# Campbell Family Electric Inc

Contractor license 876689. San Francisco building permit record since 2000.

- Page: https://www.permitgraph.org/contractor/campbell-family-electric-inc-876689
- JSON: https://www.permitgraph.org/api/contractor?license=876689
- State license record: https://www.cslb.ca.gov/onlineservices/checklicenseII/LicenseDetail.aspx?LicNum=876689

6 permits since 2000: 4 completed, 2 never finaled. Typically 19 days from filing to permit and 138 days from permit to final inspection. Of the 2 never-finaled permits, 2 are 5 to 10 years old.

- Based in: Tracy
- On San Francisco permits: Dec 2018 to Jul 2020
- Last 24 months: 0 permits filed

This is the city's permit record, not a license check. It does not show whether the state license is active, bonded or insured.

## Permits filed each year

| Year | Completed | In progress | Never finaled | Expired or cancelled |
| --- | --- | --- | --- | --- |
| 2018 | 0 | 0 | 1 | 0 |
| 2019 | 1 | 0 | 1 | 0 |
| 2020 | 3 | 0 | 0 | 0 |

## Most recent permits

| Permit | Filed | Outcome | Address | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- |
| [202007230737](https://www.permitgraph.org/p/202007230737) | Jul 23, 2020 | Completed: final sign-off Dec 2020 | [1750 Fulton St](https://www.permitgraph.org/a/1175/031) | install (2) ev chargers in existing parking structure | $162,000 |
| [202003056282](https://www.permitgraph.org/p/202003056282) | Mar 5, 2020 | Completed: final sign-off Jul 2020 | [1150 Ocean Av](https://www.permitgraph.org/a/3180/006) | replace (2) level 2 ev chargers w/(2) level (3) ev chargers. | $20,000 |
| [202003056279](https://www.permitgraph.org/p/202003056279) | Mar 5, 2020 | Completed: final sign-off Aug 2020 | [1000 Van Ness Av](https://www.permitgraph.org/a/0715/014) | install (9) level 3 evs e chargers and (1) level 2 charger & require electrical equipment. | $150,000 |
| [201912179802](https://www.permitgraph.org/p/201912179802) | Dec 17, 2019 | Completed: final sign-off Jun 2020 | [1160 Mission St](https://www.permitgraph.org/a/3702/061) | install (2) l3 vehicle charging stations | $48,000 |
| [201902062285](https://www.permitgraph.org/p/201902062285) | Feb 6, 2019 | Never finaled: issued Feb 2019, no final | [1160 Mission St](https://www.permitgraph.org/a/3702/061) | install 10 electric vehicle charger and equipment | $115,000 |
| [201812107887](https://www.permitgraph.org/p/201812107887) | Dec 10, 2018 | Never finaled: issued Feb 2019, no final | [600 California St](https://www.permitgraph.org/a/0241/003) | install 10 level 3 ev chargers anx 2 level 2 chargers in e parking stalls. install evgo support equipment | $160,000 |

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 23 November 2026.
This is the text of https://www.permitgraph.org/contractor/campbell-family-electric-inc-876689.