# 2440 16th St

Block 3928, lot 013. Page: https://www.permitgraph.org/a/3928/013

- City's use: Industrial
- Built: 1957
- Stories: 3
- Building: 128,040 sq ft
- Lot: 46,250 sq ft
- Zoning: M1
- Construction type: NA

From the assessor's latest secured roll, which can lag recent work.

## Permits filed here

18 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [202209293384](https://www.permitgraph.org/p/202209293384) | Sep 29, 2022 | Completed: final sign-off Mar 2023 | [2440 16th St](https://www.permitgraph.org/a/3928/013) | [Metropolitan Electrical Construction](https://www.permitgraph.org/contractor/metropolitan-electrical-construction-401047) | at&t modif of unmanned telecom, remove/replace (6) antennas, remove (6) tma's, install new rf safety signage, r/r (12) batteries (leudacid) w/in(e) cabinet, r/r cabling w/in sector a cable tray, inst… | $55,000 |
| [202206156364](https://www.permitgraph.org/p/202206156364) | Jun 15, 2022 | Completed: final sign-off Dec 2022 | [2440 16th St](https://www.permitgraph.org/a/3928/013) | [New Pacific Roofing Company Inc](https://www.permitgraph.org/contractor/new-pacific-roofing-company-inc-810659) | reroofing | $198,000 |
| [202005207653](https://www.permitgraph.org/p/202005207653) | May 20, 2020 | Completed: final sign-off Sep 2022 | [2440 16th St](https://www.permitgraph.org/a/3928/013) | [Metropolitan Electrical Construction](https://www.permitgraph.org/contractor/metropolitan-electrical-construction-401047) | at&t modification: swap (3) (e) antennas, paint to match; remove (3) (e) rrus; install (6) (n) rrus; install (1) (n) stacked purcell cabinet above (e) cabinet; install (1) (n) battery cabinet w/ (8)… | $25,000 |
| [201903195668](https://www.permitgraph.org/p/201903195668) | Mar 19, 2019 | Completed: final sign-off Jun 2019 | [2440 16th St](https://www.permitgraph.org/a/3928/013) | [Metropolitan Electrical Construction](https://www.permitgraph.org/contractor/metropolitan-electrical-construction-401047) | at&t revision to app#201804105931. do not install new emerson power plant, remove 12 extg 90 ah batteries, swap 12 extg 155 ah batteries with 12 nw 180 ah batteries inside extg power plant. |  |
| [201804105931](https://www.permitgraph.org/p/201804105931) | Apr 10, 2018 | Completed: final sign-off Jun 2019 | [2440 16th St](https://www.permitgraph.org/a/3928/013) | [Metropolitan Electrical Construction](https://www.permitgraph.org/contractor/metropolitan-electrical-construction-401047) | at&t mobility to (e) att telecom facility: remove and replace 6 (e) antennas with 6 (n) antennas with cable shrouds, paint to match; install 2 (n) cabinets; install other small equipment, install (n)… | $43,000 |
| [201703302828](https://www.permitgraph.org/p/201703302828) | Mar 30, 2017 | Completed: final sign-off Oct 2017 | [2440 16th St](https://www.permitgraph.org/a/3928/013) | [Electric Tech Construction Inc](https://www.permitgraph.org/contractor/electric-tech-construction-inc-897792) | att modification: r&r 3 extg antennas with 3 new antennas, install 3 new rrus-32 b66, 3 new rrus-11, r&r extg dus-41 with new dus 5216 & new xmu, r&r extg h frame with nw h-frame, extg rba72 with nw… | $33,000 |
| [201606220571](https://www.permitgraph.org/p/201606220571) | Jun 22, 2016 | Completed: final sign-off Nov 2016 | [2440 16th St](https://www.permitgraph.org/a/3928/013) | [Electric Tech Construction Inc](https://www.permitgraph.org/contractor/electric-tech-construction-inc-897792) | at&t modification: r&r 6 extg antennas with 6 nw antennas, relocate one extg antenna to nw antenna mount, install 3 new rrus -32, r&r 3 extg rrus-12 with 3 new rrus-32 b2; install surge suppressor on… | $32,000 |
| [201404213736](https://www.permitgraph.org/p/201404213736) | Apr 21, 2014 | Expired or cancelled: cancelled Oct 2016 | [2440 16th St](https://www.permitgraph.org/a/3928/013) | [Nu Rev Communications Inc.](https://www.permitgraph.org/contractor/nu-rev-communications-inc-962583) | modification to an (e) unmanned att telecommunication facility consisting of adding a (n) dus41 unit inside a (e) purcell cabinet & adding (3) (n) rrus-12 w/(3) (n) a2 modules. compliance with ordina… | $9,500 |
| [201302200581](https://www.permitgraph.org/p/201302200581) | Feb 20, 2013 | Completed: final sign-off Nov 2014 | [2440 16th St](https://www.permitgraph.org/a/3928/013) | [Nu Rev Communications Inc.](https://www.permitgraph.org/contractor/nu-rev-communications-inc-962583) | modification to an (e) unmanned telecommunication facility consisting of removing & replacing 3 (e) att & t antennas with 3 new at & t antennas; compliance with ord 155-13 not required | $8,000 |
| [201111018081](https://www.permitgraph.org/p/201111018081) | Nov 1, 2011 | Completed: final sign-off Mar 2012 | [2440 16th St](https://www.permitgraph.org/a/3928/013) | [Peak General Contractors Inc](https://www.permitgraph.org/contractor/peak-general-contractors-inc-854299) | adding handicap chairlift at ground floor per plan. | $11,500 |
| [201102150297](https://www.permitgraph.org/p/201102150297) | Feb 15, 2011 | Completed: final sign-off Aug 2011 | [2440 16th St](https://www.permitgraph.org/a/3928/013) | [Cba Site Services Inc.](https://www.permitgraph.org/contractor/cba-site-services-inc-455726) | remove & replace (3) antennas. add 6 rru's, add (n) rba-72 cabinet & (2) purcell lte cabinets, add (n) fiber inner ducts inside (b) cable tray. | $23,000 |
| [201005112201](https://www.permitgraph.org/p/201005112201) | May 11, 2010 | Completed: final sign-off Jul 2011 | [2440 16th St](https://www.permitgraph.org/a/3928/013) | [Broken Arrow Communications Inc](https://www.permitgraph.org/contractor/broken-arrow-communications-inc-853651) | a modif. to an (e) unmanned telecommunications facility consisting of adding a(n)3106 cabinet to an(e)outdoor equipment area on rooftop.removing&replacing (3)(e)antennae w/ret's(remote electronic til… | $28,000 |
| [200902051496](https://www.permitgraph.org/p/200902051496) | Feb 5, 2009 | Expired or cancelled: withdrawn Jul 2016 | [2440 16th St](https://www.permitgraph.org/a/3928/013) |  | add 6 runs coax cable, install 6 tma's, 3 ret cables, and 6 new rcu's. | $8,000 |
| [M73449](https://www.permitgraph.org/p/M73449) | Jun 18, 2007 | Never finaled: issued Jun 2007, no final | [2440 16th St](https://www.permitgraph.org/a/3928/013) |  | street space |  |
| [200603166853](https://www.permitgraph.org/p/200603166853) | Mar 16, 2006 | Expired or cancelled: expired Feb 2007 | [2440 16th St](https://www.permitgraph.org/a/3928/013) |  | building alteration of removing catwalk between buildings. | $5,000 |
| [200512271035](https://www.permitgraph.org/p/200512271035) | Dec 27, 2005 | Expired or cancelled: cancelled Dec 2006 | [2440 16th St](https://www.permitgraph.org/a/3928/013) |  | replace existing umts cabinet with new rbs3106 umts cabinet. installation of 2 ericsson rbs 2106 equipment cabinets and minibay mcpa enclosure on the roof of an existing building. replacement of 3 ex… | $20,000 |
| [M28814](https://www.permitgraph.org/p/M28814) | Aug 19, 2004 | Never finaled: issued Aug 2004, no final | [1634 Bryant St](https://www.permitgraph.org/a/3928/013) |  | street space & sidewalk permit |  |
| [200205075993](https://www.permitgraph.org/p/200205075993) | May 7, 2002 | Completed: final sign-off Jun 2003 | [2440 16th St](https://www.permitgraph.org/a/3928/013) | [Pacific Tower Enterprises](https://www.permitgraph.org/contractor/pacific-tower-enterprises-653099) | install 6 wireless panel antennas & 1 gps antenna onto (e)roof parapets, install equip on skid frame | $60,000 |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [Metropolitan Electrical Construction](https://www.permitgraph.org/contractor/metropolitan-electrical-construction-401047) (4), [Electric Tech Construction Inc](https://www.permitgraph.org/contractor/electric-tech-construction-inc-897792) (2), [Nu Rev Communications Inc.](https://www.permitgraph.org/contractor/nu-rev-communications-inc-962583) (2), [Broken Arrow Communications Inc](https://www.permitgraph.org/contractor/broken-arrow-communications-inc-853651), [Cba Site Services Inc.](https://www.permitgraph.org/contractor/cba-site-services-inc-455726), [New Pacific Roofing Company Inc](https://www.permitgraph.org/contractor/new-pacific-roofing-company-inc-810659), [Pacific Tower Enterprises](https://www.permitgraph.org/contractor/pacific-tower-enterprises-653099), [Peak General Contractors Inc](https://www.permitgraph.org/contractor/peak-general-contractors-inc-854299)
- Architects: [Jeffrey Rome](https://www.permitgraph.org/professional/jeffrey-rome-C20876) (2)
- Engineers: [Streamline](https://www.permitgraph.org/professional/streamline-S6336) (2), [Chris E Lee](https://www.permitgraph.org/professional/chris-e-lee-76549), [John Anderson Jr.](https://www.permitgraph.org/professional/john-anderson-jr-69368), [Larry Houghtby](https://www.permitgraph.org/professional/larry-houghtby-C69891), [Zahra Gerami](https://www.permitgraph.org/professional/zahra-gerami-89570)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.