# Alpha Pacific Engineering & Contr. Inc.

Contractor license 982973. San Francisco building permit record since 2000.

- Page: https://www.permitgraph.org/contractor/alpha-pacific-engineering-contr-inc-982973
- JSON: https://www.permitgraph.org/api/contractor?license=982973
- State license record: https://www.cslb.ca.gov/onlineservices/checklicenseII/LicenseDetail.aspx?LicNum=982973

14 permits since 2000: 14 completed. Typically 2 days from filing to permit and 46 days from permit to final inspection.

- Based in: Elk Grove
- On San Francisco permits: May 2016 to Oct 2020
- Last 24 months: 0 permits filed

This is the city's permit record, not a license check. It does not show whether the state license is active, bonded or insured.

## Permits filed each year

| Year | Completed | In progress | Never finaled | Expired or cancelled |
| --- | --- | --- | --- | --- |
| 2016 | 5 | 0 | 0 | 0 |
| 2017 | 1 | 0 | 0 | 0 |
| 2020 | 8 | 0 | 0 | 0 |

## Most recent permits

| Permit | Filed | Outcome | Address | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- |
| [202010076079](https://www.permitgraph.org/p/202010076079) | Oct 7, 2020 | Completed: final sign-off Nov 2020 | [425 Folsom St](https://www.permitgraph.org/a/3748/029) | to obtain final inspection for work approved under permit applications #201402118284, #201507171841 and #201602190005; all work is complete |  |
| [202010076062](https://www.permitgraph.org/p/202010076062) | Oct 7, 2020 | Completed: final sign-off Nov 2020 | [425 Folsom St](https://www.permitgraph.org/a/3748/029) | to obtain final inspection for work approved under permit application #201605278656; all work is complete | $25,000 |
| [202009234806](https://www.permitgraph.org/p/202009234806) | Sep 23, 2020 | Completed: final sign-off Nov 2020 | [1101 Illinois St](https://www.permitgraph.org/a/4175/018) | to obtain final inspection for work approved under permit application #201501286909; all work is complete | $50,000 |
| [202009234811](https://www.permitgraph.org/p/202009234811) | Sep 23, 2020 | Completed: final sign-off Sep 2020 | [1101 Illinois St](https://www.permitgraph.org/a/4175/018) | to obtain final inspection for work approved under permit application #201512225744; all work is complete | $50,000 |
| [202009113956](https://www.permitgraph.org/p/202009113956) | Sep 11, 2020 | Completed: final sign-off Oct 2020 | [425 Folsom St](https://www.permitgraph.org/a/3748/029) | to obtain final inspection for work approved under permit application number 201502269460; all work is complete |  |
| [202009113963](https://www.permitgraph.org/p/202009113963) | Sep 11, 2020 | Completed: final sign-off Sep 2020 | [1101 Illinois St](https://www.permitgraph.org/a/4175/018) | to obtain final inspection for work approved under permit application #201605167473; all work is complete |  |
| [202008312967](https://www.permitgraph.org/p/202008312967) | Aug 31, 2020 | Completed: final sign-off Sep 2020 | [1101 Illinois St](https://www.permitgraph.org/a/4175/018) | to obtain final inspection for work approved under permit application #201407010205; all work is complete | $775,000 |
| [202008272807](https://www.permitgraph.org/p/202008272807) | Aug 27, 2020 | Completed: final sign-off Oct 2020 | [425 Folsom St](https://www.permitgraph.org/a/3748/029) | to obtain final inspection for work approved under permit application #201507313044; all work is complete |  |
| [201706078682](https://www.permitgraph.org/p/201706078682) | Jun 7, 2017 | Completed: final sign-off Jul 2017 | [425 Folsom St](https://www.permitgraph.org/a/3748/029) | installation of new 6" fire sprinkler supply line from curb to new building under pa#201401136157 deferred submittal. ref sprinkler permit #201506249787. |  |
| [201609016566](https://www.permitgraph.org/p/201609016566) | Sep 1, 2016 | Completed: final sign-off Jul 2017 | [1201 Illinois St](https://www.permitgraph.org/a/4175/007) | rev. to pa#201608225676, installation of 8" to 4" fire sprinkler line (supply) from point of connection at curb to new bldg. pa#201402138486, new fire dept. connection & 8" back flow preventor. inter… |  |
| [201608225676](https://www.permitgraph.org/p/201608225676) | Aug 22, 2016 | Completed: final sign-off Jul 2017 | [1201 Illinois St](https://www.permitgraph.org/a/4175/007) | installation of in ground 8" fire sprinkler supply line from curb to new bldg under permit #201402138486. interior fire sprinkler under seperate permit 201603152019. n/a for maher | $35,000 |
| [201608013889](https://www.permitgraph.org/p/201608013889) | Aug 1, 2016 | Completed: final sign-off Feb 2021 | [1201 Illinois St](https://www.permitgraph.org/a/4175/007) | battery room per 2013 cfc sec 608 - install battery and battery chargers in designated battery room. ref pa 2014-0213-8486(r1) n/a for maher ordinance no.155-13. | $120,000 |
| [201605278656](https://www.permitgraph.org/p/201605278656) | May 27, 2016 | Completed: final sign-off Nov 2020 | [425 Folsom St](https://www.permitgraph.org/a/3748/029) | deferred submittal #5 - electrical equipment vault and trench grating and access ladders. ref pa 2014-01-13-6157 r3 | $25,000 |
| [201605167473](https://www.permitgraph.org/p/201605167473) | May 16, 2016 | Completed: final sign-off Nov 2020 | [1201 Illinois St](https://www.permitgraph.org/a/4175/007) | deferred submittal #5. crane rail crane rail and hook bolt connection to support beam. ref app#201402138486 r-1. n/a for maher | $16,000 |

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 23 November 2026.
This is the text of https://www.permitgraph.org/contractor/alpha-pacific-engineering-contr-inc-982973.