# Air Filtration Co. Inc.

Contractor license 404511. San Francisco building permit record since 2000.

- Page: https://www.permitgraph.org/contractor/air-filtration-co-inc-404511
- JSON: https://www.permitgraph.org/api/contractor?license=404511
- State license record: https://www.cslb.ca.gov/onlineservices/checklicenseII/LicenseDetail.aspx?LicNum=404511

19 permits since 2000: 8 completed, 6 never finaled, 5 expired or cancelled. Typically 30 days from filing to permit and 149 days from permit to final inspection. Of the 6 never-finaled permits, 6 are over 10 years old.

- Based in: Oroville
- On San Francisco permits: Jul 2004 to Dec 2015
- Last 24 months: 0 permits filed

This is the city's permit record, not a license check. It does not show whether the state license is active, bonded or insured.

## Permits filed each year

| Year | Completed | In progress | Never finaled | Expired or cancelled |
| --- | --- | --- | --- | --- |
| 2004 | 2 | 0 | 0 | 2 |
| 2005 | 1 | 0 | 1 | 0 |
| 2007 | 0 | 0 | 1 | 0 |
| 2008 | 0 | 0 | 0 | 1 |
| 2009 | 1 | 0 | 2 | 2 |
| 2011 | 0 | 0 | 1 | 0 |
| 2012 | 2 | 0 | 0 | 0 |
| 2014 | 0 | 0 | 1 | 0 |
| 2015 | 2 | 0 | 0 | 0 |

## Most recent permits

| Permit | Filed | Outcome | Address | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- |
| [201512185527](https://www.permitgraph.org/p/201512185527) | Dec 18, 2015 | Completed: final sign-off Jan 2016 | [5666 Mission St](https://www.permitgraph.org/a/7099/012) | revision to 201509217597, as build - install two 12 inch 90 degree elbows. |  |
| [201509217597](https://www.permitgraph.org/p/201509217597) | Sep 21, 2015 | Completed: final sign-off Jan 2016 | [5666 Mission St](https://www.permitgraph.org/a/7099/012) | install new autobdy spray booth, mixing room and prep bench. replacing (e) in same location. | $110,000 |
| [201401247016](https://www.permitgraph.org/p/201401247016) | Jan 24, 2014 | Never finaled: issued Mar 2014, no final | [2715 Geary Bl](https://www.permitgraph.org/a/1092/036) | add heated air make-up system to extg permitted auto paint spray booth. | $30,700 |
| [201203156155](https://www.permitgraph.org/p/201203156155) | Mar 15, 2012 | Completed: final sign-off Jul 2012 | [1315 Carroll Av](https://www.permitgraph.org/a/4883/025) | installation of automotive style paint spray booth w/6' exhaust duct above roofline. use of equipment for "event co" - not automotive. under separate permit - fire suppression by licensed contractor… | $45,600 |
| [201201091900](https://www.permitgraph.org/p/201201091900) | Jan 9, 2012 | Completed: final sign-off Feb 2013 | [2220 Revere Av](https://www.permitgraph.org/a/5333/038) | #b: mechanical installation of auto paint spray booth with heated air make up system. exhaust duct terminating 6ft above roof line. fire suppression done by sub-contractor, not afc. replace (e) spray… | $61,530 |
| [201108102177](https://www.permitgraph.org/p/201108102177) | Aug 10, 2011 | Never finaled: issued Aug 2011, no final | [2715 Geary Bl](https://www.permitgraph.org/a/1092/036) | install exhaust filter bench for sanding only in (e) auto body shop. includes exhaust duct terminating 6 ft above roof line. also installation of curtains to enclose exhaust bench | $12,900 |
| [200906120342](https://www.permitgraph.org/p/200906120342) | Jun 12, 2009 | Expired or cancelled: cancelled Jan 2026 | [505 South Van Ness Av](https://www.permitgraph.org/a/3571/017) | installation of exhaust bench with exhaust duct 6ft above roof line. prupose-spot paint bumpers repair | $30,000 |
| [200905057685](https://www.permitgraph.org/p/200905057685) | May 5, 2009 | Never finaled: issued May 2009, no final | [2715 Geary Bl](https://www.permitgraph.org/a/1092/036) | install auto paint spray booth w/ exhaust duet 6ft above roof line. revision to 200812178667, spray booth manufacturer change |  |
| [200905057698](https://www.permitgraph.org/p/200905057698) | May 5, 2009 | Completed: final sign-off Dec 2009 | [165 14th St](https://www.permitgraph.org/a/3549/047) | install 1 auto paint spray booth w/ heated air make-up system, 1 paint mix rm, 1 exhaust bench w/ duct 6 ft above roof line, new booth replaces existing paint booth w/ duct, exhaust bench is existing… | $114,515 |
| [200903244736](https://www.permitgraph.org/p/200903244736) | Mar 24, 2009 | Expired or cancelled: cancelled Jan 2026 | [1419 Pacific Av](https://www.permitgraph.org/a/0185/041) | installation of exhaust filtered bench with duct 6ft above roof line (for paint prep sanding). fire suppression by sub-contractor filed seperately | $14,146 |
| [200901270852](https://www.permitgraph.org/p/200901270852) | Jan 27, 2009 | Never finaled: issued Feb 2009, no final | [450 Potrero Av](https://www.permitgraph.org/a/3973/002A) | replace existing spray paint with new auto paint spray booth with heated air make-up system, duct 6' above roof line. also add (1) paint mix room. correct 1 restroom door swing. fire suppression by l… | $116,273 |
| [200803257955](https://www.permitgraph.org/p/200803257955) | Mar 25, 2008 | Expired or cancelled: expired May 2010 | [4352 Mission St](https://www.permitgraph.org/a/6799/004) | sheet metal erection of booth, air makeup. installation of automotive paint spray booth with fresh air make-up (no heat) & duct above roof line. roof penetration, air line plumbing, electrical hook-u… | $45,860 |
| [200707197207](https://www.permitgraph.org/p/200707197207) | Jul 19, 2007 | Never finaled: issued Aug 2007, no final | [3536 Sacramento St](https://www.permitgraph.org/a/1010/028) | install 3 stacks of 25-1/2" dia. duct to existing exhaust duct. (securing with guide wires) | $5,300 |
| [200507198047](https://www.permitgraph.org/p/200507198047) | Jul 19, 2005 | Completed: final sign-off Mar 2006 | [981 Howard St](https://www.permitgraph.org/a/3732/119) | relocation of customers (e) paint spray booth (automotive) air filtration model ara2712, from sansom | $17,367 |
| [200501062644](https://www.permitgraph.org/p/200501062644) | Jan 6, 2005 | Never finaled: issued Apr 2005, no final | [1835 Folsom St](https://www.permitgraph.org/a/3550/019) | installation of metal canopy over paint spray booth. (paint spray booth under#200407280072 | $7,300 |
| [200412222014](https://www.permitgraph.org/p/200412222014) | Dec 22, 2004 | Expired or cancelled: cancelled Mar 2007 | [150 Toland St](https://www.permitgraph.org/a/5230/015) | #5 - mechanical installation of automative spray paint booth with fresh aire make up intake & | $35,500 |
| [200408101199](https://www.permitgraph.org/p/200408101199) | Aug 10, 2004 | Completed: final sign-off Aug 2005 | [384 07th St](https://www.permitgraph.org/a/3755/015) | mechanical installation of automotive spray paint booth w/fresh air makeup and ducts | $36,200 |
| [200408101195](https://www.permitgraph.org/p/200408101195) | Aug 10, 2004 | Expired or cancelled: expired Mar 2007 | [440 09th St](https://www.permitgraph.org/a/3525/006) | mechanical installation of automtoive spray paint booth, w/heated air makeup & duct, auto prep benc | $116,500 |
| [200407280072](https://www.permitgraph.org/p/200407280072) | Jul 28, 2004 | Completed: final sign-off Mar 2006 | [1835 Folsom St](https://www.permitgraph.org/a/3550/019) | mechanical installation of automotive spray paint | $95,500 |

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 23 November 2026.