# 923 Folsom St

Block 3753, lot 141. Page: https://www.permitgraph.org/a/3753/141

The city's assessor roll has no record for this parcel.

## Permits filed here

7 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [202412066318](https://www.permitgraph.org/p/202412066318) | Dec 6, 2024 | Completed: final sign-off Jun 2025 | [923 Folsom St](https://www.permitgraph.org/a/3753/141) | [Wfp Construction, Llc](https://www.permitgraph.org/contractor/wfp-construction-llc-1035087) | reset building back to original state for wells fargo atm installed and replace with windows in the same opening to match existing exterior | $10,000 |
| [202001172220](https://www.permitgraph.org/p/202001172220) | Jan 17, 2020 | Completed: final sign-off May 2025 | [923 Folsom St](https://www.permitgraph.org/a/3753/141) | [Rcm Fire Protection Inc.](https://www.permitgraph.org/contractor/rcm-fire-protection-inc-793205) | fire: relocate 1 sprinkler head. ref pa #201907155854. | $1,500 |
| [M1174627](https://www.permitgraph.org/p/M1174627) | Dec 11, 2019 | Never finaled: issued Dec 2019, no final | [923 Folsom St](https://www.permitgraph.org/a/3753/141) |  | street space |  |
| [201907155854](https://www.permitgraph.org/p/201907155854) | Jul 15, 2019 | Completed: final sign-off Apr 2020 | [923 Folsom St](https://www.permitgraph.org/a/3753/141) | [Wfp Construction, Llc](https://www.permitgraph.org/contractor/wfp-construction-llc-1035087) | install 1 (n) atm. to incl conduits, conduits, camera, cat 5, (n) awning, removal of (e) window to fit atm. | $20,000 |
| [M784687](https://www.permitgraph.org/p/M784687) | May 11, 2017 | Never finaled: issued May 2017, no final | [923 Folsom St](https://www.permitgraph.org/a/3753/141) |  | street space. |  |
| [M762228](https://www.permitgraph.org/p/M762228) | Feb 17, 2017 | Never finaled: issued Feb 2017, no final | [923 Folsom St](https://www.permitgraph.org/a/3753/141) |  | street space |  |
| [201702109206](https://www.permitgraph.org/p/201702109206) | Feb 10, 2017 | Completed: final sign-off May 2025 | [923 Folsom St](https://www.permitgraph.org/a/3753/141) | [Cahill Contractors Inc](https://www.permitgraph.org/contractor/cahill-contractors-inc-300647) | roof: revision to 2013-1120-2410 "s" - elevator hoisting smoke detector detail to match what was already on the issued addendum 3 (arch/mep) maher na | $1,000 |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [Wfp Construction, Llc](https://www.permitgraph.org/contractor/wfp-construction-llc-1035087) (2), [Cahill Contractors Inc](https://www.permitgraph.org/contractor/cahill-contractors-inc-300647), [Rcm Fire Protection Inc.](https://www.permitgraph.org/contractor/rcm-fire-protection-inc-793205)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.