# 301 Mission St

Block 3719, lot 385. Page: https://www.permitgraph.org/a/3719/385

- City's use: Single Family Residential
- Built: 2009
- Stories: 1
- Rooms: 2 bedrooms, 3 bathrooms
- Building: 5,096 sq ft
- Zoning: NA
- Construction type: NA

From the assessor's latest secured roll, which can lag recent work.

## Permits filed here

10 permits filed for this property since 2000.

| Permit | Filed | Outcome | Address | Contractor | Work described on the permit | Declared cost |
| --- | --- | --- | --- | --- | --- | --- |
| [201711012832](https://www.permitgraph.org/p/201711012832) | Nov 1, 2017 | Completed: final sign-off Nov 2018 | [301 Mission St](https://www.permitgraph.org/a/3719/385) | [Paul Ryan Associates](https://www.permitgraph.org/contractor/paul-ryan-associates-414867) | removal of existing water feature from the corner of lounge area the perimeter of unit ph2b. new flooring to be installed where water feature is removed. maher na | $17,000 |
| [201407302563](https://www.permitgraph.org/p/201407302563) | Jul 30, 2014 | Completed: final sign-off Oct 2014 | [301 Mission St](https://www.permitgraph.org/a/3719/385) | [Red Hawk Fire & Security Ca Llc](https://www.permitgraph.org/contractor/red-hawk-fire-security-ca-llc-713099) | install 14 notification devices. 1 smoke detector and 2 door holds. 2 dmp with smoke detector for heat pum shutdown. 1 booster power supply for strobes. monitor module to monitor 120 vac smoke/co sen… | $26,000 |
| [201404153223](https://www.permitgraph.org/p/201404153223) | Apr 15, 2014 | Completed: final sign-off Oct 2014 | [301 Mission St](https://www.permitgraph.org/a/3719/385) | [Paul Ryan Associates](https://www.permitgraph.org/contractor/paul-ryan-associates-414867) | the scope of work involves a revision to the fireplace flue penetration at the existing shaft wall. revision to pa#201403241517. n/a ordinance #155-13. |  |
| [201403241517](https://www.permitgraph.org/p/201403241517) | Mar 24, 2014 | Completed: final sign-off Oct 2014 | [301 Mission St](https://www.permitgraph.org/a/3719/385) | [Paul Ryan Associates](https://www.permitgraph.org/contractor/paul-ryan-associates-414867) | revision app. 2013.08.06.3622. updated mechanical drawings & architectural information. the information included revised location and additional informatioa for the heat pumps and revised location of… | $300 |
| [201401297313](https://www.permitgraph.org/p/201401297313) | Jan 29, 2014 | Completed: final sign-off Oct 2014 | [301 Mission St](https://www.permitgraph.org/a/3719/385) | [Pribuss Engineering Inc](https://www.permitgraph.org/contractor/pribuss-engineering-inc-251241) | fire sprinkler t.i. 2013-0419-4987 - relocate & change out 42 sprinkler heads, add 22 sprinkler heads. compliance with ordinance #155-13 not required. total: 64 x 514.62 - 32936. | $32,936 |
| [201312124010](https://www.permitgraph.org/p/201312124010) | Dec 12, 2013 | Completed: final sign-off Nov 2014 | [301 Mission St](https://www.permitgraph.org/a/3719/385) | [Paul Ryan Associates](https://www.permitgraph.org/contractor/paul-ryan-associates-414867) | level ph2 corridor - work includes renovation of common lobby & corridor. new floor & wall finishes & new light fixtures. no work will be done to existing mechanical system, fire & alarm system excep… | $250,000 |
| [201309187118](https://www.permitgraph.org/p/201309187118) | Sep 18, 2013 | Completed: final sign-off Nov 2014 | [301 Mission St](https://www.permitgraph.org/a/3719/385) | [Paul Ryan Associates](https://www.permitgraph.org/contractor/paul-ryan-associates-414867) | ph2b: revision to app#201308063622. to include structural calculations and drawings for a cmu block wall adjacent to a demising wall between the client's residential unit and his neighbor's unit on t… | $2,000 |
| [201308063622](https://www.permitgraph.org/p/201308063622) | Aug 6, 2013 | Completed: final sign-off Oct 2014 | [301 Mission St](https://www.permitgraph.org/a/3719/385) | [Paul Ryan Associates](https://www.permitgraph.org/contractor/paul-ryan-associates-414867) | ph2b-revision to pa #2013.04.19.4987/r-1: additional mechanical & plumbing information is shown in this submittal related to new hot tub per rquirement of bldg management.(entire plan set of pa#2013.… | $20,000 |
| [201304194987](https://www.permitgraph.org/p/201304194987) | Apr 19, 2013 | Completed: final sign-off Oct 2014 | [301 Mission St](https://www.permitgraph.org/a/3719/385) | [Paul Ryan Associates](https://www.permitgraph.org/contractor/paul-ryan-associates-414867) | architectural residential build-out of unit "ph2b" at mullenium tower. contruction of non-structural partitions, finishes, mechanical, elelctrical, telecom, fire sprinkler, fire management and plumbi… | $700,000 |
| [201303222800](https://www.permitgraph.org/p/201303222800) | Mar 22, 2013 | Completed: final sign-off Oct 2014 | [301 Mission St](https://www.permitgraph.org/a/3719/385) | [Paul Ryan Associates](https://www.permitgraph.org/contractor/paul-ryan-associates-414867) | ph2b (millenium tower) - work include the preparation of the shell for the future build-out of interiors. plumbing will be modified & re-routed according to future architectural design. the existing… | $18,000 |

## Who worked here

Everyone with a license on these permits, by role, with how many permits each is on.

- Contractors: [Paul Ryan Associates](https://www.permitgraph.org/contractor/paul-ryan-associates-414867) (8), [Pribuss Engineering Inc](https://www.permitgraph.org/contractor/pribuss-engineering-inc-251241), [Red Hawk Fire & Security Ca Llc](https://www.permitgraph.org/contractor/red-hawk-fire-security-ca-llc-713099)
- Architects: [Ernani Aita-Barea](https://www.permitgraph.org/professional/ernani-aita-barea-C27862) (5)

---
Source: City and County of San Francisco building permit records (DataSF, https://data.sf.gov/), permits filed since 1 January 2000, reloaded nightly. Data as of 23 November 2026.