# Balfour Beatty Construction Llc

Contractor license 979126. San Francisco building permit record since 2000.

- Page: https://www.permitgraph.org/contractor/balfour-beatty-construction-llc-979126
- JSON: https://www.permitgraph.org/api/contractor?license=979126
- State license record: https://www.cslb.ca.gov/onlineservices/checklicenseII/LicenseDetail.aspx?LicNum=979126

58 permits since 2000: 49 completed, 5 never finaled, 4 expired or cancelled. Typically 18 days from filing to permit and 458 days from permit to final inspection. Of the 5 never-finaled permits, 3 are 5 to 10 years old, 2 are over 10 years old.

- Based in: Oakland
- On San Francisco permits: Sep 2013 to Mar 2021
- Last 24 months: 0 permits filed

This is the city's permit record, not a license check. It does not show whether the state license is active, bonded or insured.

## Permits filed each year

| Year | Completed | In progress | Never finaled | Expired or cancelled |
| --- | --- | --- | --- | --- |
| 2013 | 5 | 0 | 0 | 0 |
| 2014 | 10 | 0 | 0 | 0 |
| 2015 | 8 | 0 | 1 | 1 |
| 2016 | 13 | 0 | 1 | 1 |
| 2017 | 5 | 0 | 1 | 2 |
| 2018 | 5 | 0 | 0 | 0 |
| 2019 | 1 | 0 | 2 | 0 |
| 2020 | 1 | 0 | 0 | 0 |
| 2021 | 1 | 0 | 0 | 0 |

## By project type

| Project type | Permits | Completed | In progress | Never finaled | Expired or cancelled | Typical days to permit | Typical days to final |
| --- | --- | --- | --- | --- | --- | --- | --- |
| Stairs | 2 | 2 | 0 | 0 | 0 | 52 | 168 |
| Roof deck | 1 | 1 | 0 | 0 | 0 | 10 | 364 |

## Most recent permits

| Permit | Filed | Outcome | Address | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- |
| [202103015616](https://www.permitgraph.org/p/202103015616) | Mar 1, 2021 | Completed: final sign-off Apr 2021 | [532 Folsom St](https://www.permitgraph.org/a/3736/158) | to obtain final inspection for work approved under permit application no(s): 201604184988. all work is complete | $55,800 |
| [202012080560](https://www.permitgraph.org/p/202012080560) | Dec 8, 2020 | Completed: final sign-off Feb 2021 | [500 Folsom St](https://www.permitgraph.org/a/3736/120) | remove in-duct detectors from certain garage exhaust fans per recommendations from the smoke control consultant, modify the fa programming & gcp graphics so that the fso's in the garage used solely f… | $11,000 |
| [201912270783](https://www.permitgraph.org/p/201912270783) | Dec 27, 2019 | Never finaled: issued Dec 2019, no final | [500 Folsom St](https://www.permitgraph.org/a/3736/120) | ref pa# 201503110506; updated smoke control matrix for revisions to the garage exhauset |  |
| [201911197696](https://www.permitgraph.org/p/201911197696) | Nov 19, 2019 | Completed: final sign-off Apr 2021 | [500 Folsom St](https://www.permitgraph.org/a/3736/120) | for record purposes only that pertain to unit reduction. 2 studio units were removed from each floor on levels 39-42 for a total of 8 units removed from the project. (ref pa #2015-0311-0506 s) |  |
| [201905291862](https://www.permitgraph.org/p/201905291862) | May 29, 2019 | Never finaled: issued May 2019, no final | [500 Folsom St](https://www.permitgraph.org/a/3736/120) | smoke control panel layout submitted as a revision to the addendum 4 (mep) issued permit. ref pa #201503110506 s4. n/a for maher. |  |
| [201812037205](https://www.permitgraph.org/p/201812037205) | Dec 3, 2018 | Completed: final sign-off Dec 2018 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | to obtain final inspection for work approved under pa#2016-0421-5391, 2017-0417-4155 & 201705257609 |  |
| [201809069330](https://www.permitgraph.org/p/201809069330) | Sep 6, 2018 | Completed: final sign-off Dec 2020 | [500 Folsom St](https://www.permitgraph.org/a/3736/120) | shoring & hold down anchors to combat hydrostatic pressure from ground water: relocation of one hydrostatic tiedown anchor one foot away from the original location. (ref pa #2015-0311-0506 s1) | $240,000 |
| [201807265647](https://www.permitgraph.org/p/201807265647) | Jul 26, 2018 | Completed: final sign-off Dec 2020 | [500 Folsom St](https://www.permitgraph.org/a/3736/120) | document parking layout from pre-app meeting & da-09. rev to pa#201503110506-s3(arch). maher n/a. |  |
| [201805310671](https://www.permitgraph.org/p/201805310671) | May 31, 2018 | Completed: final sign-off Apr 2021 | [500 Folsom St](https://www.permitgraph.org/a/3736/120) | grey water system (storm water).**maher n/a** |  |
| [201801239301](https://www.permitgraph.org/p/201801239301) | Jan 23, 2018 | Completed: final sign-off Dec 2020 | [500 Folsom St](https://www.permitgraph.org/a/3736/120) | temporary truss shoring for levels 3-9 (ref pa #201503110506-s) | $1,000 |
| [201711274818](https://www.permitgraph.org/p/201711274818) | Nov 27, 2017 | Completed: final sign-off Dec 2020 | [500 Folsom St](https://www.permitgraph.org/a/3736/120) | phase 2 of the tower crane submital - tower crane permit for tie-ins. ref pa# 2015/03/11/0506-s. ** maher: n/a ** | $116,000 |
| [201705257609](https://www.permitgraph.org/p/201705257609) | May 25, 2017 | Expired or cancelled: expired Dec 2018 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | for record purposes only: revision to ab-005 approved pa# 2017-0124-7758. ** maher: n/a ** |  |
| [201705187052](https://www.permitgraph.org/p/201705187052) | May 18, 2017 | Completed: final sign-off May 2017 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | to obtain final inspection for work approved under pa# 201503191348 & 201309045884. all work is complete. n/a for maher. |  |
| [201704254826](https://www.permitgraph.org/p/201704254826) | Apr 25, 2017 | Never finaled: issued Aug 2017, no final | [522 08th St](https://www.permitgraph.org/a/3781/007) | relocation of extg low pressure fire hydrant 10 feet from current location on corner. |  |
| [201704174155](https://www.permitgraph.org/p/201704174155) | Apr 17, 2017 | Expired or cancelled: expired Dec 2018 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | revision to title sheet good for 201309045886 s2 revision to bike count to 311 spaces and reduction of parking by 1 to 428 to reflect final condition in the bldg. revisions meet planning code require… |  |
| [201703201849](https://www.permitgraph.org/p/201703201849) | Mar 20, 2017 | Completed: final sign-off Dec 2020 | [500 Folsom St](https://www.permitgraph.org/a/3736/120) | tower crane for new construction at 500 folsom street. (ref pa#201503110506). this permit is for phase 1 tower crane erection up to level 16 (mast height 217 ft) ** maher; n/a ** | $200,000 |
| [201701247758](https://www.permitgraph.org/p/201701247758) | Jan 24, 2017 | Completed: final sign-off Dec 2018 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | alteration to mechanical roof ventialation system to pa# 2013/09/04/5886-s , including mechanical ventilation of concelaed space associated wit roof area ** maher: n/a ** | $250,000 |
| [201701096740](https://www.permitgraph.org/p/201701096740) | Jan 9, 2017 | Completed: final sign-off Jan 2018 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | temporary leasing office will be placed on a temporary parking lot maher not req | $50,000 |
| [201612165243](https://www.permitgraph.org/p/201612165243) | Dec 16, 2016 | Completed: final sign-off Jan 2018 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | revision to pa #201309045886 - roof ventilation & draft stopping requirements- n/a maher ordinance | $200,000 |
| [201608084465](https://www.permitgraph.org/p/201608084465) | Aug 8, 2016 | Completed: final sign-off Aug 2017 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | roof deck fire pit (ref. pa 201309045886); maher n/a | $5,000 |
| [201607132214](https://www.permitgraph.org/p/201607132214) | Jul 13, 2016 | Completed: final sign-off Dec 2020 | [500 Folsom St](https://www.permitgraph.org/a/3736/120) | temporary excavation shoring for the removal of an existing burried basement wall (ref. pa 201503110506s). | $90,000 |
| [201605056677](https://www.permitgraph.org/p/201605056677) | May 5, 2016 | Completed: final sign-off Dec 2020 | [500 Folsom St](https://www.permitgraph.org/a/3736/120) | temporary equipment trestle for new construction.ref pa# 2015/03/11/0506-s ** maher: n/a ** | $465,000 |
| [201604215391](https://www.permitgraph.org/p/201604215391) | Apr 21, 2016 | Expired or cancelled: expired Dec 2018 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | revision to s1 app#201309045886. provide additional drainage from the garage open to the sky. n/a for maher. |  |
| [201604184983](https://www.permitgraph.org/p/201604184983) | Apr 18, 2016 | Completed: final sign-off Apr 2021 | [19 Clementina St](https://www.permitgraph.org/a/3736/124) | tiebacks extending into 19 clementina due to shoring for 500 folsom street ref pa2015-0925-8114 ** maher: exempted - approval from dph attached ** | $249,550 |
| [201604184987](https://www.permitgraph.org/p/201604184987) | Apr 18, 2016 | Completed: final sign-off Apr 2021 | [528 Folsom St](https://www.permitgraph.org/a/3736/016) | tiebacks extending into 528 folsom street due to shoring of 500 folsom per pa 2015-0925-8114 ** maher: exempted - approval from dph attached ** | $305,350 |
| [201604184988](https://www.permitgraph.org/p/201604184988) | Apr 18, 2016 | Never finaled: issued May 2016, no final | [532 Folsom St](https://www.permitgraph.org/a/3736/158) | tiebacks extending to 532 folsom street for shoring off 500 folsom per pa 2015-0925-8114 ** maher: exempted - approval from dph attached. ** | $55,800 |
| [201603141975](https://www.permitgraph.org/p/201603141975) | Mar 14, 2016 | Completed: final sign-off May 2017 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | revision per bldg inspector request to comply with the correction notice & report #2 filed 3/4/16 under pa 2013-0904-5886, to provide an approved revision for the change in boundary element ties to #… |  |
| [201603031088](https://www.permitgraph.org/p/201603031088) | Mar 3, 2016 | Completed: final sign-off May 2017 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | revision per bldg inspection request to comply with the correction notice and report #1 filed 2/23/16 under app#201309045886 for the concrete beam schedule change. n/a for maher |  |
| [201602190089](https://www.permitgraph.org/p/201602190089) | Feb 19, 2016 | Completed: final sign-off Dec 2020 | [500 Folsom St](https://www.permitgraph.org/a/3736/120) | jet grout ground improvement for new construction. ref pa# 2015/03/11/0506-s. ** maher: exempted; see attached approval letter from dph ** | $1,000 |
| [201602190086](https://www.permitgraph.org/p/201602190086) | Feb 19, 2016 | Completed: final sign-off Dec 2020 | [500 Folsom St](https://www.permitgraph.org/a/3736/120) | soil removal for new construction (site migitation plan). ref pa# 2015/03/11/0506-s. ** maher: exempted; see attached approval letter from dph ** | $1,000 |
| [201602058965](https://www.permitgraph.org/p/201602058965) | Feb 5, 2016 | Completed: final sign-off May 2017 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | additional structural detail as corrective measure requested by inspector at area they were unable to inspect. ref 201601278143, 201601257916, 201309045886 maher not req |  |
| [201601278143](https://www.permitgraph.org/p/201601278143) | Jan 27, 2016 | Completed: final sign-off May 2017 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | revision to 201601257916. additonal clarification regarding corner condition detail as requested by bldg inspector to comply with correction notice and report filed under 201309045886. compliance wit… |  |
| [201601257916](https://www.permitgraph.org/p/201601257916) | Jan 25, 2016 | Completed: final sign-off May 2017 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | comply with correction notice and report per app#201309045886 regarding top plates detail. n/a for maher. |  |
| [201512175338](https://www.permitgraph.org/p/201512175338) | Dec 17, 2015 | Completed: final sign-off Dec 2018 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | revision to pa# 2013/09/04/5886 s-2. added one transformer room for ac revision. added ac unit support on roof. revise garage b entrance. ** maher: n/a ** | $5,700,000 |
| [201509258115](https://www.permitgraph.org/p/201509258115) | Sep 25, 2015 | Completed: final sign-off Dec 2020 | [500 Folsom St](https://www.permitgraph.org/a/3736/120) | excavate shoring for new construction pa #2015-03-11-0506s. maher ordinance exempted by dph. | $3,000,000 |
| [201508214980](https://www.permitgraph.org/p/201508214980) | Aug 21, 2015 | Completed: final sign-off May 2017 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | rev. to addendum 1 ref pa#201309045886. added one transformer room for ac revision. added ac unit support on roof. revise garage b entrance. n/a for maher ordinance. | $4,500,000 |
| [201507212092](https://www.permitgraph.org/p/201507212092) | Jul 21, 2015 | Completed: final sign-off Apr 2016 | [360 Post St](https://www.permitgraph.org/a/0295/006) | revision to 201412163862 to simplify scope of work with existing offices to remain |  |
| [201505186561](https://www.permitgraph.org/p/201505186561) | May 18, 2015 | Completed: final sign-off Jan 2017 | [939 Ellis St](https://www.permitgraph.org/a/0738/019) | facde renovate w/ new cladding on building, and the rooftop will be updated to provide private roof-top space for tenants. maher ordinance ext is not required. | $5,670,128 |
| [201505065510](https://www.permitgraph.org/p/201505065510) | May 6, 2015 | Completed: final sign-off Dec 2018 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | revision to s1. revised foundation pile plans based on revised test pile layout & calcs; added sand/oil & grease interceptors in level 1; added cable thru in transformer rooms; revised area separatio… | $150,000 |
| [201504234473](https://www.permitgraph.org/p/201504234473) | Apr 23, 2015 | Never finaled: issued Jun 2015, no final | [315 Montgomery St](https://www.permitgraph.org/a/0259/029) | interior work only at first floor, includes raised floor, new access ramp, new offices & meeting rooms, ceiling design, restrooms and breakroom. also, includes new furniture & finishes. compliance wi… | $600,000 |
| [201503231641](https://www.permitgraph.org/p/201503231641) | Mar 23, 2015 | Completed: final sign-off Aug 2015 | [995 Market St](https://www.permitgraph.org/a/3704/078) | to abate nov numbers 200993151, 200236116, which were performed under permit #201409226984 |  |
| [201503191348](https://www.permitgraph.org/p/201503191348) | Mar 19, 2015 | Expired or cancelled: expired May 2017 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | indicator piles for site permit #201309045886. maher ordinance-exempted per letter. | $1,000 |
| [201502178437](https://www.permitgraph.org/p/201502178437) | Feb 17, 2015 | Completed: final sign-off Nov 2015 | [995 Market St](https://www.permitgraph.org/a/3704/078) | 1st floor: demo select partitions, power/data, & construction of demising wall & slab infill @ (e) stair location between ground floor & mezz. | $100,000 |
| [201412163862](https://www.permitgraph.org/p/201412163862) | Dec 16, 2014 | Completed: final sign-off Apr 2016 | [360 Post St](https://www.permitgraph.org/a/0295/006) | 8/f: office ti on the 8th fl including new partitions, fixtures, finishes, mechanical and electrical. no exterior work. fire protection under sep permit | $386,000 |
| [201410280103](https://www.permitgraph.org/p/201410280103) | Oct 28, 2014 | Completed: final sign-off Aug 2015 | [995 Market St](https://www.permitgraph.org/a/3704/078) | revision to app#201312264763. removing 2 accessible restrooms from mezz level. tenant space to remain vacant per ab-017 until all accessible features and required fixture counts are returned. ada res… |  |
| [201410280106](https://www.permitgraph.org/p/201410280106) | Oct 28, 2014 | Completed: final sign-off Nov 2015 | [995 Market St](https://www.permitgraph.org/a/3704/078) | barrier removal only. install new restrooms in kadvance of new t.i. on mezzanine. mep and fire projection under seperate permits. |  |
| [201409226984](https://www.permitgraph.org/p/201409226984) | Sep 22, 2014 | Completed: final sign-off Aug 2015 | [995 Market St](https://www.permitgraph.org/a/3704/078) | to comply with nov 200236116. restoring aluminum and non-structrual cladding system in designated exterior area with the following. remaining all deteriorated components and installing new flashing s… | $2,340,000 |
| [201408133690](https://www.permitgraph.org/p/201408133690) | Aug 13, 2014 | Completed: final sign-off Apr 2016 | [360 Post St](https://www.permitgraph.org/a/0295/006) | rev. to pa#201203166226 adding fsd's to electrical & communications closets based on building inspectors request. work includes shaft infill with light weight concrete on basement & 1/f. | $12,000 |
| [201406239124](https://www.permitgraph.org/p/201406239124) | Jun 23, 2014 | Completed: final sign-off Apr 2016 | [360 Post St](https://www.permitgraph.org/a/0295/006) | revision to 201203166226. add fire smoke dampers to electrical closets on floor 3-11, except for 5 based on bldg inspectors request | $150,000 |
| [201405095406](https://www.permitgraph.org/p/201405095406) | May 9, 2014 | Completed: final sign-off Apr 2016 | [360 Post St](https://www.permitgraph.org/a/0295/006) | revision to 201203166226. 5th fl change single tenant layout to 2 tenant layout | $95,000 |
| [201404304589](https://www.permitgraph.org/p/201404304589) | Apr 30, 2014 | Completed: final sign-off Jul 2014 | [1019 Market St](https://www.permitgraph.org/a/3703/076) | b/f -for place of assembly permit for commercial t.i. approved under permit #201312194666 to establish a-2 occupancy loads |  |
| [201404284367](https://www.permitgraph.org/p/201404284367) | Apr 28, 2014 | Completed: final sign-off Jul 2015 | [995 Market St](https://www.permitgraph.org/a/3704/078) | comply w/nov 200236116-mock up w/intend to later repair. exterior repair: restore alum & glass curtain wall sys, remove deteriorated components, install new flashing, hand-scrub cleaning panels, rest… | $10,000 |
| [201404183597](https://www.permitgraph.org/p/201404183597) | Apr 18, 2014 | Completed: final sign-off Jun 2014 | [1019 Market St](https://www.permitgraph.org/a/3703/076) | revision to permit #2012-1219-4666 change electrical room names 208,308,406,507 |  |
| [201312204763](https://www.permitgraph.org/p/201312204763) | Dec 20, 2013 | Completed: final sign-off Apr 2015 | [995 Market St](https://www.permitgraph.org/a/3704/078) | voluntary structural upgrade, interior upgrades, restroom upgrades. mep deferred permits. no exterior work in job scope. ** interim controls - market street & soma: see attached. ** | $1,330,000 |
| [201312204717](https://www.permitgraph.org/p/201312204717) | Dec 20, 2013 | Completed: final sign-off Apr 2015 | [995 Market St](https://www.permitgraph.org/a/3704/078) | barrier removal at restrooms on 4, 5, 6, 7, 10, 11, & 14 floors. project scope consists demo of partitions, and associated elec,plumbing and ceiling work at restrooms. install new ceilings,finishes,… | $250,000 |
| [201312194666](https://www.permitgraph.org/p/201312194666) | Dec 19, 2013 | Completed: final sign-off Jun 2014 | [1017 Market St](https://www.permitgraph.org/a/3703/076) | interior commercial tenant improvement & fit-out of (e) bldg totalling approx 75,000 sq ft. improvements comprise open office w/ distributed offices & mtg rms, pantrys, break area, (n) 1-story stairc… | $4,200,000 |
| [201311051207](https://www.permitgraph.org/p/201311051207) | Nov 5, 2013 | Completed: final sign-off Apr 2015 | [995 Market St](https://www.permitgraph.org/a/3704/078) | project scope consists of path of travel upgrades with minor construction involved for compliance with sf dbi administrative bulletin #056. no modification to (e) mechanical or structural system is r… | $18,500 |
| [201309045886](https://www.permitgraph.org/p/201309045886) | Sep 4, 2013 | Completed: final sign-off Dec 2018 | [801 Brannan St](https://www.permitgraph.org/a/3783/001) | to erect 6 stories, no basement, 434 dwelling units, type 1a & 3a, residential/retail/parking building. ** maher: compliance with ordinance no# 155-13 not required ** | $112,000,000 |

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 23 November 2026.
This is the text of https://www.permitgraph.org/contractor/balfour-beatty-construction-llc-979126.