# 20 Heron St

Block 3755, lot 044. Page: https://www.permitgraph.org/a/3755/044

- City's use: Industrial
- Built: 1931
- Stories: 4
- Units: 1
- Rooms: 4 bathrooms
- Building: 26,162 sq ft
- Lot: 6,900 sq ft
- Zoning: SLR
- Construction type: D

From the assessor's latest secured roll, which can lag recent work.

## Permits filed here

35 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [202210184587](https://www.permitgraph.org/p/202210184587) | Oct 18, 2022 | Completed: final sign-off Feb 2023 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Tot'l Environm'l /Pwer Sym Inc Dba:Teps](https://www.permitgraph.org/contractor/tot-l-environm-l-pwer-sym-inc-dba-teps-817449) | modification to (e) verizon electrical system to meet additional power requirements. | $5,000 |
| [202208039823](https://www.permitgraph.org/p/202208039823) | Aug 3, 2022 | Never finaled: issued Jan 2023, no final | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [C C I Commercial Construction & Improv](https://www.permitgraph.org/contractor/c-c-i-commercial-construction-improv-985808) | change of occupancy & use from s-2 to f-1, light manufacturing. |  |
| [202207128241](https://www.permitgraph.org/p/202207128241) | Jul 12, 2022 | Completed: final sign-off Jul 2022 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Rrs Fire Alarm Inc Dba California Fire D](https://www.permitgraph.org/contractor/rrs-fire-alarm-inc-dba-california-fire-d-1046925) | revision to pa# 202202027152; add strobes, smokes & duct detectors on 1st, 3rd & 4th floors; ti ref pa# 202110281420 | $5,000 |
| [202204142201](https://www.permitgraph.org/p/202204142201) | Apr 14, 2022 | Completed: final sign-off Jul 2022 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [City Mechanical Inc](https://www.permitgraph.org/contractor/city-mechanical-inc-622065) | tenant improvement - install new vrf indoor units. ref pa# 202110281420. | $55,000 |
| [202204041462](https://www.permitgraph.org/p/202204041462) | Apr 4, 2022 | Never finaled: issued Jul 2022, no final | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Quality Telecom Consultants](https://www.permitgraph.org/contractor/quality-telecom-consultants-814859) | verizon wireless: remove 3 (e) antennas. install 3 (n) antennas. install 3 (n) integrated units. | $40,000 |
| [202203049264](https://www.permitgraph.org/p/202203049264) | Mar 4, 2022 | Completed: final sign-off Jul 2022 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Elson Electric Holdings Inc](https://www.permitgraph.org/contractor/elson-electric-holdings-inc-1045018) | commerical t.i. t24 electrical compliance. new lighting, led. new run off (e) panel. ref e/p ew202203011732 & t.i pa 202110281420. | $100,000 |
| [202202027152](https://www.permitgraph.org/p/202202027152) | Feb 2, 2022 | Completed: final sign-off Aug 2022 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Rrs Fire Alarm Inc Dba California Fire D](https://www.permitgraph.org/contractor/rrs-fire-alarm-inc-dba-california-fire-d-1046925) | new fire alarm system. add one strobe for 3/f ti. | $5,000 |
| [202201286920](https://www.permitgraph.org/p/202201286920) | Jan 28, 2022 | Completed: final sign-off Jun 2022 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Aura Fire Safety Inc](https://www.permitgraph.org/contractor/aura-fire-safety-inc-966824) | 1st fl - modification of (e) fire sprinkler system per approved building plans 2021-1028-1420 | $6,850 |
| [202110281420](https://www.permitgraph.org/p/202110281420) | Oct 28, 2021 | Completed: final sign-off Jul 2022 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [C C I Commercial Construction & Improv](https://www.permitgraph.org/contractor/c-c-i-commercial-construction-improv-985808) | new interior wall partitions, ada shower, kitchenetts and pendant lighting on 1st to 4th floor. | $225,000 |
| [202106112208](https://www.permitgraph.org/p/202106112208) | Jun 11, 2021 | Completed: final sign-off Nov 2021 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Elson Electric Holdings Inc](https://www.permitgraph.org/contractor/elson-electric-holdings-inc-1045018) | install new lighting in looby, stairwells & restrooms. install new subpanels on each floor. 202012020112. maher n/a. | $70,000 |
| [202104279384](https://www.permitgraph.org/p/202104279384) | Apr 27, 2021 | Completed: final sign-off Aug 2021 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Aura Fire Safety Inc](https://www.permitgraph.org/contractor/aura-fire-safety-inc-966824) | added 1 sprinkler heads at elevator lobby 4th floor. as built plans refer to #2020-0507-7345 | $1,000 |
| [202103227036](https://www.permitgraph.org/p/202103227036) | Mar 22, 2021 | Completed: final sign-off Aug 2021 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [City Mechanical Inc](https://www.permitgraph.org/contractor/city-mechanical-inc-622065) | vrf equipment and ventilation impovements. ref app#202003036027 | $120,000 |
| [202012020112](https://www.permitgraph.org/p/202012020112) | Dec 2, 2020 | Completed: final sign-off Nov 2021 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [C C I Commercial Construction & Improv](https://www.permitgraph.org/contractor/c-c-i-commercial-construction-improv-985808) | minor rev to pa202003036027 including removal of kitchenettes on floors 1-3, and shower at g/f. door added to switch gear from and changes to elevator / lobby wall layout. |  |
| [202010086198](https://www.permitgraph.org/p/202010086198) | Oct 8, 2020 | Completed: final sign-off Nov 2021 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [C C I Commercial Construction & Improv](https://www.permitgraph.org/contractor/c-c-i-commercial-construction-improv-985808) | (n) elevator extension to roof deck, plus new vehicle/man door entrance at rodgers st and new property line windows. | $48,000 |
| [202009265123](https://www.permitgraph.org/p/202009265123) | Sep 26, 2020 | Completed: final sign-off Jun 2021 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [True North Signs & Graphic Services](https://www.permitgraph.org/contractor/true-north-signs-graphic-services-856249) | evacuation sign permit. all plaques interior | $3,850 |
| [202009234789](https://www.permitgraph.org/p/202009234789) | Sep 23, 2020 | Completed: final sign-off Nov 2021 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Rrs Fire Alarm Inc Dba California Fire D](https://www.permitgraph.org/contractor/rrs-fire-alarm-inc-dba-california-fire-d-1046925) | installation of new fire alarm system for core and shell | $30,000 |
| [202009184472](https://www.permitgraph.org/p/202009184472) | Sep 18, 2020 | Completed: final sign-off Oct 2021 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Tot'l Environm'l /Pwer Sym Inc Dba:Teps](https://www.permitgraph.org/contractor/tot-l-environm-l-pwer-sym-inc-dba-teps-817449) | verizon: remove (e) 30kw diesel generator and replace with (n) 80kw diesel generator with (n) 52 gallon replacement tank; relocate (2) (e) condenser units; install (1) (n) condenser unit; no change t… | $55,000 |
| [202009124066](https://www.permitgraph.org/p/202009124066) | Sep 12, 2020 | Expired or cancelled: withdrawn May 2021 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [C C I Commercial Construction & Improv](https://www.permitgraph.org/contractor/c-c-i-commercial-construction-improv-985808) | new open-air security gate & new curb cut on rodgers st. plus structural details at 4th fl. | $52,000 |
| [M1221307](https://www.permitgraph.org/p/M1221307) | Aug 11, 2020 | Never finaled: issued Aug 2020, no final | [20 Heron St](https://www.permitgraph.org/a/3755/044) |  | street space |  |
| [202005077345](https://www.permitgraph.org/p/202005077345) | May 7, 2020 | Completed: final sign-off Aug 2021 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Aura Fire Safety Inc](https://www.permitgraph.org/contractor/aura-fire-safety-inc-966824) | install fire sprinklers per nfps 13 and install fire underground fire line per nfpa24. ref to building plan 2020 0303 6027 | $150,000 |
| [202003036027](https://www.permitgraph.org/p/202003036027) | Mar 3, 2020 | Completed: final sign-off Nov 2021 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [C C I Commercial Construction & Improv](https://www.permitgraph.org/contractor/c-c-i-commercial-construction-improv-985808) | new elevator, new communicating stair, ada compliant restroom at each level | $245,000 |
| [201912068886](https://www.permitgraph.org/p/201912068886) | Dec 6, 2019 | Completed: final sign-off Nov 2020 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [C C I Commercial Construction & Improv](https://www.permitgraph.org/contractor/c-c-i-commercial-construction-improv-985808) | demolition of interior non-bearing walls per ab-017 | $24,000 |
| [201902263834](https://www.permitgraph.org/p/201902263834) | Feb 26, 2019 | Completed: final sign-off Oct 2021 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Tot'l Environm'l /Pwer Sym Inc Dba:Teps](https://www.permitgraph.org/contractor/tot-l-environm-l-pwer-sym-inc-dba-teps-817449) | verizon modification: install 2 (n) equipment room partitions; remove 1 (e) partition; extend 1 (e) equipment room ceiling; install 2 (n) battery racks; 3 (n) air cooling units; 1 (n) power dist. pan… | $60,000 |
| [201807033625](https://www.permitgraph.org/p/201807033625) | Jul 3, 2018 | Never finaled: issued Sep 2018, no final | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Jfc Construction Inc.](https://www.permitgraph.org/contractor/jfc-construction-inc-592562) | ste3755 in (e): installation of (2) 4" conduits appx(205lf),4 pull cans,(8) 4" cores,(1)1.25" innerduct 25lf,(2)1.5"unistruct hangers,(1) 3/4"muletape in all new & (e) conduits/innerduct.no modificat… | $20,000 |
| [201611021766](https://www.permitgraph.org/p/201611021766) | Nov 2, 2016 | Expired or cancelled: cancelled Aug 2022 | [20 Heron St](https://www.permitgraph.org/a/3755/044) |  | install 1 hvac unit on roof & 2 stacked ac units on roof (total of 3 ac units). remove (e) 200a meter on ground floor & replace it iwth 400a meter. ** maher: n/a ** | $10,000 |
| [201509217494](https://www.permitgraph.org/p/201509217494) | Sep 21, 2015 | Completed: final sign-off Jan 2016 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Apex Site Solutions Inc](https://www.permitgraph.org/contractor/apex-site-solutions-inc-956144) | modification to (e) verizon wireless site. all interior work inside ti equipment room on roof of building. install 3 pcs rrhs in (e) equipment room. install (10 fiber tray at (e) equipment rack, remo… | $10,000 |
| [M598047](https://www.permitgraph.org/p/M598047) | Jun 26, 2015 | Never finaled: issued Jun 2015, no final | [20 Heron St](https://www.permitgraph.org/a/3755/044) |  | streetspace |  |
| [M588827](https://www.permitgraph.org/p/M588827) | May 19, 2015 | Never finaled: issued May 2015, no final | [20 Heron St](https://www.permitgraph.org/a/3755/044) |  | street space & sidewalk repair. |  |
| [201310038365](https://www.permitgraph.org/p/201310038365) | Oct 3, 2013 | Never finaled: issued May 2015, no final | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Quality Telecom Consultants](https://www.permitgraph.org/contractor/quality-telecom-consultants-814859) | remove / replace 12 (e) wireless antenna's with like for like antennas. replacement of coax cable, installation of support equipment for antenna. verizon wireless | $10,500 |
| [201210021130](https://www.permitgraph.org/p/201210021130) | Oct 2, 2012 | Completed: final sign-off Aug 2013 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Jfc Construction Inc.](https://www.permitgraph.org/contractor/jfc-construction-inc-592562) | install 1 small diesel generator as backup power on roof of the building. | $9,000 |
| [200905198706](https://www.permitgraph.org/p/200905198706) | May 19, 2009 | Completed: final sign-off Nov 2009 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [N S A Wireless Inc](https://www.permitgraph.org/contractor/n-s-a-wireless-inc-867615), [A C Construction](https://www.permitgraph.org/contractor/a-c-construction-869949) | verizon wireless proposes to remove and replace six extg 4' panel antenas. | $2,500 |
| [200702053353](https://www.permitgraph.org/p/200702053353) | Feb 5, 2007 | Never finaled: issued Feb 2007, no final | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Broken Arrow Communications Inc](https://www.permitgraph.org/contractor/broken-arrow-communications-inc-853651) | renew appl#200512059496 for final inspection. |  |
| [200512059496](https://www.permitgraph.org/p/200512059496) | Dec 5, 2005 | Never finaled: issued Dec 2005, no final | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Broken Arrow Communications Inc](https://www.permitgraph.org/contractor/broken-arrow-communications-inc-853651) | renew appl#200502024658 for final inspection. replace center antennas |  |
| [200502024658](https://www.permitgraph.org/p/200502024658) | Feb 2, 2005 | Never finaled: issued Jun 2005, no final | [20 Heron St](https://www.permitgraph.org/a/3755/044) |  | replace center antenna on each sector, 6- total | $2,500 |
| [200207171665](https://www.permitgraph.org/p/200207171665) | Jul 17, 2002 | Completed: final sign-off Mar 2003 | [20 Heron St](https://www.permitgraph.org/a/3755/044) | [Balch Petroleum Contractors & Builders](https://www.permitgraph.org/contractor/balch-petroleum-contractors-builders-396575) | verizon wireless cell site;12 antennas mounted to roof structure | $100,000 |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [C C I Commercial Construction & Improv](https://www.permitgraph.org/contractor/c-c-i-commercial-construction-improv-985808) (7), [Aura Fire Safety Inc](https://www.permitgraph.org/contractor/aura-fire-safety-inc-966824) (3), [Rrs Fire Alarm Inc Dba California Fire D](https://www.permitgraph.org/contractor/rrs-fire-alarm-inc-dba-california-fire-d-1046925) (3), [Tot'l Environm'l /Pwer Sym Inc Dba:Teps](https://www.permitgraph.org/contractor/tot-l-environm-l-pwer-sym-inc-dba-teps-817449) (3), [Broken Arrow Communications Inc](https://www.permitgraph.org/contractor/broken-arrow-communications-inc-853651) (2), [City Mechanical Inc](https://www.permitgraph.org/contractor/city-mechanical-inc-622065) (2), [Elson Electric Holdings Inc](https://www.permitgraph.org/contractor/elson-electric-holdings-inc-1045018) (2), [Jfc Construction Inc.](https://www.permitgraph.org/contractor/jfc-construction-inc-592562) (2), [Quality Telecom Consultants](https://www.permitgraph.org/contractor/quality-telecom-consultants-814859) (2), [A C Construction](https://www.permitgraph.org/contractor/a-c-construction-869949), [Apex Site Solutions Inc](https://www.permitgraph.org/contractor/apex-site-solutions-inc-956144), [Balch Petroleum Contractors & Builders](https://www.permitgraph.org/contractor/balch-petroleum-contractors-builders-396575), [N S A Wireless Inc](https://www.permitgraph.org/contractor/n-s-a-wireless-inc-867615), [True North Signs & Graphic Services](https://www.permitgraph.org/contractor/true-north-signs-graphic-services-856249)
- Architects: [Albert Costa](https://www.permitgraph.org/professional/albert-costa-C25678) (7), [Conrad Alfaro](https://www.permitgraph.org/professional/conrad-alfaro-C28899)
- Engineers: [Edward Rivera](https://www.permitgraph.org/professional/edward-rivera-2835) (2), [Conrad Alfaro](https://www.permitgraph.org/professional/conrad-alfaro-C28899), [Esrah Persellin](https://www.permitgraph.org/professional/esrah-persellin-C88844), [James A. Underwood](https://www.permitgraph.org/professional/james-a-underwood-E14253), [James R. Rowland](https://www.permitgraph.org/professional/james-r-rowland-M26879), [Jason Ceglia](https://www.permitgraph.org/professional/jason-ceglia-E21184), [Kevin Sorensen](https://www.permitgraph.org/professional/kevin-sorensen-4469), [Pablo Orozco](https://www.permitgraph.org/professional/pablo-orozco-M27485), [Robert J Lara](https://www.permitgraph.org/professional/robert-j-lara-30334), [Steven Terry](https://www.permitgraph.org/professional/steven-terry-C66211), [Thomas Morse](https://www.permitgraph.org/professional/thomas-morse-49457)
- Authorized agents: [Albert Costa](https://www.permitgraph.org/professional/albert-costa-C25678)
- Designers: [Sean Shafer](https://www.permitgraph.org/professional/sean-shafer-1045018)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.