# 934 Howard St

Block 3725, lot 014. Page: https://www.permitgraph.org/a/3725/014

- City's use: Commercial Office
- Built: 1924
- Stories: 3
- Building: 10,998 sq ft
- Lot: 3,666 sq ft
- Zoning: MUR
- Construction type: NA

From the assessor's latest secured roll, which can lag recent work.

## Permits filed here

15 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [202405081730](https://www.permitgraph.org/p/202405081730) | May 8, 2024 | In progress: issued May 2024 | [934 Howard St](https://www.permitgraph.org/a/3725/014) | [R B Roofing Co Inc](https://www.permitgraph.org/contractor/r-b-roofing-co-inc-444351) | reroof. (subject to the cool roof program) | $43,500 |
| [201905211289](https://www.permitgraph.org/p/201905211289) | May 21, 2019 | Completed: final sign-off Dec 2021 | [934 Howard St](https://www.permitgraph.org/a/3725/014) | [Swinerton Builders](https://www.permitgraph.org/contractor/swinerton-builders-92) | tie back extending under 934 howard. documentation for tieback encroachment only. n/a for maher. ref. main permit #2019-0521-1281. |  |
| [201812138248](https://www.permitgraph.org/p/201812138248) | Dec 13, 2018 | Completed: final sign-off Jan 2019 | [934 Howard St](https://www.permitgraph.org/a/3725/014) | [Crime Watch Security Sys Llc](https://www.permitgraph.org/contractor/crime-watch-security-sys-llc-808503) | installation of a new fire alarm system with sprinkler monitoring, ref pa# 201708296223, ref sprinkler# 201803163848 | $13,000 |
| [201811065057](https://www.permitgraph.org/p/201811065057) | Nov 6, 2018 | Completed: final sign-off Jan 2019 | [934 Howard St](https://www.permitgraph.org/a/3725/014) | [K Bali Construction](https://www.permitgraph.org/contractor/k-bali-construction-965124) | to obtain final inspection for work approved under pa 2013-0416-4687. all work is complete. |  |
| [201805169313](https://www.permitgraph.org/p/201805169313) | May 16, 2018 | Completed: final sign-off Jan 2019 | [934 Howard St](https://www.permitgraph.org/a/3725/014) | [Stevenson Mechanical Inc](https://www.permitgraph.org/contractor/stevenson-mechanical-inc-783316) | 3 rooftop hvac units, 2 heat pump split systems | $145,000 |
| [201803295012](https://www.permitgraph.org/p/201803295012) | Mar 29, 2018 | Completed: final sign-off Jan 2019 | [934 Howard St](https://www.permitgraph.org/a/3725/014) | [Jalilie Electric Inc /Ridgeway Electric](https://www.permitgraph.org/contractor/jalilie-electric-inc-ridgeway-electric-842195) | install shell lighting and power for future t.i. space in existing building. n/a for maher. | $70,000 |
| [201803163848](https://www.permitgraph.org/p/201803163848) | Mar 16, 2018 | Completed: final sign-off Sep 2018 | [934 Howard St](https://www.permitgraph.org/a/3725/014) | [Freedom Fire Protection Inc.](https://www.permitgraph.org/contractor/freedom-fire-protection-inc-876161) | fire sprinkler system, relocating 2 heads and installing 20 new heads | $7,121 |
| [M900187](https://www.permitgraph.org/p/M900187) | Mar 15, 2018 | Never finaled: issued Mar 2018, no final | [934 Howard St](https://www.permitgraph.org/a/3725/014) |  | street space permit - renewal of permit #201708296223 |  |
| [201708296223](https://www.permitgraph.org/p/201708296223) | Aug 29, 2017 | Completed: final sign-off Jan 2019 | [934 Howard St](https://www.permitgraph.org/a/3725/014) | [K Bali Construction](https://www.permitgraph.org/contractor/k-bali-construction-965124) | base bldg improvement of e 3 story bldg. replace e freight elevator , new accessible passenger elevator, new partitoins for new tenant spaces and monor storefront modification on mary street facade.… | $160,000 |
| [201502037300](https://www.permitgraph.org/p/201502037300) | Feb 3, 2015 | Completed: final sign-off Jun 2015 | [934 Howard St](https://www.permitgraph.org/a/3725/014) | [Doorman Property Management](https://www.permitgraph.org/contractor/doorman-property-management-382267) | tenant improvements at 1st flr only: new accessible break room, new conference room, expansion of accessible bathrooms & shower; new exterior level landing, new signage at restrooms; mechanical, elec… | $10,000 |
| [201307121745](https://www.permitgraph.org/p/201307121745) | Jul 12, 2013 | Completed: final sign-off Jul 2022 | [934 Howard St](https://www.permitgraph.org/a/3725/014) | [International Fire Equip](https://www.permitgraph.org/contractor/international-fire-equip-253912) | fire sprinkler add air cap to drain(basement). 2nd fl partially ofset main and add 5 sprinler heads in showers, 3rd fl add 5 sprinler heads in shower s and 2 in office | $5,000 |
| [201305207393](https://www.permitgraph.org/p/201305207393) | May 20, 2013 | Completed: final sign-off Sep 2013 | [934 Howard St](https://www.permitgraph.org/a/3725/014) | [Remodel 4 Less](https://www.permitgraph.org/contractor/remodel-4-less-929859) | relocation of office functions to ground floor and necessary work to comply with ground floor b occupancy. they include enclosing the stairs, enclosing the freight elevator, provide ada handrails & s… | $8,000 |
| [201304164687](https://www.permitgraph.org/p/201304164687) | Apr 16, 2013 | Never finaled: issued Apr 2013, no final | [934 Howard St](https://www.permitgraph.org/a/3725/014) |  | demolition (interior). existing vacant building. reconfigure non-accessible bathrooms installation of showers. full access compliance will be provided at future tenant improvement permit per sfbc ab-… | $28,000 |
| [M155504](https://www.permitgraph.org/p/M155504) | Mar 13, 2009 | Never finaled: issued Mar 2009, no final | [934 Howard St](https://www.permitgraph.org/a/3725/014) |  | mta pkg (50' - 5 days) |  |
| [200903053444](https://www.permitgraph.org/p/200903053444) | Mar 5, 2009 | Completed: final sign-off Apr 2009 | [934 Howard St](https://www.permitgraph.org/a/3725/014) | [Westech Roofing Co](https://www.permitgraph.org/contractor/westech-roofing-co-641344) | reroofing. | $27,000 |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [K Bali Construction](https://www.permitgraph.org/contractor/k-bali-construction-965124) (2), [Crime Watch Security Sys Llc](https://www.permitgraph.org/contractor/crime-watch-security-sys-llc-808503), [Doorman Property Management](https://www.permitgraph.org/contractor/doorman-property-management-382267), [Freedom Fire Protection Inc.](https://www.permitgraph.org/contractor/freedom-fire-protection-inc-876161), [International Fire Equip](https://www.permitgraph.org/contractor/international-fire-equip-253912), [Jalilie Electric Inc /Ridgeway Electric](https://www.permitgraph.org/contractor/jalilie-electric-inc-ridgeway-electric-842195), [R B Roofing Co Inc](https://www.permitgraph.org/contractor/r-b-roofing-co-inc-444351), [Remodel 4 Less](https://www.permitgraph.org/contractor/remodel-4-less-929859), [Stevenson Mechanical Inc](https://www.permitgraph.org/contractor/stevenson-mechanical-inc-783316), [Swinerton Builders](https://www.permitgraph.org/contractor/swinerton-builders-92), [Westech Roofing Co](https://www.permitgraph.org/contractor/westech-roofing-co-641344)
- Architects: [Steve Suzuki](https://www.permitgraph.org/professional/steve-suzuki-C18661) (2), [Harvey J Hacker](https://www.permitgraph.org/professional/harvey-j-hacker-C8520), [Marc Dimalanta](https://www.permitgraph.org/professional/marc-dimalanta-C33350)
- Engineers: [E.S. Lindquist](https://www.permitgraph.org/professional/e-s-lindquist-C56713)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 22 November 2026.
This is the text of https://www.permitgraph.org/a/3725/014.