - roof top. 2 new split system a/c units. 1 exhaust fan ref pa# 2015 0304 9904 | $60,000 |
| [201503090298](https://www.permitgraph.org/p/201503090298) | Mar 9, 2015 | Completed: final sign-off Mar 2016 | [1050 Sansome St](https://www.permitgraph.org/a/0135/008) | renovate lobby. add new bike room, demolish floor at 2nd floor to create 2 story lobby, new restrooms finishes at 2nd floor. also provide new finishes, mep and structural work in 2 story lobby area. | $500,000 |
| [201503049904](https://www.permitgraph.org/p/201503049904) | Mar 4, 2015 | Completed: final sign-off Nov 2015 | [1050 Sansome St](https://www.permitgraph.org/a/0135/008) | t.i. to 5th and 6th floors , includes new walls, lifhting. electrical, plmg and mechanical deferred submittals | $550,500 |
| [201412234377](https://www.permitgraph.org/p/201412234377) | Dec 23, 2014 | Completed: final sign-off Jan 2015 | [1050 Sansome St](https://www.permitgraph.org/a/0135/008) | i.t. data room at basement floor, new walls as shown per note #1; new door as shown per note #3 and me as required. | $8,600 |
| [201412163775](https://www.permitgraph.org/p/201412163775) | Dec 16, 2014 | Completed: final sign-off Apr 2015 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 8th flr: construction of new break area including cabinetry plumbing and lighting; mep to be design built under separate permit. building fully sprinklered; maher n/a | $15,000 |
| [201411202158](https://www.permitgraph.org/p/201411202158) | Nov 20, 2014 | Completed: final sign-off Feb 2015 | [1050 Sansome St](https://www.permitgraph.org/a/0135/008) | demolition of 2nd and 3rd floors, non structural partiton walls | $30,000 |
| [201410219478](https://www.permitgraph.org/p/201410219478) | Oct 21, 2014 | Completed: final sign-off Nov 2014 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 5th floor suite #500: t.i. to include selective demo nonstruction of non-load bearings partitions. mep & life safety under separate permit. maher n/a. | $40,000 |
| [201409186640](https://www.permitgraph.org/p/201409186640) | Sep 18, 2014 | Completed: final sign-off Oct 2015 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | flrs: 8 and 9- construction of communication stair between 2 existing "b" occupancy floors (8th and 9th flrs) maher n/a | $176,000 |
| [201406208981](https://www.permitgraph.org/p/201406208981) | Jun 20, 2014 | Completed: final sign-off Mar 2016 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 8th floor:phase iii meps for 201402289570 | $240,000 |
| [201406047437](https://www.permitgraph.org/p/201406047437) | Jun 4, 2014 | Expired or cancelled: expired May 2022 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | t.i. includes demo of portion existing concrete slab for new communication stair between existing 8/f & 9/f tenant suites. permit for new stair and 9/f t.i. submitted seperately. ti on both floors se… | $1,000 |
| [201405296966](https://www.permitgraph.org/p/201405296966) | May 29, 2014 | Completed: final sign-off Jun 2014 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 4th floor #400/490 - revision to appl #2014.0417.3490: modify duct work hvac no new units. n/a maher ordinance 155-13 |  |
| [201404173490](https://www.permitgraph.org/p/201404173490) | Apr 17, 2014 | Completed: final sign-off Jun 2014 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | #400 & #490- t.i. includes build out of a few full height non-structural partitions, doors/frames & glazing, all new or revised hvac, electrical, plumbing and life safety, work will be submitted sepe… | $250,000 |
| [201403241533](https://www.permitgraph.org/p/201403241533) | Mar 24, 2014 | Completed: final sign-off Jun 2014 | [725 Folsom St](https://www.permitgraph.org/a/3751/0172) | ground floor:t.i. includes demo of non structural partitions and building new non structural partitions. all new or revised hvac, electrical, plmbg and life safety work wil be design build and sumitt… | $75,000 |
| [201402289570](https://www.permitgraph.org/p/201402289570) | Feb 28, 2014 | Completed: final sign-off Aug 2015 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 8th floor t.i. includes building new non-structural partitions, new raised floor area & kitchen. (all new or revised hvac, electrical, plumbing & life safety work will be design build & submitted for… | $750,000 |
| [201402188702](https://www.permitgraph.org/p/201402188702) | Feb 18, 2014 | Completed: final sign-off Apr 2015 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 8th fl new non structural paritions, interior doors, glazing. new or revised hvac, elec, plumbing, life safety design build, submitted separately. building fully sprinlered. glass partitions under se… | $750,000 |
| [201402037592](https://www.permitgraph.org/p/201402037592) | Feb 3, 2014 | Completed: final sign-off Apr 2014 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 8th floor: interior demo only. ab-017 will remain unoccupied until t. i. permit is approved. n/a for maher ordinance #155-13 | $11,000 |
| [201311051159](https://www.permitgraph.org/p/201311051159) | Nov 5, 2013 | Completed: final sign-off Feb 2014 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 7/f- removal of section of partition and interior glazing at existing elevator lobby, if applicable, all new or modified hvac, electrical and life safety work will be design build and submitted seper… | $5,000 |
| [201310119086](https://www.permitgraph.org/p/201310119086) | Oct 11, 2013 | Never finaled: issued Oct 2013, no final | [300 California St](https://www.permitgraph.org/a/0238/002) | addition of access controls to the existing all glass entry doors, new card reader and door. secuirty hardware to be tied to fire life safety system and retain existing accessible entry clearance | $32,000 |
| [201306260586](https://www.permitgraph.org/p/201306260586) | Jun 26, 2013 | Completed: final sign-off Feb 2014 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 9th floor-revision to pa# 2013-0522-7681-revision include lighting (title 24); changes include lighting plan a2.09 power and signal a.3.09 compliance with ord 155-13 not required | $15,000 |
| [201306139429](https://www.permitgraph.org/p/201306139429) | Jun 13, 2013 | Completed: final sign-off Jul 2013 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 3rd floor-ti include demolition of non structural partitions, new non structural partitions, relocate doors, new or revised hvac, electrical, plumbing & life safety work will be design build & submit… | $35,000 |
| [201306119153](https://www.permitgraph.org/p/201306119153) | Jun 11, 2013 | Completed: final sign-off Oct 2013 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 8th floor-multi-tenant floor-interior demo, no disabled access upgrades, per ab-017. arch, mep, sprinkler & fire alarm under separate applications. maintain life safety and sprinkler systems operatio… | $30,000 |
| [201306048676](https://www.permitgraph.org/p/201306048676) | Jun 4, 2013 | Completed: final sign-off Dec 2014 | [28 Geary St](https://www.permitgraph.org/a/0310/008) | suite #500-interior office improvements-new carpet, paint, new interior non structural partitions, new millwork, cabinets, new interior doors. (e) lighting to remain, no structural work. re-work (e)… | $97,000 |
| [201305227681](https://www.permitgraph.org/p/201305227681) | May 22, 2013 | Completed: final sign-off Aug 2013 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 9th floor t.i. includes bldg full height non-sttructural partition, new doors, frames, interior, glazing, relocation of light fixtures & selected new lights, all new or modified hvac, electrical, plu… | $175,000 |
| [201304235259](https://www.permitgraph.org/p/201304235259) | Apr 23, 2013 | Completed: final sign-off Apr 2013 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | electrical, mechanical title 24 work associated with bldg pa# 2013-0319-2501 | $3,000 |
| [201303192501](https://www.permitgraph.org/p/201303192501) | Mar 19, 2013 | Completed: final sign-off Apr 2013 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 6th floor suite # 600: t. i. include the demo of non-structural partitions. all new or revised hvac, electrical, plmg and life safety work will be design build and submitted for permit seperately. bl… | $38,000 |
| [201303121968](https://www.permitgraph.org/p/201303121968) | Mar 12, 2013 | Completed: final sign-off Apr 2013 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 7th floor-suite #735-build out full height non structural partitions. new doors & frames, interior glazing. demo of (e) ceiling & relocate lights. all new or revised hvac, electrical, plumbing & life… | $35,000 |
| [201301087448](https://www.permitgraph.org/p/201301087448) | Jan 8, 2013 | Completed: final sign-off Feb 2013 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 4th fl. ste 470. ti include building out, full height, non structural partitions, new doors/frames, interior glazing. demo of existing ceiling and relocation of light fixtures; all new or modified hv… | $55,000 |
| [201301087446](https://www.permitgraph.org/p/201301087446) | Jan 8, 2013 | Completed: final sign-off Mar 2013 | [1550 Bryant St](https://www.permitgraph.org/a/3923/006) | 5th fl. ste 525, 535, 545. ti include building out, full height, non structural partitions, new door/frames, interior glazing. demo of existing ceiling and relocation of light fixtures; all new or mo… | $89,000 |
| [201211295089](https://www.permitgraph.org/p/201211295089) | Nov 29, 2012 | Expired or cancelled: cancelled Jan 2014 | [300 California St](https://www.permitgraph.org/a/0238/002) | 3rd floor suite 300 - demolition & construction of non-load bearing partitions, relocation of light fixtures & demo of exisitng acoustic ceiling grid & tile, new doors, new finishes. mechanical & ele… | $125,000 |
| [201210262946](https://www.permitgraph.org/p/201210262946) | Oct 26, 2012 | Completed: final sign-off May 2013 | [848 Battery St](https://www.permitgraph.org/a/0141/002) | revision to app#201208157467 to clarify framing at gathering steps per bldg inspectors request and submit as an addition to extg permit. |  |
| [201208157467](https://www.permitgraph.org/p/201208157467) | Aug 15, 2012 | Completed: final sign-off May 2013 | [840 Battery St](https://www.permitgraph.org/a/0141/002) | demolition on existing office-non structural interior walls include wm outlets.relocation of existing lights.new partitions, electrical,server rm,lights, millwork and finishes and new communication s… | $750,000 |
| [201207185118](https://www.permitgraph.org/p/201207185118) | Jul 18, 2012 | Completed: final sign-off Oct 2012 | [2622 Ocean Av](https://www.permitgraph.org/a/7224/002A) | change of use from m-retail to b-medical office-new ceiling, lights, plumbing & finishes. | $62,000 |
| [201206213184](https://www.permitgraph.org/p/201206213184) | Jun 21, 2012 | Completed: final sign-off Sep 2012 | [170 Maiden Ln](https://www.permitgraph.org/a/0309/023) | 5th floor-t.i. to consist of demolition non bearing partitions, new partitions, electrical, hvac, plumbing, acoustical ceilings, sprinkler & finishes. m.e.p under seperate permits. all work on 5th fl… | $420,000 |

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 23 November 2026.
This is the text of https://www.permitgraph.org/contractor/d-a-pope-inc-381993.