5 permits since 2000: 4 completed, 1 never finaled. Typically 90 days from filing to permit and 201 days from permit to final inspection. Of the 1 never-finaled permit, 1 is 3 to 5 years old.

- Based in: Pleasanton
- On San Francisco permits: Dec 2019 to Oct 2024
- Last 24 months: 0 permits filed

This is the city's permit record, not a license check. It does not show whether the state license is active, bonded or insured.

## Permits filed each year

| Year | Completed | In progress | Never finaled | Expired or cancelled |
| --- | --- | --- | --- | --- |
| 2019 | 1 | 0 | 0 | 0 |
| 2020 | 1 | 0 | 0 | 0 |
| 2023 | 0 | 0 | 1 | 0 |
| 2024 | 2 | 0 | 0 | 0 |

## Most recent permits

| Permit | Filed | Outcome | Address | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- |
| [202410223446](https://www.permitgraph.org/p/202410223446) | Oct 22, 2024 | Completed: final sign-off Jan 2025 | [790 Pennsylvania Av](https://www.permitgraph.org/a/4167/011) | addition and relocation of lighting and ventilation as required for new partition wall. all mep, fire alarm and sprinkler under a separate permit. work not visible from street | $40,000 |
| [202402065323](https://www.permitgraph.org/p/202402065323) | Feb 6, 2024 | Completed: final sign-off Feb 2025 | [2343 Fillmore St](https://www.permitgraph.org/a/0611/001A) | renovation of existing interior garage for use in medical imaging. | $200,399 |
| [202301120059](https://www.permitgraph.org/p/202301120059) | Jan 12, 2023 | Never finaled: issued Feb 2023, no final | [1035 Howard St](https://www.permitgraph.org/a/3731/094) | demo (e) structures detached in yard of building, demo altered, recent abandoned hvac & mep elements. planning record #2019012604 | $30,000 |
| [202010196839](https://www.permitgraph.org/p/202010196839) | Oct 19, 2020 | Completed: final sign-off Dec 2021 | [180 Redwood St](https://www.permitgraph.org/a/0766/013) | minor modification to (e) building lobby & exterior. selective demo and modifications to celing, new light fixtures, new exterior doors and new finishes. maher n/a. | $443,971 |
| [201912109081](https://www.permitgraph.org/p/201912109081) | Dec 10, 2019 | Completed: final sign-off Sep 2020 | [1035 Howard St](https://www.permitgraph.org/a/3731/094) | interior soft demo of existing building including demo of all non-structural interior partitions, hvac, and mep items, non-structural flooring and furniture, fixture, and equipment. reference to plan… | $150,000 |

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 23 November 2026.