# 312 Connecticut St

Block 4035, lot 003. Page: https://www.permitgraph.org/a/4035/003

- City's use: Commercial Misc
- Built: 1996
- Stories: 1
- Rooms: 2 bathrooms
- Building: 9,940 sq ft
- Lot: 3,367 sq ft
- Zoning: NCT2
- Construction type: C

From the assessor's latest secured roll, which can lag recent work.

## Permits filed here

15 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [202501249024](https://www.permitgraph.org/p/202501249024) | Jan 24, 2025 | Completed: final sign-off Jan 2025 | [312 Connecticut St](https://www.permitgraph.org/a/4035/003) | [General Express Construction Dba Roof Ex](https://www.permitgraph.org/contractor/general-express-construction-dba-roof-ex-1072766) | re-roofing. hot works. | $17,898 |
| [202404039240](https://www.permitgraph.org/p/202404039240) | Apr 3, 2024 | In progress: filed Apr 2024, not yet issued | [312 Connecticut St](https://www.permitgraph.org/a/4035/003) |  | remove (e) 2 powder rooms (toilet & sink) @ street level and 1 powder room @ 3nd level; remove partial floor @ 2nd level; add steel beams to support 2nd level (partial) change of occupacny to elimina… | $45,000 |
| [201309278023](https://www.permitgraph.org/p/201309278023) | Sep 27, 2013 | Completed: final sign-off Oct 2013 | [312 Connecticut St](https://www.permitgraph.org/a/4035/003) |  | to obtain final inspection for work approved under pa#200104056117. all work is complete. |  |
| [201309278019](https://www.permitgraph.org/p/201309278019) | Sep 27, 2013 | Completed: final sign-off Oct 2013 | [312 Connecticut St](https://www.permitgraph.org/a/4035/003) |  | to obtain final inspection for work approved under pa#9307498. all work is complete. |  |
| [201309278012](https://www.permitgraph.org/p/201309278012) | Sep 27, 2013 | Completed: final sign-off Oct 2013 | [312 Connecticut St](https://www.permitgraph.org/a/4035/003) |  | to obtain final inspection for work approved under pa#9303117. all work is complete. |  |
| [201309278020](https://www.permitgraph.org/p/201309278020) | Sep 27, 2013 | Completed: final sign-off Oct 2013 | [312 Connecticut St](https://www.permitgraph.org/a/4035/003) |  | to obtain final inspection for work approved under pa#9307498. all work is complete. |  |
| [201309278022](https://www.permitgraph.org/p/201309278022) | Sep 27, 2013 | Completed: final sign-off Oct 2013 | [312 Connecticut St](https://www.permitgraph.org/a/4035/003) |  | to obtain final inspection for work approved under pa#9712183. all work is complete. |  |
| [201309278018](https://www.permitgraph.org/p/201309278018) | Sep 27, 2013 | Completed: final sign-off Oct 2013 | [312 Connecticut St](https://www.permitgraph.org/a/4035/003) |  | to obtain final inspection for work approved under pa#9609446. all work is complete. |  |
| [201309278021](https://www.permitgraph.org/p/201309278021) | Sep 27, 2013 | Completed: final sign-off Oct 2013 | [312 Connecticut St](https://www.permitgraph.org/a/4035/003) |  | to obtain final inspection for work approved under pa#9609481. all work is complete. |  |
| [201212035362](https://www.permitgraph.org/p/201212035362) | Dec 3, 2012 | Completed: final sign-off Jun 2013 | [312 Connecticut St](https://www.permitgraph.org/a/4035/003) |  | poured conc balcony & pipe w/cable handrail.addition to permit 9320874. to comply with complaint/nov # 201130941. | $3,000 |
| [201106097825](https://www.permitgraph.org/p/201106097825) | Jun 9, 2011 | Never finaled: filed Jun 2011, never issued | [312 Connecticut St](https://www.permitgraph.org/a/4035/003) |  | comply with nov# 201130941-poured concrete balcony & handrails, addition to pa# 9320874 | $2,000 |
| [201101269083](https://www.permitgraph.org/p/201101269083) | Jan 26, 2011 | Completed: final sign-off Oct 2013 | [312 Connecticut St](https://www.permitgraph.org/a/4035/003) |  | to obtain final inspection for work approved under pa 9506233; all work is complete |  |
| [201101269084](https://www.permitgraph.org/p/201101269084) | Jan 26, 2011 | Completed: final sign-off Oct 2013 | [312 Connecticut St](https://www.permitgraph.org/a/4035/003) |  | to obtain final inspection for work approved under pa 9320874; all work is complete |  |
| [M187592](https://www.permitgraph.org/p/M187592) | Jan 6, 2010 | Never finaled: issued Jan 2010, no final | [312 Connecticut St](https://www.permitgraph.org/a/4035/003) |  | street space & sidewalk |  |
| [200104056117](https://www.permitgraph.org/p/200104056117) | Apr 5, 2001 | Expired or cancelled: expired Oct 2001 | [312 Connecticut St](https://www.permitgraph.org/a/4035/003) |  | renewal per app #9300874/installing stairway/some sheetrock and trimwork | $10,000 |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [General Express Construction Dba Roof Ex](https://www.permitgraph.org/contractor/general-express-construction-dba-roof-ex-1072766)
- Architects: [Terry Lindahl](https://www.permitgraph.org/professional/terry-lindahl-C17896)
- Engineers: [Timothy O'sullivan](https://www.permitgraph.org/professional/timothy-o-sullivan-C35235)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/a/4035/003.